7. Procedure for Modification in Existing Connections.

(a) application format for change in name of registered consumer due to change in ownership/occupancy - Annexure 4;
(b) application format for transfer of ownership to legal heir - Annexure 5;
(c) application format for Conversion of Services / Change of Consumer Category / Shifting of Premises - Annexure 6;
(d) application format for load enhancement/reduction - Annexure 7.
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12 Transfer of Connection (Change of name).
(a) The applicant shall apply for change of consumer's name in the format prescribed in Annexure 4 to these Regulations, along with a copy of the latest bill duly paid. The request for transfer of connection shall not be accepted unless all dues recoverable against the concerned connection are settled. The application form shall be accepted on showing proof of ownership/occupancy of property. A No Objection Certificate from the registered consumer/ authorised person/ previous occupant of the premises shall be required for cases involving transfer of security deposit in the name of applicant. The Distribution Licensee shall process the application form in accordance with clauses 7.6 to 7.11 of these Regulations;
(b) In case the No Objection Certificate from the registered consumer/ authorised person/ previous occupant is not submitted, an application form for change of name shall be entertained only if security deposit as stipulated in these Regulations is paid afresh. However, the original security deposit shall be refunded to the claimant as and when a claim is preferred by the concerned person;
(c) Change of consumer's name shall be effected within thirty (30) days from receipt of complete application along with payment of necessary charges, if any.
(a) The applicant shall apply for change of consumer's name in the format prescribed in Annexure 5 to these Regulations, along with a copy of the latest bill duly paid. The application form shall be accepted on showing the Registered Will/deed, Succession/Legal heir Certificate, Mutation in municipal/land records or any other proof of legal heirship. The Distribution Licensee shall process the application form in accordance with clauses 7.6 to 7.11 of these Regulations;
(b) Change of consumer's name shall be effected within thirty (30) days from receipt of complete application along with payment of necessary charges, if any;
(c) Any charge for electricity or any sum other than charge for electricity as due and payable to licensee which remains unpaid by a deceased consumer or the erstwhile owner/occupier of any land/premises as the case may be, shall be a charge on the premise transmitted to the legal representative/ successors-in-law or transferred to the new owner of the premise as the case may be, and same shall be recoverable by the Distribution Licensee as due from such legal representative or successor-in-law or new owner/occupier of the premises as the case may be.
7.13 Conversion of Services.
7.14 Shifting of Meter / Existing Connection.
7.15 Reclassification of Consumer Category.
7.16 Load Enhancement.
(a) whether the additional power can be supplied at existing voltage or at a higher voltage;
(b) addition or alterations, if any, required to be made to the system and the cost to be borne by the consumer;
(c) amount of additional security deposit, cost of additional infrastructure and the system strengthening charges or capacity building charges, if any, to be deposited; and
(d) change in classification of the consumer and applicability of tariff, if required.
(a) pay additional security deposit, cost of addition or alteration required to be made to the system, if any, and system strengthening charges/capacity building charges, if any, within fifteen (15) days of receipt of the demand note; and
(b) execute a revised Agreement.
7.17 Load Reduction.
(a) details of alteration/modification/removal of electrical installation with work completion certificate and test report from a Licensed Electrical Contractor where alteration of installation is involved;
(b) any other reason(s) for reduction of contract demand;
(c) Details of generator, if any, installed by the consumer with safety clearance certificate form competent authority as applicable.
7.18 Annual Review of Contract Demand.