19. Temporary Supply.

(i) The applicant shall make request for temporary supply in the format prescribed in ANNEXE-II to these Regulations or as approved by the Commission from time to time.
(ii) The Licensee shall issue dated receipt of the request to the applicant. Any deficiencies in the application shall be got corrected immediately at the time of receipt of application. The application shall be considered to be accepted on removal of such deficiencies.
(iii) The Licensee shall examine the technical feasibility of the connection requested for and if found feasible shall sanction the load and raise a demand note in accordance with the provisions of the Regulations within two days of acceptance of application. If the connection is not found technically feasible, it shall intimate to the applicant in writing within three days of acceptance of application giving reason for the same. No connection upto 10 kW shall be rejected on technical grounds.
(iv) The applicant shall make the payment in accordance with the demand note within two days of receipt of demand note failing which the sanction shall stand lapsed. Also Licensee may, at the request of applicant, accept payment at the time of making application which shall be received on account and subject to completion of all commercial formalities.
(v) After payment of applicable charges, the Licensee shall energise the connection in accordance with the date indicated in the application.
(vi) If there are dues on the premises, temporary connection can be refused till the dues are paid by the consumer.
(vii) Temporary connection shall be granted for a period of upto three months at a time, which can be further extend depending upon the requirement.
(viii) The grant of temporary connection does not create a right in favour of the applicant for claiming a permanent connection, which should be governed by Regulation 15 and 16 for providing new connection.
Existing connections