    "act_title": "The Delhi Electricity Supply Code And Performance Standards Regulations, 2007",
    "act_slug": "the-delhi-electricity-supply-code-and-performance-standards-regulations-2007",
    "section_label": "Section",
    "section": {
        "number": "17",
        "title": "17. Connection where system augmentation is required.",
        "chapter": null,
        "content": "(ii) For connection requiring augmentation of distribution system, the Licensee shall inform the applicant the approximate time frame by which applied load can be energized which shall not exceed the time schedule given in Table 1 below:\nTable 1\nTable 1\n1.\nExtension of LT line upto 5 poles\nFifteen days\n2.\nElectrified Areas where extension of lines or augmentation of\n\t\t\t\tDistribution Transformer is required\nSixty days\n3.\nElectrified Areas where new Distribution Transformer is\n\t\t\t\trequired\nOne hundred and twenty days\n4.\nElectrified Areas where existing 11 KV network needs to be\n\t\t\t\tstrengthened\nOne hundred and eighty days\n5.\nElectrified Areas where existing (66/33 kV grid sub-station\n\t\t\t\tneeds to be augmented\nTwo hundred and forty days",
        "footnote": "",
        "is_definition": false,
        "sort_order": 16
    },
    "prev_section": "16",
    "next_section": "18"
}