18. Iron Ore Mining and Ore Processing

A.
Emission Standards for Stack for De-dusing Unit
A.
Emission Standards for Stack for De-dusing Unit
Particulate
matter
100mg/Nm3
Stack
height**
15.0 m
**
Stack height for De-dusting unit shall be calculated as H=74 Q
0.27, where H and Q are stack height in metre and particulate
matter (PM) emission in tonner/hr respectively, i.e.
Q
(kg/hr) Up to 2.71 2.72 – 7.86 7.87 –
17.96 17.97 – 35.29
H(metre) 15 20 25 30
Note:- Stack
attached to De-dusting unit shall have minimum height of 15.0
metres and would be atleast 2.50 metres above the top-most point
of the nearby building/shed or plant in the mine.
Note:-
B.
Fugitive Emission Standards
B.
Fugitive Emission Standards
Particulate
matter
Particulate
matter
1200
µ100mg/Nm3
1200
µ100mg/Nm3
Note:- Fugitive emission shall be monitored in the predominant downwind
direction at a distance0 25.0+2.0 metres from the source of
fugitive emission as per following :
Note:-
Area
Area
Monitoring
location
Monitoring
location
Mine face/Benches
Drilling
excavation and loading applicable for operation benches above
waterable
Haul Roads/Service
Roads
Haul roads to ore
processing plant, waste dumps and loading areas and service road
Crushing plant
Run-off mine
unloading at hopper, crushing areas, screens and transfer points.
Screening Plant
Screens, conveying
and transportation of ore discharge points
Ore Storage and
Loading
Intermediate stock
bin/pile areas ore stock bin/pile areas , wagon/truck loading
areas
Waste dump
Active
waste/reject dumps
C.
Effluent Standards
C.
Effluent Standards
pH
5.5-9.0
Suspended
solids (non-rainy day)
50
mg/l
Suspended
solids (railny day)
100
mg/l
Oil
and grease
10
mg/l
Note:- (I)
All efforts shall be made to reuse and rel-circulate the treated
effluent. (ii) The aforesaid effluent standards shall be
complied with for sewage, service water, beneficiation of ore
washwater and surface run-off put together
Note:-