1. Introduction.

Section 1

2. All Users that connect with and/or utilize the State Grid are required to abide by the principles and procedures as laid down in the Grid Code in so far as they apply to that User.

Section 2

3. The Grid Code shall be enforced by STU. Users must provide STU reasonable rights of access, service and facilities necessary to discharge its responsibilities in the users premises and to comply with instructions as issued by STU to implement and enforce the Grid code.

Section 3

2. SLDC shall bring the non-compliance to the notice of BERC.

Section 2

3. Consistent failure to comply with the Grid Code provisions may lead to disconnection of the User's plant and /or facilities.

Section 3

2. STU shall not be held responsible for any consequences that arise from its reasonable and prudent actions on the basis of such information.

Section 2

2. STU shall not, other than as required by the Grid Code, disclose such information to any person other than Central or State Government and BERC without the prior written consent of the provider of the information.

Section 2

2. In the event of any conflict between any provision of the Grid Code and any contract or agreement between STU and Users, the provision(s) of the Grid Code will prevail.

Section 2

2. Glossary and Definition.

Section 2

3. Management of Grid Code.

Section 3

1. The State Transmission Utility (STU) is required to implement and comply with the Bihar Electricity Grid Code and to carry out periodic review and amendments of the same with the approval of Bihar Electricity Regulatory Commission (BERC). A Review Panel shall be constituted by STU, as required in this Section, comprising of the representatives of the Users of the Transmission System.

Section 1

2. No change in this Grid Code, however small or large, shall be made without being deliberated and agreed by the Grid Code Review Panel and thereafter approved by BERC. However, in an unusual situation where normal day to day operation is not possible without revision of some clauses of Grid Code, a provisional revision may be implemented before approval of BERC is received, but only after discussion at a special Review Panel Meeting convened on emergency basis. BERC should promptly be intimate

Section 2
CHAPTER 2

CHAPTER 2

Section 13

4. System Planning.

Section 4

1. This Section specifies the methods for data submission by Users to STU for planning and development of the State Transmission System. This Section also specifies the procedures to be adopted by STU in the planning and development of the State Transmission System.

Section 1

2. Requirement for reinforcement or extension of the State Transmission system arise due to many reasons of which a few are mentioned below:

Section 2

5. Connection Conditions.

Section 5

1. The User shall meet all necessary conditions as specified in the State Grid Code and submit the application to STU containing all the information as may be specified.

Section 1

2. STU shall make a formal offer within 60 days of the receipt of the application. The offer shall specify and take into account any work required for the extension or reinforcement of the State Transmission System necessitated by the applicant's proposal and for obtaining any consent necessary for the purpose. STU shall process the application in accordance with the CEA Regulations on Grid Connectivity

Section 2

3. If the specified time limit for making the offer against any application is not adequate, STU shall make a preliminary offer within the specified time indicating the extent of further time required for detailed analysis.

Section 3

4. Any offer made by STU shall remain valid for a period of 60 days and unless accepted before the expiry of such period, shall lapse thereafter.

Section 4

5. In the event of offer becoming invalid or not accepted by the applicant, STU shall not be bound to consider any further application from the same applicant within 12 months unless the new application is substantially different from the original application.

Section 5

6. The applicant shall furnish the Detailed Planning Data as per Appendix-B.

Section 6
CHAPTER 3

CHAPTER 3

Section 24

6. Operation Planning.

Section 6

7. Outage Planning.

Section 7

8. Contingency Planning.

Section 8

9. Cross Boundary Safety.

Section 9

10. Operational Event/Accident Reporting.

Section 10
CHAPTER 4

CHAPTER 4

Section 30

11. Scheduling and Despatch.

Section 11

1. SLDC will issue despatch instructions required to regulate all generation and imports from IPPs / CPPs according to the 15-minute day ahead generation schedule. In the absence of any despatch instruction by SLDC, SGS shall generate/ export according to the day ahead generation schedule.

Section 1

2. The SLDC shall regulate the overall State generation in such a manner that generation from following types of power stations shall not be curtailed except under abnormal operating conditions.

Section 2

3. Despatch instructions to SGS shall be in standard format to be finalized by SLDC.

Section 3

4. The algebraic sum of scheduled drawals from ISGS, long term open access, and short term open access arrangements shall be the net drawal schedule for the control area of the utility.

Section 4

12. Frequency and Voltage Management.

Section 12

13. Monitoring of Generation and Drawal.

Section 13
CHAPTER 5

CHAPTER 5

Section 38

14. Protection.

Section 14
CHAPTER 6

CHAPTER 6

Section 40

15. Metering Code.

Section 15
CHAPTER 7

CHAPTER 7

Section 42

16. Data Registration.

Section 16

1. Rated MVA.

Section 1

2. Voltage Ratio.

Section 2

3. Vector Group.

Section 3

4. Positive sequence reactance for maximum, minimum, normal Tap. (% on MVA).

Section 4

5. Positive sequence resistance for maximum, minimum, normal Tap. (% on MVA).

Section 5

6. Zero sequence reactance (% on MVA).

Section 6

7. Tap changer Range (+% to -%) and steps.

Section 7

8. Type of Tap changer, (off/on load).

Section 8

1. Rated voltage (kV).

Section 1

2. Type of circuit breaker (MOCB/ABCB/SF6).

Section 2

3. Rated short circuit breaking current (kA) 3 phase.

Section 3

4. Rated short circuit breaking current (kA) 1 phase.

Section 4

5. Rated short circuit making current (kA) 3 phase.

Section 5

6. Rated short circuit making current (kA) 1 -phase.

Section 6

7. Provisions of auto reclosing with details.

Section 7

1. Busbar.

Section 1

2. Switchgear.

Section 2

3. Transformer bushings.

Section 3

4. Transformer windings.

Section 4

1. Hot

Section 1

2. Warm

Section 2

3. Cold

Section 3

1. Hot

Section 1

2. Warm

Section 2

3. Cold

Section 3

1. Land

Section 1

2. Coal

Section 2

3. Water

Section 3

4. Environmental clearance

Section 4

5. Rehabilitation of displaced persons

Section 5

1. Multipurpose

Section 1

2. For Power

Section 2

1. Area capacity curves and

Section 1

2. Unit capability at different net heads

Section 2

1. Rated MVA

Section 1

2. Voltage Ratio

Section 2

3. Vector Group

Section 3

4. Positive sequence reactance for maximum, minimum and normal Tap.(% on MVA).

Section 4

5. Positive sequence resistance for maximum, minimum and normal Tap.(% on MVA).

Section 5

6. Zero sequence reactance (% on MVA)

Section 6

7. Tap changer range (+% to -%) and steps.

Section 7

8. Type of Tap changer (off/on load).

Section 8

9. Neutral grounding details.

Section 9

1. Rated voltage (KV).

Section 1

2. Type of Breaker (MOCB/ABCB/SF6).

Section 2

3. Rated short circuit breaking current (KA) 3 phase.

Section 3

4. Rated short circuit breaking current (KA) 1 phase.

Section 4

5. Rated short circuit making current (KA) 3 phase.

Section 5

6. Rated short circuit making current (KA) 1 phase.

Section 6

7. Provisions of auto re-closing with details.

Section 7

1. Bus bar.

Section 1

2. Switchgear.

Section 2

3. Transformer Bushings

Section 3

4. Transformer windings.

Section 4

1. Rated terminal voltage (KV).

Section 1

2. Rated MVA.

Section 2

3. Rated MW

Section 3

4. Speed (rpm) or number of poles.

Section 4

5. Inertia constant H (MW sec./MVA).

Section 5

6. Short circuit ratio.

Section 6

7. Direct axis synchronous reactance Xd (% on MVA).

Section 7

8. Direct axis (saturated) transient reactance (% on MVA) X'd.

Section 8

9. Direct axis (saturated) sub-transient reactance (% on MVA) X"d.

Section 9

10. Quadrature axis synchronous reactance (% on MVA) Xq.

Section 10

11. Quadrature axis (saturated) transient reactance (% on MVA) X'q.

Section 11

12. Quadrature axis (saturated) sub-transient reactance (% on MVA) X"q.

Section 12

13. Direct axis transient open circuit time constant (sec) T'do.

Section 13

14. Direct axis sub-transient open circuit time constant (sec) T"do.

Section 14

15. Quadrature axis transient open circuit time content (sec) T'qo.

Section 15

16. Quadrature axis transient open circuit time constant (sec) T"qo.

Section 16

17. Stator Resistance (Ohm) Ra.

Section 17

18. Stator leakage reactance (Ohm) X1.

Section 18

19. Stator time constant (Sec).

Section 19

20. Rated Field current (A).

Section 20

21. Neutral grounding details.

Section 21

22. Open Circuit saturation characteristics of the Generator for various terminal voltages giving the compounding current to achieve this.

Section 22

23. Type of Turbine.

Section 23

24. Operating Head (Metres)

Section 24

25. Discharge with full gate opening (cumecs)

Section 25

26. Speed Rise on total Load throw off(%).

Section 26

27. MW and MVAr Capability curve

Section 27

1. Minimum notice required to Synchronise a Generating Unit from desynchronisation.

Section 1

2. Minimum time between Synchronising different Generating Units in a Power Station.

Section 2

3. Minimum block load requirements on Synchronising.

Section 3

1. Topographical survey

Section 1

2. Geological survey

Section 2

3. Land

Section 3

4. Environmental Clearance

Section 4

5. Rehabilitation of displaced persons.

Section 5

1. Short Circuit studies

Section 1

2. Stability Studies.

Section 2

3. Load Flow Studies.

Section 3

1. Voltage

Section 1

2. No. of circuits

Section 2

3. Point of Connection.

Section 3

1. Name of Sub-station.

Section 1

2. Power Station connected.

Section 2

3. Number and length of circuits.

Section 3

4. Interconnecting transformers.

Section 4

5. Sub-station bus layouts.

Section 5

6. Power transformers.

Section 6

7. Reactive compensation equipment.

Section 7

1. Bus bar layouts.

Section 1

2. Electrical circuitry, lines, cables, transformers, switchgear etc.

Section 2

3. Phasing arrangements.

Section 3

4. Earthing arrangements.

Section 4

5. Switching facilities and interlocking arrangements.

Section 5

6. Operating voltages.

Section 6

7. Numbering and nomenclature:

Section 7

8. Transformers.

Section 8

9. Circuits.

Section 9

10. Circuit breakers.

Section 10

11. Isolating switches.

Section 11

1. Length of line (km).

Section 1

2. Number of circuits.Per Circuit values.

Section 2

3. Operating voltage (KV).

Section 3

4. Positive Phase sequence reactance (pu on 100 MVA) X1

Section 4

5. Positive Phase sequence resistance (pu on 100 MVA) R1

Section 5

6. Positive Phase sequence susceptance (pu on 100 MVA) B1

Section 6

7. Zero Phase sequence reactance (pu on 100 MVA) X0

Section 7

8. Zero Phase sequence resistance (pu on 100 MVA) R0

Section 8

9. Zero Phase sequence susceptance (pu on 100 MVA) B0

Section 9