12.2. Objective.
(1) To define the responsibilities of all Users in contributing to frequency and voltage management.
(2) To define the actions required to enable SLDC and STU to maintain the State Transmission System voltages and frequency within acceptable levels in accordance with IEGC guidelines as well as Planning and Security Standards for the State Transmission System specified by the Commission, if any.
12.3. Frequency Management.
12.4. Voltage Management.
Voltage (KV r ms)
Nominal
Maximum
Minimum
400
420
380
220
245
198
132
145
122
Section 12 • Bihar Electricity Grid Code, 2010
12. Frequency and Voltage Management.
bihar-electricity-grid-code-2010-sec-12.json
•
Section 12
{
"act_title": "Bihar Electricity Grid Code, 2010",
"act_slug": "bihar-electricity-grid-code-2010",
"section_label": "Section",
"section": {
"number": "12",
"title": "12. Frequency and Voltage Management.",
"chapter": null,
"content": "12.2. Objective.\n(1) To define the responsibilities of all Users in contributing to frequency and voltage management.\n(2) To define the actions required to enable SLDC and STU to maintain the State Transmission System voltages and frequency within acceptable levels in accordance with IEGC guidelines as well as Planning and Security Standards for the State Transmission System specified by the Commission, if any.\n12.3. Frequency Management.\n12.4. Voltage Management.\nVoltage (KV r ms)\nNominal\nMaximum\nMinimum\n400\n420\n380\n220\n245\n198\n132\n145\n122",
"footnote": "",
"is_definition": false,
"sort_order": 35
},
"prev_section": "4",
"next_section": "13"
}