18. Connection in Un-electrified areas.

(ii) Within three months of notification of these Regulations, the Licensee shall submit the detailed plan for electrification of these areas duly taking into account the number of pending applications for service connections, potential for load growth etc. While submitting the plans for electrification, the Licensee shall ensure that all relevant laws of the land are complied with.
(iii) The Licensee shall electrify such areas as per schedule given in Table 2 below and release new connection to the applicants.
Table 2
Table 2
1.
Un-Electrified Areas Where extension from nearby existing
network is possible
Six months After receipt of deposit of consumers’
share of necessary development charges as specified in these
Regulations to cover the electrification requirement for
supplying electricity to 50% of the prospective consumer base.
2.
Un-Electrified Areas/ Green Field Projects Where new network
is to be laid or grid station needs to be established
Twelve months after receipt of deposit of consumers’
share of necessary development charges as approved by the
Commission under Miscellaneous Charges to cover the
electrification requirement for supplying electricity to 50% of
the prospective consumer base and availability of Right of Way
and land for grid from the revenue authorities, land owning
agencies. Licensee shall apply for land not later than 30 days of
having known of the requirement to such land / revenue agencies
with copy to the Commission