    "section": {
        "number": "8",
        "title": "8. Contingency Planning.",
        "chapter": null,
        "content": "8.2. Objective.\n8.3. Contingency Planning Procedure.\n•  Partial system black out in the State due to multiple tripping of the Transmission lines emanating from power stations/sub-stations\n•  Total black out in the State/Region\n•  Synchronisation of system islands and system split\n8.4. Restoration Procedure.\n- Total System Black out\n- Partial System Blackout\n- Synchronisation of System Islands and System Split\n8.5. Special Considerations.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 26
    },
    "prev_section": "7",