17. Connection where system augmentation is required.

(ii) For connection requiring augmentation of distribution system, the Licensee shall inform the applicant the approximate time frame by which applied load can be energized which shall not exceed the time schedule given in Table 1 below:
Table 1
Table 1
1.
Extension of LT line upto 5 poles
Fifteen days
2.
Electrified Areas where extension of lines or augmentation of
Distribution Transformer is required
Sixty days
3.
Electrified Areas where new Distribution Transformer is
required
One hundred and twenty days
4.
Electrified Areas where existing 11 KV network needs to be
strengthened
One hundred and eighty days
5.
Electrified Areas where existing (66/33 kV grid sub-station
needs to be augmented
Two hundred and forty days