← Back to Directory
Chhattisgarh State Electricity Supply Code, 2011
Chhattisgarh State Electricity Supply Code, 2011
Sections
1. If main meter is stopped and check meter is found working, billing to be done as per check meter.
Section 12. If both meters found working and consumption difference between these two meters is within the permissible limit, billing be done as per consumption recorded by main meter.
Section 23. If both meters found working but consumption difference between these two meters is more than permissible limit, both meters to be tested and billing be done on the basis of consumption recorded by main meter considering its percentage error.
Section 31. On the basis of average of previous 3 months consumption if meter is found functioning correctly during such 3 months period and consumption is found uniform.
Section 12. On the basis of average of last 1 year consumption if meter is found functioning correctly during last one year and there is appreciable fluctuation in consumption.
Section 23. On the basis of consumption of corresponding month of previous . years-in case consumption found varying based on season and the meter is found functioning correctly during corresponding month of previous year.
Section 34. In case the meter became stop/defective from the date of connection or reliable consumption of sufficient period after connection is not available then average consumption of subsequent three billing month/ billing cycle period after installation of good meter, may be considered.
Section 45. In case of 3 phase 4 wire LT meter for balanced load if during checking/testing meter is not found functioning in 1 phase and found functioning properly in other 2 phases then recorded consumption and demand be multiplied by 1.5 i.e. 50% additional to be billed based on recorded demand and consumption corresponding for two phases.
Section 56. If during checking/testing 3 phase 4 wire LT meter for balanced load is not found working properly in 2 phases but found working properly in third phase, the recorded demand and consumption be multiplied by 3 i.e. two times additional demand and consumption to be billed, corresponding to recorded demand and consumption of one phase.
Section 67. If proper recorded data is available in memory of electronic meter through MRI/AMR, billing to decide based on available data, after computation.
Section 78. Meter to be tested, percentage error to be found out and billing be done based on percentage error arrived during testing.
Section 89. To substantiate the assessment wherever required licensee may consider other basis such as connected load, working hour and load factor, consumption of similar type of other connection, production data of industries approved by excise department etc.
Section 91. Industrial Service
Section 12. Commercial Service
Section 23. Agricultural Service
Section 34. Other Service Four
Section 41. Chhattisgarh State Electricity Supply Code, 2007
Section 12. Chhattisgarh State Electricity Regulatory Commission (Security Deposit) Regulations, 2005
Section 23. Chhattisgarh State Electricity Regulatory Commission (Procedure for Filing Appeal Before the Appellate Authority) Regulations, 2005
Section 31. In case of a partnership firm - The applicant shall furnish the partnership deed and an authorization in the name of the applicant for signing the requisition form and agreement.
Section 12. In case of public and/or private limited company - the applicant shall furnish a Memorandum and Articles of Association and Certificate of Incorporation alongwith an authorization in the name of the applicant for signing the requisition form and agreement.
Section 23. Other documents applicable only for select consumer categories :
Section 31. Proof of ownership of the premises:
Section 12. A map indicating the proposed location of the plant/office duly marked the area by red ink where supply is to be utilized and the point where supply is required. MoP should normally be scale of I Cm representing 1200 Cm.
Section 23. Licence/NOC from statutory authority, if required or a declaration by the applicant that his connection does not fall under the requirement of NOC under any statute.
Section 34. In case of a proprietary firm, an affidavit to be submitted stating that the applicant is the sole proprietor of the firm.
Section 45. In case of partnership firm, partnership deed.
Section 56. In case of Limited Company, Memorandum and Articles of Association and Certificate of Incorporation.
Section 67. Proof of permanent residential address of the consumer and PAN Number, if any. If there is any change at a later date, the same shall be intimated by the consumer to the licensee immediately.
Section 78. Letter of intent for production/enhancement in production may be furnished.
Section 89. List of equipments proposed to be installed alongwith the expected load.
Section 910. Resolution for authorized signatory.
Section 1011. Registration from Industries Department.
Section 1112. Extract of project report relevant to power and process requirements (in case of industries).
Section 1213. Copy of the relevant section of the current tariff order that provides details of the tariff category opted by the consumer and duly signed by him. This will be appended with the agreement after completion of formalities.
Section 131. Copy of latest bill duly paid
Section 12. Proof of ownership/legal occupancy of premises
Section 23. No objection certificate from the existing consumer if available/possible
Section 34. Registered deed/Succession or legal heir certificate/Mutation deed/.....................
Section 45. NOC from other legal heir(s) in case connection is to be changed in the name of one of the legal heirs.
Section 51. A work completion certificate & test report from Licensed Electrical Contractor, if the consumer's installation has been altered.
Section 12. Resolution for authorized signatory.
Section 21. Site verification report
Section 12. Comments of concerned official
Section 21. For better result capacitors be installed at the terminal of individual motors matching to its capacity so that capacitors may be switched on/switched off alongwith the motor with supply.
Section 12. In case common capacitor is installed at one point for number of small motors, capacitor shall be switched off when there is only light and fan load in circuit or else it may affect the average monthly power factor due to over compensation during no load or less load period.
Section 2
chhattisgarh-state-electricity-supply-code-2011.json
•
46 Sections
•
Chhattisgarh
{
"id": 16052,
"slug": "chhattisgarh-state-electricity-supply-code-2011",
"title": "Chhattisgarh State Electricity Supply Code, 2011",
"short_title": "Chhattisgarh State Electricity Supply Code, 2011",
"act_number": "Published vide Notification No. 39/CSERC/2011, dat",
"act_year": 2011,
"act_type": "STATE",
"location": "Chhattisgarh",
"law_status": "unknown",
"enactment_date": null,
"description": "Chhattisgarh State Electricity Supply Code, 2011",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. If main meter is stopped and check meter is found working, billing to be done as per check meter.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 0
},
{
"number": "2",
"title": "2. If both meters found working and consumption difference between these two meters is within the permissible limit, billing be done as per consumption recorded by main meter.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 1
},
{
"number": "3",
"title": "3. If both meters found working but consumption difference between these two meters is more than permissible limit, both meters to be tested and billing be done on the basis of consumption recorded by main meter considering its percentage error.",
"chapter": null,
"content": "(B). When only main meter is installed the consumption of previous three years period or from the date of connection whichever is less need to be reviewed to know the trend of consumption and to arrive the conclusion about the month from which meter became defective. Any of the following method or its combination can be adopted to arrive to reasonable assessment of energy consumed during the period meter remained stop/defective.",
"footnote": "",
"is_definition": false,
"sort_order": 2
},
{
"number": "1",
"title": "1. On the basis of average of previous 3 months consumption if meter is found functioning correctly during such 3 months period and consumption is found uniform.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "2",
"title": "2. On the basis of average of last 1 year consumption if meter is found functioning correctly during last one year and there is appreciable fluctuation in consumption.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "3",
"title": "3. On the basis of consumption of corresponding month of previous . years-in case consumption found varying based on season and the meter is found functioning correctly during corresponding month of previous year.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "4",
"title": "4. In case the meter became stop/defective from the date of connection or reliable consumption of sufficient period after connection is not available then average consumption of subsequent three billing month/ billing cycle period after installation of good meter, may be considered.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "5",
"title": "5. In case of 3 phase 4 wire LT meter for balanced load if during checking/testing meter is not found functioning in 1 phase and found functioning properly in other 2 phases then recorded consumption and demand be multiplied by 1.5 i.e. 50% additional to be billed based on recorded demand and consumption corresponding for two phases.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 7
},
{
"number": "6",
"title": "6. If during checking/testing 3 phase 4 wire LT meter for balanced load is not found working properly in 2 phases but found working properly in third phase, the recorded demand and consumption be multiplied by 3 i.e. two times additional demand and consumption to be billed, corresponding to recorded demand and consumption of one phase.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
{
"number": "7",
"title": "7. If proper recorded data is available in memory of electronic meter through MRI/AMR, billing to decide based on available data, after computation.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 9
},
{
"number": "8",
"title": "8. Meter to be tested, percentage error to be found out and billing be done based on percentage error arrived during testing.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 10
},
{
"number": "9",
"title": "9. To substantiate the assessment wherever required licensee may consider other basis such as connected load, working hour and load factor, consumption of similar type of other connection, production data of industries approved by excise department etc.",
"chapter": null,
"content": "Contents of the Energy Bill:\n(a) Service Connection Number (unique consumer number as per clause 9.9)\n(b) Bill number\n(c) Period of bill\n(d) Name and address of the consumer\n(e) Pole Number from which connection is served\n(f) Name, address and telephone number of the distribution centre\n(g) Date of issue of bill\n(h) Tariff category\n(i) Tariff, rate of electricity duty and cess as applicable (j) Contracted/Connected load/ demand\n(k) Single phase or three phase connection\n(I) Identification details of the meter\n(m) Reading date-past and present\n(n) Meter reading-past and present\n(o) Units assessed/consumed\n(p) Credit\n(q) Basis of bill\n(r) Meter rental\n(s) Current month's charges-Energy Charges, fixed/demand charge, Minimum Charges, Variable Cost Adjustment (VCA) Charges, Electricity Duty, Cess, meter rent, welding/capacitor surcharge, security deposit instalment, Rebate allowed, others if any\n(t) Arrear of Electricity Charges, Delayed Payment Surcharge arrears\n(u) Bill delivery charges if applicable\n(v) Total charges\n(w) Delayed payment surcharge\n(x) Due dates of payment-for payment through cheque and cash\n(y) Authority in whose favour cheque/Bank draft is to be issued. (To be printed on reverse of the bill)\n(z) Security deposit held and required\n(aa) Confirmation of last payment received-amount and date of payment.\n(a) The name(s)/address(es) of collection centres.\n(b) Working hours for collection of bills.\n(c) Designation and address of the authority of licensee with whom grievance pertaining to bills, meter, meter reading etc. can be lodged address, phone number of Forum and Electricity Ombudsman.\n(d) Any other message that the Licensee may like to give e.g. requesting the consumer to indicate their phone/mobile number, if available, on the portion of the bill retained by the licensee on receipt of payment. This information can be used for better communication with consumers.\nSupplementary (other than regular) bill:\nChapter 10\nPayment of Bill; Temporary and Permanent Disconnection of Supply\n10.1 Payment of bill.\n(a) Electricity Duty and Cess on the current consumption\n(b) Arrears of Electricity Duty plus arrears of Cess, if any\n(c) Delayed payment surcharge\n(d) Balance of arrears, if any\n(e) Current bill amount\nInstalment facilities.\nDisputed/Erroneous monthly bills :\n(i) an amount equal to the sum claimed from him, or\n(ii) the electricity charges due from him for each month calculated on the basis of average charge for electricity paid by him during the preceding six months,\n(b) A complaint may be lodged with the designated officer in the complaint form available at the licensee's complaint receiving office. In case such form is not available in the office, complaint may be lodged on plain paper along with the following details :\n(i) Name and address of the consumer alongwith telephone number/ mobile no, if any\n(ii) Service connection number\n(iii) Category/purpose of connection\n(iv) Details of complaint in brief.\n(c) If on investigation, the licensee finds the bill to be erroneous, a revised corrected bill shall be furnished to the consumer indicating the revised due date not less than seven days from the date of delivery of revised bill. Excess amount found paid by the consumer, if any, shall be adjusted in the subsequent bill(s).\n(d) In the event if it is established that the original bill was correct, the consumer shall be informed accordingly and notified to pay the balance, if any, with surcharge as applicable within 7 days.\n(e) In case the consumer is not satisfied with the decision on the dispute, he may take further action as provided in the relevant regulation for Redressal of Consumer Grievance.\nResponsibility of legal heir:\nTemporary Disconnection:\nTemporary disconnection on request of consumer:\nPermanent disconnection and termination of agreement:\nUnconnected LT industrial and HT connections :\nFor LT industries up to 50 HP\n-\n10 HP\nFor LT industries more than 50 HP\n-\n20 HP\nFor HT connection 33 and 11KV\n-\n60 KVA\nDisconnected LT industries and HT consumers :\nFor LT industries up to 50 HP\n-\n10 HP\nFor LT industries more than 50 HP\n-\n20 HP\nFor HT connection 33 and 11KV\n-\n60 KVA\nChapter 11\nPrejudicial use of Supply\n11.1\nAccess to consumer premises:\nUnauthorized use of electricity :\n(i) by any artificial means; or\n(ii) by a means not authorised by the concerned person or authority or licensee; or\n(iii) through a tampered meter; or\n(iv) for a purpose other than for which the usage of electricity has been authorized;\n(a) Use of electricity in the premises or areas other than those for which the supply of electricity was authorised; or\n(b) shifting of location of meter.\nAssessment:\nProvisional and final assessment:\n(i)\nOfficers of rank of Asstt. Engineer\n-\nFor all LT connections up to 15KW\n(ii)\nOfficers of rank of Executive Engineer\n-\nFor all LT connections more than 15KW\n(iii)\nOfficers of rank of Superintending Engineer and\n\t\t\t\tabove.\n-\nFor all HT & EHT connection :\nAppeal against final assessment:\n(i)\nNext immediate officer-Executive Engineer\n-\nFor all LT connection up to 15KW\n(ii)\nNext immediate officer-Superintending Engineer\n-\nFor all LT connection above 15KW\n(iii)\nNext immediate officer-Chief Engineer\n-\nfor HT & EHT consumer.\nMaximum demand exceeding of contract demand/load found increased:\nTheft of Electricity:\n(i) taps, makes or causes to be made any connection with overhead, underground or underwater lines or cables, or service wires or service facilities of a licensee or supplier, as the case may be; or\n(ii) tampers a meter, installs or uses a tampered meter, current reversing transformer, loop connection or any other device or method, which interferes with accurate or proper registration, calibration or metering of electric current or otherwise results in a manner whereby electricity is stolen or wasted; or\n(iii) damages or destroys an electric meter, apparatus, equipment, or wire or causes or allows any of them to be so damaged or destroyed as to interfere with proper or accurate metering of electricity, so as to abstract or consume or use electricity; or\n(iv) uses electricity through a tampered meter; or\n(v) uses electricity for the purpose other than for which the usage of electricity was authorised;\nshall be punishable under the provision of section 135 of the Act.\nPeriod of Assessment:\n(1) Actual period from the date of commencement of supply to the date of detection of theft;\n(2) Actual period from the date of replacement of component of metering system in which the evidence is detected to the date of detection of theft;\n(3) Actual period from the date of previous checking of installation to date of detection of theft;\n(4) Meter Reading Instrument (MRI) data should be considered wherever available.\nResponsibility on consumer to prove otherwise:\nThe methodology for assessment of consumption in case of theft of energy :\n(A) In respect of existing connection:\nUnits assessed = L X D X H X F Where\nL = Load (connected load found in the consumer's premises during the course of inspection in KW.\nD = Period of assessment in days:\nH = is hours of use per day,\nF = Load factor, which shall be taken for different categories of use as given below :-\nS. No.\nParticulars\nLoad factor\n1.\nHT industries\n100%\n2.\nHT connection other than industries (Residential, General\n\t\t\t\tpurpose) water work\n75%\n3.\nLT Industry\n75%\n4.\nLT Non domestic and Agriculture allied\n50%\n5.\nLT Domestic\n40%\n6.\nLT Agriculture\n50%\n7.\nLT Water supply\n50%\n8.\nStreet light\n50%\n9.\nDirect theft-AU categories (without availing connection)\n100%\nH = 8 hours all consumers (other than domestic and street light)\n6 hours for domestic\n12 hours for street light\nFor industries period of working to be decided based on its normal functioning but shall not be less than 8 hours.\n(B) Assessment of energy in case of direct theft (without availing) connection :\nUnits assessed = L x D x FI\nWhere,\nL = Load (found connected at the time of inspection) in KW\nD= Period of assessment in days; and\nH= is hours per day, which shall be taken as 8 hours for all consumers except industrial consumers in respect of whom the hours of use shall be as per the hours the industry generally operates in a day which in any case shall not be less than 8 hours.\nTheft of electricity in premises having no connection (direct hooking):\nProcedure in case of suspected theft:\nAbetment:\nCompounding of offences:\nNature of Service\nRate at which the sum of money for compounding to be collected\n\t\t\t\tper Kilowatt (KW)/Horse Power (HP) or part thereof for Low\n\t\t\t\tTension (LT) supply and per Kilo Volt Ampere (KVA) of contracted\n\t\t\t\tdemand for High Tension (IIT)/ Extra High Tension (EHT).",
"footnote": "",
"is_definition": false,
"sort_order": 11
},
{
"number": "1",
"title": "1. Industrial Service",
"chapter": null,
"content": "Twenty thousand rupees;",
"footnote": "",
"is_definition": false,
"sort_order": 12
},
{
"number": "2",
"title": "2. Commercial Service",
"chapter": null,
"content": "Ten thousand rupees;",
"footnote": "",
"is_definition": false,
"sort_order": 13
},
{
"number": "3",
"title": "3. Agricultural Service",
"chapter": null,
"content": "Two thousand rupees;",
"footnote": "",
"is_definition": false,
"sort_order": 14
},
{
"number": "4",
"title": "4. Other Service Four",
"chapter": null,
"content": "thousand rupees;\nPreventive measures to control theft of electricity:\nChapter 12\nGenerator Connectivity with the Grid\n12.1 Generator in consumer's installation.\nConnectivity with the grid:\nStart-up power by generator :\nReduction of contract demand by prospective captive and non-captive consumer :\nMetering at interface point:\nAssessment in case of defective meters:\nChapter 13\nMiscellaneous\n13.1 Force Majeure.\n(a) Acts of God, natural phenomena, including but not limited to floods, droughts, earthquakes and epidemics;\n(b) Acts of any Government domestic or foreign, including but not limited to war declared or undeclared, hostilities, priorities, quarantines, embargoes;\n(c) Riot or civil commotion;\n(d) Grid's failure not attributable to agencies involved.\n(a) Energy charges shall be on the basis of actual meter reading recorded in the energy meter.\n(b) Other charges (excluding electricity duty and cess) shall be prorated on the basis of the number of days power was provided to the consumer.\nDamage to electrical plant, lines or meter:\nClearance from electric lines (clause 63 of CEA Safety Regulation):\nAuthorisation of Franchisees:\nDistribution in SEZ area:\nService of Notice:\n(a) The officer authorized or designated by the distribution licensee for HT and EHT consumer.\n(b) The licensee's Executive Engineer or person holding an equivalent post of the area or his authorised representative in the case of L.T. consumers.\nUnforeseen Circumstances:\nInterpretation :\nRepeal:",
"footnote": "",
"is_definition": false,
"sort_order": 15
},
{
"number": "1",
"title": "1. Chhattisgarh State Electricity Supply Code, 2007",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 16
},
{
"number": "2",
"title": "2. Chhattisgarh State Electricity Regulatory Commission (Security Deposit) Regulations, 2005",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 17
},
{
"number": "3",
"title": "3. Chhattisgarh State Electricity Regulatory Commission (Procedure for Filing Appeal Before the Appellate Authority) Regulations, 2005",
"chapter": null,
"content": "Power to remove difficulties :\nJurisdiction of Court:\nSavings:\nPower to amend.\nPower to relaxation.\nNote. - In case of any difference/dispute in the interpretation or understanding of the provisions of the Hindi version of this Supply Code with that of the English version (the original version), the latter will prevail and in case of any dispute in this regard, the decision of the Commission shall be final and binding.\nNote.\nAnnexure-1\nAnnexure-1\nApplication Form - for new Low Tension Connection\nApplication Form - for new Low Tension Connection\n(Please strike-off of purpose that is not applicable)\n1\nName of the Applicant/Organization:\n2\nName of father/husband/Director/ Partner/\n\t\t\t\tTrustee:\n3(a)\nPostal Address for communication\nHouse/Plot/Premise\n\t\t\t\tno.\nStreet\nArea/Colony\nTown/City/Village\nDistrict\nMobile No\n\t\t\t\t….............................\nE-mail:\n\t\t\t\t…..........................................\n(b)\nLocation where the\n\t\t\t\tnew connection is applied for\n(indicate any landmarks to-identify the\n\t\t\t\tlocation)\nHouse/Plot/Premise\n\t\t\t\tno.\nStreet\nArea/Colony\nDistrict\n4\nPlot size :\n\t\t\t\t…....................................sq. feet\nCovered area : …........................sq.\n\t\t\t\tfeet\n5\nCategory of Supply: (list of categories\n\t\t\t\tattached)\n6\nPurpose of Supply :\n7\nTotal Load applied for (in kW)/HP:\n8\nType of Supply (Permanent/Temporary):\n8(a)\nIf Temporary supply, specify period of\n\t\t\t\trequirement :\nFrom (date):\nTo (date):\n9\nPlease indicate whether you want to carry out\n\t\t\t\tthe works of laying service line and/or dedicated distribution\n\t\t\t\tfacility for the electricity supply requisitioned (Yes/No)\n10.\nPlease indicate whether you want to install your\n\t\t\t\town CEA approved meter (Yes/No)\n11\nList of documents attached:\n(a)\nPhotograph to be affixed on application form\n\t\t\t\t(Yes/No)\n(b)\nIdentity Proof submitted alongwith this\n\t\t\t\tapplication form:\nIf applicant is\n\t\t\t\t\ta person\n(Tick any one)\n(i) Electoral\n\t\t\t\tidentity card;\n(ii)Passport\n(iii) Driving\n\t\t\t\tLicense;\n(iv) Ration Card;\n(v) Photo identity\n\t\t\t\tcard issued by Government agency;\n(vi) PAN card;\n(vii) Certificate from village Pradhan/Patwari\nIf Applicant is\n\t\t\t\t\tan organization\n(Tick any one)\nSignature of competent authority alongwith\n\t\t\t\trelevant resolution/ authority letter of the institution\n\t\t\t\tconcerned\n(c)\nProof of legal occupancy of premises for which\n\t\t\t\telectricity connection is required alongwith a copy of map of\n\t\t\t\tpremise/land indicating proposed point of supply (Tick any\n\t\t\t\tone)\n(i) Copy of\n\t\t\t\tRegistered sale deed/lease deed/ partition deed, succession or\n\t\t\t\theirship certificate or deed of last will/certificate from\n\t\t\t\tSarpanch/ Patwari, payment of property tax or in the case of\n\t\t\t\tagriculture connection a copy of khasra/khatauni/khata nakal\n\t\t\t\talongwith location of water source.\n(ii) Registered\n\t\t\t\tGeneral Power of Attorney;\n(iii) Municipal tax\n\t\t\t\treceipt or Demand notice or other related document;\n(iv) Letter of\n\t\t\t\tallotment issued by competent authority\n(v) An applicant who is not an owner but an\n\t\t\t\toccupier of the premises shall alongwith any one of the documents\n\t\t\t\tlisted at (i) to (iv) above also furnish a no objection\n\t\t\t\tcertificate from owner of the premises.\n(d)\nProof of current\n\t\t\t\taddress\n(Tick any one)\n(i) Electoral\n\t\t\t\tidentity card;\n(ii) Passport;\n(iii) Driving\n\t\t\t\tlicense;\n(iv) Ration card;\n(v) Photo identity\n\t\t\t\tcard issued by any Government agency;\n(vi) Statement of\n\t\t\t\trunning Bank Account;\n(vii) Water/Telephone/ Electricity/ Gas\n\t\t\t\tConnection Bill;\n(viii) Income Tax assessment order.\n(e)\nAny other document as applicable (Please\n\t\t\t\tspecify)\n12\nAny electricity dues outstanding in licensee's\n\t\t\t\tarea of operation in consumer's name: Yes/No\n13\nAny electricity dues outstanding for the\n\t\t\t\tpremises for which connection applied for: Yes/No\n14\nAny electricity dues outstanding with the\n\t\t\t\tlicensee against any firm with which the consumer is associated\n\t\t\t\tas an Owner, Partner, Director or Managing Director: Yes/No\n(For questions 13,14 & 15 if the answer\n\t\t\t\tis ' Yes' in any case please provide details on a separate sheet)\n(a) The information provided in this application is true to my knowledge.\n(b) I/We have read the Chhattisgarh Electricity Supply Code and agree to abide by the conditions mentioned therein.\n(c) I/We will deposit electricity dues, every month, as per the applicable electricity tariff and other charges.\n(d) I/We own the responsibility of security and safety of the meter, cut-out and the installation thereafter.\nDate:\nSignature of the consumer/Authorized Signatory\nPlace:\nName:\nDesignation:\nNote. - Apart from documents for identify proof, proof of ownership/occupancy of premises and proof of current address, the following documents shall be attached with the application form -\nNote.",
"footnote": "",
"is_definition": false,
"sort_order": 18
},
{
"number": "1",
"title": "1. In case of a partnership firm - The applicant shall furnish the partnership deed and an authorization in the name of the applicant for signing the requisition form and agreement.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 19
},
{
"number": "2",
"title": "2. In case of public and/or private limited company - the applicant shall furnish a Memorandum and Articles of Association and Certificate of Incorporation alongwith an authorization in the name of the applicant for signing the requisition form and agreement.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 20
},
{
"number": "3",
"title": "3. Other documents applicable only for select consumer categories :",
"chapter": null,
"content": "(a) Industrial consumers: Valid industrial license, NOC from Pollution Control Board if applicable. (b) Agriculture consumer: No Objection Certificate from competent government authority, if source of water is river, tank, canal etc. (c) For Temporary Structure: No Objection Certificate allotment order from the Nagar Nigam/Nagar Palika/Nagar Panchayat/Gram Sabha/Gram Panchayat/ Land Development Authority/Land Owning Agency. (d) Approval/permission of local authority if required under any law/statue. Acknowledgement Application of...........................(name of applicant) for................................................ (purpose) is hereby received on...............(date). In the regard, the applicant is given a reference no..............to be used for all future correspondence. Signature /Seal of licensee's representative Name and Designation : Annexure-2 Application form - for new High Tension / Extra High Tension connection (please strike-off the purpose which is not applicable) 1 Name of the Applicant/Organization 2 Name of Father/Husband/Director/ Partner/ Trustee: 3 Postal Address for communication with Telephone Nos. and E-mail\n\t\t\t\taddress. 4 Address where the new connection is applied for (Indicate landmarks to identify the location) 5 Voltage at which supply is required (kV) (Please tick the category applicable) 11KV 33KV 66KV 110KV 132KV 220KV 6 Type of Supply (Permanent/Temporary): 6(a) If Temporary supply, specify period of requirement: From (date): To (date): 7 Total Contract Demand applied for kVA: 8 Basis for projection of Contract Demand-Diversity Factor assumed: 9 Phasing of Contract Demand required (Yes/No): If Yes, then provide the following details in the given format: CD required (kVA) alongwith remarks, if any Tentative Date from which required (a) (b) (c) 10 Purpose of connection 11 Category of Tariff opted for 12 Production capacity 13 Category of Industry: (Tick the applicable one) SSI MSI LSI Type of unit: (viz. Ownership/Partnership/Private Ltd./Public Ltd./Society/\n\t\t\t\tGovt. Dept./Govt undertaking) 14 Name of Institution developing Industrial Premises: if any 15(a) Possession Letter or No-Objection Certificate attached Yes / No 15(b) Issued by the Institution (attach a copy) Number: Date: 16 Whether supply is needed through an independent feeder Yes / No 17 Whether the above unit ever operated at some other place or\n\t\t\t\tapplied for connection? (if Yes, please provide details) (a) Sanctioned Load: (b) Service Connection No. (c) Arrears of payment (if any): 18 If electricity connection for the premises was requested in the\n\t\t\t\tpast? (If Yes, please provide details) (a) Name of unit: (b) Service Connection No: (c) Arrears of payment (if any): 19 Status of land acquisition 20 Expected date by which finance will be available 21 Whether the requisite consent/NOC (if applicable as per the list\n\t\t\t\tof Pollution Control Board) has been obtained as per statutory\n\t\t\t\trequirements (If yes, attach a copy) 22 Any electricity dues outstanding in licensee's area of operation\n\t\t\t\tin consumer's name: Yes / No 23 Any electricity dues outstanding for the premises for which\n\t\t\t\tconnection applied for: Yes/No 24 Any electricity dues outstanding with the licensee against any\n\t\t\t\tfirm with which the consumer is associated as an Owner, Partner,\n\t\t\t\tDirector or Managing Director: Yes / No (For questions 22, 23 & 24 if the answer is 'Yes' ) 25 Please indicate whether you want to carry out work of laying of\n\t\t\t\tline. Yes / No\n(a) Industrial consumers: Valid industrial license, NOC from Pollution Control Board if applicable.\n(b) Agriculture consumer: No Objection Certificate from competent government authority, if source of water is river, tank, canal etc. (c) For Temporary Structure: No Objection Certificate allotment order from the Nagar Nigam/Nagar Palika/Nagar Panchayat/Gram Sabha/Gram Panchayat/ Land Development Authority/Land Owning Agency. (d) Approval/permission of local authority if required under any law/statue. Acknowledgement Application of...........................(name of applicant) for................................................ (purpose) is hereby received on...............(date). In the regard, the applicant is given a reference no..............to be used for all future correspondence. Signature /Seal of licensee's representative Name and Designation :\n(b) Agriculture consumer: No Objection Certificate from competent government authority, if source of water is river, tank, canal etc.\n(c) For Temporary Structure: No Objection Certificate allotment order from the Nagar Nigam/Nagar Palika/Nagar Panchayat/Gram Sabha/Gram Panchayat/ Land Development Authority/Land Owning Agency. (d) Approval/permission of local authority if required under any law/statue. Acknowledgement Application of...........................(name of applicant) for................................................ (purpose) is hereby received on...............(date). In the regard, the applicant is given a reference no..............to be used for all future correspondence. Signature /Seal of licensee's representative\n(c) For Temporary Structure: No Objection Certificate allotment order from the Nagar Nigam/Nagar Palika/Nagar Panchayat/Gram Sabha/Gram Panchayat/ Land Development Authority/Land Owning Agency.\n(d) Approval/permission of local authority if required under any law/statue. Acknowledgement Application of...........................(name of applicant) for................................................ (purpose) is hereby received on...............(date). In the regard, the applicant is given a reference no..............to be used for all future correspondence.\n(d) Approval/permission of local authority if required under any law/statue.\nAcknowledgement\nAcknowledgement\nAnnexure-2\nAnnexure-2\nApplication form - for new High Tension / Extra High Tension connection\nApplication form - for new High Tension / Extra High Tension connection\n(please strike-off the purpose which is not applicable)\n1\nName of the Applicant/Organization\n2\nName of Father/Husband/Director/ Partner/ Trustee:\n3\nPostal Address for communication with Telephone Nos. and E-mail\n\t\t\t\taddress.\n4\nAddress where the new connection is applied for\n(Indicate landmarks to identify the location)\n5\nVoltage at which supply is required (kV)\n(Please tick the category applicable)\n11KV 33KV 66KV\n110KV 132KV 220KV\n6\nType of Supply (Permanent/Temporary):\n6(a)\nIf Temporary supply, specify period of requirement:\nFrom (date):\nTo (date):\n7\nTotal Contract Demand applied for kVA:\n8\nBasis for projection of Contract Demand-Diversity Factor assumed:\n9\nPhasing of Contract Demand required (Yes/No):\nIf Yes, then provide the following details in the given format:\nCD required (kVA) alongwith remarks, if any\nTentative Date from which required\n(a)\n(b)\n(c)\n10\nPurpose of connection\n11\nCategory of Tariff opted for\n12\nProduction capacity\n13\nCategory of Industry:\n(Tick the applicable one)\nSSI MSI LSI\nType of unit:\n(viz. Ownership/Partnership/Private Ltd./Public Ltd./Society/\n\t\t\t\tGovt. Dept./Govt undertaking)\n14\nName of Institution developing Industrial Premises: if any\n15(a)\nPossession Letter or No-Objection Certificate attached\nYes / No\n15(b)\nIssued by the Institution (attach a copy)\nNumber: Date:\n16\nWhether supply is needed through an independent feeder\nYes / No\n17\nWhether the above unit ever operated at some other place or\n\t\t\t\tapplied for connection? (if Yes, please provide details)\n(a) Sanctioned Load:\n(b) Service Connection No.\n(c) Arrears of payment\n(if any):\n18\nIf electricity connection for the premises was requested in the\n\t\t\t\tpast? (If Yes, please provide details)\n(a) Name of unit:\n(b) Service Connection No:\n(c) Arrears of payment\n(if any):\n19\nStatus of land acquisition\n20\nExpected date by which finance will be available\n21\nWhether the requisite consent/NOC (if applicable as per the list\n\t\t\t\tof Pollution Control Board) has been obtained as per statutory\n\t\t\t\trequirements (If yes, attach a copy)\n22\nAny electricity dues outstanding in licensee's area of operation\n\t\t\t\tin consumer's name: Yes / No\n23\nAny electricity dues outstanding for the premises for which\n\t\t\t\tconnection applied for: Yes/No\n24\nAny electricity dues outstanding with the licensee against any\n\t\t\t\tfirm with which the consumer is associated as an Owner, Partner,\n\t\t\t\tDirector or Managing Director: Yes / No\n(For questions 22, 23 & 24 if the answer is 'Yes' )\n25\nPlease indicate whether you want to carry out work of laying of\n\t\t\t\tline. Yes / No\n(a) The information provided in this application is true to my knowledge.\n(b) I/We have read the Chhattisgarh Electricity Supply Code and agree to abide by the conditions mentioned therein.\n(c) I/We will deposit electricity dues, every month, as per the applicable electricity tariff and other charges.\n(d) I/We own the responsibility of security and safety of the meter, cut-out and the installation thereafter.\nDate:\nSignature of the consumer/Authorized Signatory\nPlace:\nName:\nDesignation and Seal:\nNote. - The following documents shall be attached with the application form :\nNote.",
"footnote": "",
"is_definition": false,
"sort_order": 21
},
{
"number": "1",
"title": "1. Proof of ownership of the premises:",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 22
},
{
"number": "2",
"title": "2. A map indicating the proposed location of the plant/office duly marked the area by red ink where supply is to be utilized and the point where supply is required. MoP should normally be scale of I Cm representing 1200 Cm.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 23
},
{
"number": "3",
"title": "3. Licence/NOC from statutory authority, if required or a declaration by the applicant that his connection does not fall under the requirement of NOC under any statute.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 24
},
{
"number": "4",
"title": "4. In case of a proprietary firm, an affidavit to be submitted stating that the applicant is the sole proprietor of the firm.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 25
},
{
"number": "5",
"title": "5. In case of partnership firm, partnership deed.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 26
},
{
"number": "6",
"title": "6. In case of Limited Company, Memorandum and Articles of Association and Certificate of Incorporation.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 27
},
{
"number": "7",
"title": "7. Proof of permanent residential address of the consumer and PAN Number, if any. If there is any change at a later date, the same shall be intimated by the consumer to the licensee immediately.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 28
},
{
"number": "8",
"title": "8. Letter of intent for production/enhancement in production may be furnished.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 29
},
{
"number": "9",
"title": "9. List of equipments proposed to be installed alongwith the expected load.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 30
},
{
"number": "10",
"title": "10. Resolution for authorized signatory.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 31
},
{
"number": "11",
"title": "11. Registration from Industries Department.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 32
},
{
"number": "12",
"title": "12. Extract of project report relevant to power and process requirements (in case of industries).",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 33
},
{
"number": "13",
"title": "13. Copy of the relevant section of the current tariff order that provides details of the tariff category opted by the consumer and duly signed by him. This will be appended with the agreement after completion of formalities.",
"chapter": null,
"content": "Acknowledgement\nAcknowledgement\nAnnexure-3\nAnnexure-3\nAgreement for Electricity Supply to the Consumers\nAgreement for Electricity Supply to the Consumers\n(hereinafter called the \"contract demand or contracted load\")\n(b) The Licensee agrees to provide the requisite quantum of electricity as stipulated under foregoing Para 2(a) at..........................Volts for supply to the consumer and the consumer agrees to pay the necessary charges for receiving supply in accordance with the provisions under Section 45 of the Electricity Act, 2003 and other applicable provisions (hereinafter referred to as the \"Supply Code\") and Schedule of General and Misc. Charges and other Regulations of the Chhattisgarh State Electricity Regulatory Commission (hereinafter referred to as 'CSERC') as amended from time to time.\n(i) Tariff order references of CSERC..................order dated..............\n(ii) Tariff schedule..................................\n(iii) Tariff applicable................................\n(b) The consumer agrees to the supply of electricity under this agreement being curtailed, staggered or cut off altogether by the licensee if the power position or any other emergency in the power system warrants such a course of action.\nSigned by the above named\nIn the presence of\n1.\n(Name and address)\nAuthorized Representative of Chhattisgarh State\n\t\t\t\tPower Distribution Co. Ltd.\n2.\n(Name and address)\nThe common seal was hereunto affixed in presence\n\t\t\t\tof\n1.\n(Name and address)\nSeal of the Licensee\n2.\n(Name and address)\nSigned by the above named\nIn the presence of\n1.\n(Name and address)\n(Consumer)\nPaste passport size photo and Put\n\t\t\t\t\t\t\tsignature across it for connection other than Govt. and local\n\t\t\t\t\t\t\tbody\n(Name and address)\n…..........................................\n…..........................................\n….............................................\n2.\n(Name and address)\nThe common seal was\n\t\t\t\thereunto affixed in presence of\n1.\n(Name and address)\n(Rubber/Common Seal of\n\t\t\t\tthe Consumer, if applicable)\n2.\n(Name and address)\nAnnexure-4\nAnnexure-4\nApplication form-Change in Name of Registered Consumer/Transfer of Ownership to Legal Heir/Change of Consumer Category/Shifting of premises\nApplication form-Change in Name of Registered Consumer/Transfer of Ownership to Legal Heir/Change of Consumer Category/Shifting of premises\n(Tick the applicable purpose)\n1\nService Connection No.\n2\nName of Registered Consumer (at present)\n3\nConsumer category\n4\nContracted load\n5\nAddress:\nTelephone No. Mobile No.\n6\nName of the person in whose name connection to\n\t\t\t\tbe changed (in capital letters)\n7\nRequest for change in service:\n(i)\nIf request is for change in consumer category,\n\t\t\t\tmention the tariff category to which consumer wants to shift\n(See list of all tariff categories attached\n\t\t\t\twith this form)\n(ii)\nIf request is for change in premises : (a) New\n\t\t\t\taddress to which existing service connection is to be shifted.\n(b) Details of equipment to be shifted\n\t\t\t\t(Meter/service line, LT/ITT line, transformer etc.):\n7\nReason for change in service\nNote. - The following documents are attached with the application form :\nNote.\n(Tick whichever applicable) 1. Copy of latest bill duly paid 2. Proof of ownership/legal occupancy of premises 3. No objection certificate from the existing consumer if available/possible 4. Registered deed/Succession or legal heir certificate/Mutation deed/..................... (if any other document, please specify) 5. NOC from other legal heir(s) in case connection is to be changed in the name of one of the legal heirs. Date: Signature of the Consumer Place: Name:\n(Tick whichever applicable)",
"footnote": "",
"is_definition": false,
"sort_order": 34
},
{
"number": "1",
"title": "1. Copy of latest bill duly paid",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 35
},
{
"number": "2",
"title": "2. Proof of ownership/legal occupancy of premises",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 36
},
{
"number": "3",
"title": "3. No objection certificate from the existing consumer if available/possible",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 37
},
{
"number": "4",
"title": "4. Registered deed/Succession or legal heir certificate/Mutation deed/.....................",
"chapter": null,
"content": "(if any other document, please specify)",
"footnote": "",
"is_definition": false,
"sort_order": 38
},
{
"number": "5",
"title": "5. NOC from other legal heir(s) in case connection is to be changed in the name of one of the legal heirs.",
"chapter": null,
"content": "Date:\nSignature of the Consumer\nPlace:\nName:\nAcknowledgement\nAcknowledgement\nAnnexure-5\nAnnexure-5\nApplication Form-Load Enhancement/Load Reduction/Change in Supply Voltage\nApplication Form-Load Enhancement/Load Reduction/Change in Supply Voltage\n(Tick the applicable purpose)\n1\nName of the Applicant/Organization\n2\nService Connection Number\n3\nAddress of premises to which electricity is\n\t\t\t\tbeing supplied\nTelephone No.\n\t\t\t\t…...................................\nMobile No.\n\t\t\t\t…................................................\n4\nIn case of Load Enhancement Existing sanctioned\n\t\t\t\tload (in kW)\nEnhanced load requested (in kW)\n5\nIn case of Load Reduction Existing sanctioned\n\t\t\t\tload (in kW)\nReduced load requested (in kW)\n6\nReason(s) for Load Enhancement/Reduction\n7\nDetails of load added/disconnected from supply,\n\t\t\t\tif applicable (please attach list of equipments category-wise)\n(a) Lighting\n(b) Motive power\n(c) Agricultural\n(d) Other (please specify)\n8\nIf request is for conversion of service/change\n\t\t\t\tin supply voltage (Tick whichever applicable)\na) Conversion from LT single phase to LT 3-phase\n(b) Conversion from LT 3-phase to LT single\n\t\t\t\tphase\n(c) Conversion from LT to HT\n(d) Conversion from HT to LT\n(e) Conversion from HT to EHT\nDate:\nSignature of the Consumer\nPlace:\nName:\nNote. - The following documents are attached with the application form (if applicable)\nNote.",
"footnote": "",
"is_definition": false,
"sort_order": 39
},
{
"number": "1",
"title": "1. A work completion certificate & test report from Licensed Electrical Contractor, if the consumer's installation has been altered.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 40
},
{
"number": "2",
"title": "2. Resolution for authorized signatory.",
"chapter": null,
"content": "Acknowledgement\nAcknowledgement\nAnnexure-6\nAnnexure-6\nFormat for Intimation to Consumer after Temporary Disconnection of Supply\nFormat for Intimation to Consumer after Temporary Disconnection of Supply\nLicensee's Office Address\nDate...................\nAnnexure-7\nAnnexure-7\nRequest for Permanent Disconnection & Termination of Agreement\nRequest for Permanent Disconnection & Termination of Agreement\nNote. - The following documents are attached with the application form :\nNote.\nSignature of the Consumer\nDate:...........\nName Phone No.:\nPlace:..........\nAddress\nAcknowledgement\nAcknowledgement\nName and Designation:\nAnnexure-8\nAnnexure-8\nFormat for Intimation to Consumer after Termination of Agreement\nFormat for Intimation to Consumer after Termination of Agreement\nOffice Address\nDate...................\nAnnexure-9\nAnnexure-9\nMeter Related Complaints/Request for Testing of Meter\nMeter Related Complaints/Request for Testing of Meter\nDate:\n(Signature of Consumer)\n(For Office Use)",
"footnote": "",
"is_definition": false,
"sort_order": 41
},
{
"number": "1",
"title": "1. Site verification report",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 42
},
{
"number": "2",
"title": "2. Comments of concerned official",
"chapter": null,
"content": "Signature (concerned official)\nAcknowledgement\nAcknowledgement\nAnnexure-10\nAnnexure-10\nRecommended sizes and Ratings of cable for service connection/ transformer and power loads\nRecommended sizes and Ratings of cable for service connection/ transformer and power loads\nS. No.\nPurpose & Voltage\nDescription\nService Rating\n1\nStreet Light Fitting 250/440V\nCable W.P. Alu 1 core 1.5 Sqmm Polythene\nAll categories of lamps\n2\nDomestic Service 250/440V 650/1100 V\n(a) 2.5 Sqmm 1 core cable W.P. Alu. P.V.C.\n\t\t\t\tpolythene\nUpto 10 Ams\n(b) As above 2(a)\n(c) 6 Sqmm 1 core\n\t\t\t\tcable W.P. Alu PVC polythene\n(d) Same as 2(c)\n3 to 5 HP\n20 Amps.\n7.5 to 10 HP\n3\nPower Service 650/ 1100 V\n(a) 25 Sqmm 1 core cable W.P. Alu. P.V.C.\n\t\t\t\tpoly/PVC\n15 to 30 HP and 25 KVA Transformer\n(b) 95 Sqmm 3.5 core\n\t\t\t\tpower cable Arm. Alu. 3 core 95 Sqmm 650/1100 or power cable Alu\n\t\t\t\t3.5 core 90/55 Sqmm\n(c) 120 Sqmm 3.5 core power cable Arm. Alu. 3\n\t\t\t\tcore (120 Sqmm) 3.5 core (120/70 sqmm) 3.5 core (150/70 sqmm)\n\t\t\t\tPVC/PVL\n50 to 60 HP\nAbove 60 to 100 HP\n4\nDistribution Transformer\n(a) 120 sqmm 3.5 core\n\t\t\t\tas 3(c)\n(b) Power cable Arm Alu 3.5 core 300/150 sqmm\n\t\t\t\tPVC/650/1100 V\n63 to 100 KVA\n160 to 200 KVA\nAnnexure-11\nAnnexure-11\nRecommended values of capacitor for Direct Application with individual induction motor of 1500 RPM.\nRecommended values of capacitor for Direct Application with individual induction motor of 1500 RPM.\nMotor K.W.\nMotor H.P.\nMaximum kVAR Ratings\n1.865\n2.5\n1\n3.730\n5\n2\n5.595\n7.5\n3\n7.460\n10\n4\n9.325\n12.5\n4.5\n11.2\n15\n5\n13.1\n17.5\n5.5\n14.9\n20\n6\n16.8\n22.5\n6.5\n18.7\n25\n7\n20.5\n27.5\n7.5\n22.4\n30\n8\n24.2\n32.5\n8.5\n26.1\n35\n9\n28.0\n37.5\n9.5\n29.8\n40\n11\n31.7\n42.5\n11\n33.6\n45\n11.5\n35.4\n47.5\n12\n37.3\n50\n13\n41.0\n55\n13.5\n44.8\n60\n14.5\n48.5\n65\n15.5\n52.2\n70\n16.5\n56.0\n75\n17\n59.7\n80\n19\n63.4\n85\n20\n67.1\n90\n21\n70.9\n95\n22\n74.6\n100\n23\nNote. - The recommended rating of capacitor given in above mentioned table are mainly for guidance purposes. However, where there is no facility of recording average monthly power factor in the meter installed, the capacitor recommended as above for the respective capacity of motor will be considered in order.\nNote.",
"footnote": "",
"is_definition": false,
"sort_order": 43
},
{
"number": "1",
"title": "1. For better result capacitors be installed at the terminal of individual motors matching to its capacity so that capacitors may be switched on/switched off alongwith the motor with supply.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 44
},
{
"number": "2",
"title": "2. In case common capacitor is installed at one point for number of small motors, capacitor shall be switched off when there is only light and fan load in circuit or else it may affect the average monthly power factor due to over compensation during no load or less load period.",
"chapter": null,
"content": "Annexure-12\nAnnexure-12\n(A) Clearance above ground of the lowest conductor of overhead line (Clause 58 of CEA Safety Regulation):\n(i)\nfor lines of voltage not exceeding 650 Volts\n-\n5.8 metres\n(ii)\nfor lines of voltage exceeding 650 Volts but not\n exceeding 33kV\n-\n6.1 metres\n(i)\nfor lines of voltage not exceeding 650 Volts\n-\n5.5 metres\n(ii)\nfor lines of voltage exceeding 650 Volts but not\n exceeding 33kV\n-\n5.8 metres\n(i) for lines of voltage upto including 11,000\n Volts, if bare\n-\n4.6 metres\n(ii) for lines of voltage upto and including\n 11,000 Volts, if insulated\n-\n4.0 metres\n(iii) for lines of voltage exceeding 11,000\n Volts but not exceeding 33 kV\n-\n5.2 metres\n(B) Clearance from building of lines of voltage and service lines not exceeding 650 Volts (Clause 60 of CEA Safety Regulation) -\n(i) for any flat roof, open balcony, varandah roof and lean-to-roof -\n(a) when the line passes above the building a vertical clearance of 2.5 metres from the highest point and\n(b) when the line passes adjacent to the building a horizontal clearance of 1.2 metres from the nearest point, and\n(ii) for pitched roof -\n(a) when the line passes above the building a vertical clearance of 2.5 meters immediately under the line and\n(b) when the line passes adjacent to the building a horizontal clearance of 1.2 metres.\n(C) Clearances from building of lines of voltage exceeding 650 V (Clause 61 of CEA Safety Regulation) -\n(i)\nfor lines of voltages exceeding 650 Volts upto\n and including 33,000 Volts\n-\n3.7 metres\n(ii)\nfor lines of voltages exceeding 33 kV\n-\n3.7 metres plus 0.30 metre for every additional\n 33,000 Volts or part thereof.\n(i)\nfor lines of voltages exceeding 650 V upto and\n including 11,000 Volts\n-\n1.2 metres\n(ii)\nfor lines of voltages exceeding 11.000 V and\n upto and including 33.000 V\n-\n2.0 metres\n(iii)\nfor lines of voltages exceeding 33 kV\n-\n2.0 metres plus 0.3 metre for every additional\n 33kV or part thereof.\n(D) Safe Working Clearance from High voltage and EHV lines:\nHighest system voltage in KV\nSafe working clearance in meter\n12\n2.6\n36\n2.8\n145\n3.7\n245\n4.3\nAnnexure-13(A)\nAnnexure-13(A)\nIllustration on clause 4.52 - Supply in under developed colonies\nAnnexure-13(B)\nAnnexure-13(B)\nIllustration on clause 4.55-Supply to small/cottage industries",
"footnote": "",
"is_definition": false,
"sort_order": 45
}
],
"metadata": {
"Act ID": "Last Updated 14th October, 2019 [cg197]",
"Act Number": "Published vide Notification No. 39/CSERC/2011, dated 28th November, 2011",
"Enactment Date": "",
"Act Year": "2011",
"Short Title": "Chhattisgarh State Electricity Supply Code, 2011",
"Type": "STATE",
"Location": "Chhattisgarh"
},
"updated_at": "2026-09-29 21:55:19"
}