8.2. Objective.
8.3. Contingency Planning Procedure.
• Partial system black out in the State due to multiple tripping of the Transmission lines emanating from power stations/sub-stations
• Total black out in the State/Region
• Synchronisation of system islands and system split
8.4. Restoration Procedure.
- Total System Black out
- Partial System Blackout
- Synchronisation of System Islands and System Split
8.5. Special Considerations.
Section 8 • Bihar Electricity Grid Code, 2010
8. Contingency Planning.
bihar-electricity-grid-code-2010-sec-8.json
•
Section 8
{
"act_title": "Bihar Electricity Grid Code, 2010",
"act_slug": "bihar-electricity-grid-code-2010",
"section_label": "Section",
"section": {
"number": "8",
"title": "8. Contingency Planning.",
"chapter": null,
"content": "8.2. Objective.\n8.3. Contingency Planning Procedure.\n• Partial system black out in the State due to multiple tripping of the Transmission lines emanating from power stations/sub-stations\n• Total black out in the State/Region\n• Synchronisation of system islands and system split\n8.4. Restoration Procedure.\n- Total System Black out\n- Partial System Blackout\n- Synchronisation of System Islands and System Split\n8.5. Special Considerations.",
"footnote": "",
"is_definition": false,
"sort_order": 26
},
"prev_section": "7",
"next_section": "9"
}