The Static and Mobile Pressure Vessels (Unfired) Rules, 2016

The Static and Mobile Pressure Vessels (Unfired) Rules, 2016

Raw JSON API

Sections

1. Short title and commencement.

Section 1

2. Definition.

Section 2

3. General exemptions.

Section 3

4. Restriction on filling, manufacture and import of pressure vessels including fittings and vapouriser.

Section 4

5. Restriction on delivery and despatch.

Section 5

6. Repair and modification to pressure vessels.

Section 6

7. Purging of pressure vessels used for flammable gases.

Section 7

8. Prohibition of employment of children and intoxicated persons.

Section 8

9. Supervision and Operation within the licensed premises.

Section 9

10. Special precautions against accidents.

Section 10

11. Procedure for payment of fees.

Section 11

12. Procedure for grant and revocation of recognition to competent person and inspector.

Section 12

13. Design code.

Section 13

14. Design pressure.

Section 14

15. Design of vessels for gases at low temperature.

Section 15

16. Filling capacity and filling pressure.

Section 16

17. Markings and Painting of pressure vessels.

Section 17

18. Fittings.

Section 18

19. Periodic testing of pressure vessels in service.

Section 19

20. Precautions to be observed in carrying out periodic test.

Section 20

21. General.

Section 21

22. Location of pressure vessels.

Section 22

23. Foundations for pressure vessels.

Section 23

24. Cleanliness and restriction of unauthorized person.

Section 24

25. Earthing.

Section 25

26. Fire protection.

Section 26

27. Loading and unloading facilities.

Section 27

28. Transfer operations.

Section 28

29. Dispenser for auto LPG dispensing station.

Section 29

30. Special Provisions for filling fuel tanks of motor vehicles and unloading of tank-truck in Auto LPG dispensing station.

Section 30

31. Electrical apparatus and installations.

Section 31

32A. Classification of hazardous area for flammable gases.

Section 32A

32B. Extent of hazardous area.

Section 32B

33. Certificate of safety.

Section 33

34. Application.

Section 34

35. Vehicles for transport of compressed gas.

Section 35

36. Design.

Section 36

37. Protection of valves and accessories.

Section 37

38. Equipment.

Section 38

39. Vehicle design considerations.

Section 39

40. Marking of vehicle.

Section 40

41. Fire protection.

Section 41

42. Operations.

Section 42

43. Certificate of Safety.

Section 43

44. Inspection and maintenance of vehicles.

Section 44

45. License for storage of compressed gas.

Section 45

46. Prior approval of specification and plans of vessels and premises proposed to be licensed.

Section 46

47. No Objection Certificate.

Section 47

48. License for transport of compressed gas.

Section 48

49. Grant of license.

Section 49

50. Application for license.

Section 50

51. Period for which licenses may be granted or renewed.

Section 51

52. Power of licensing authority to alter conditions.

Section 52

53. Prior approval necessary for alteration in the licensed premises.

Section 53

54. Amendment and Transfer of license.

Section 54

55. Renewal of license.

Section 55

56. Refusal of license.

Section 56

57. Suspension and cancellation of license.

Section 57

58. Procedure on expiration, suspension or cancellation of license.

Section 58

59. Appeals.

Section 59

60. Procedure on death or disability of licensee.

Section 60

61. Loss of license.

Section 61

62. Display of information in licensed premises and production of license on demand.

Section 62

63. Compliance of instruction of licensing authority.

Section 63

64. Procedure on reports of infringement.

Section 64

65. Executive control over authorities.

Section 65

66. Powers to exempt.

Section 66

67. Recording of incidents and notice of accident.

Section 67

68. Inquiry into accidents.

Section 68

69. Inquiry into more serious accidents.

Section 69

70. Powers of inspection, search, seizure, detention and removal.

Section 70

71. Protection of action taken in good faith.

Section 71

72. Repeal and Savings.

Section 72

1. Name & full address of the organization with telephone no. and E-mail:

Section 1

2. Organization status (proprietary firm, partnership firm, Government organization, Public Sector Undertaking, Autonomous body, Company registered under Company Act,):

Section 2

3. Purpose for which competency is sought (Specify the rules):

Section 3

4. Whether the organization has been declared as a competent person under any other status, if so, give details:

Section 4

6. Particulars of equipments, gauges etc. available with the Organization for carrying out the inspection/testing:

Section 6

7. Details of the procedures followed in carrying out stage by stage inspection/test for certification under different rules:

Section 7

8. Any other information:

Section 8

9. Declaration:

Section 9

1. Name & Full address of the organization with telephone no. and E-mail:

Section 1

2. Organization status (proprietary firm, partnership firm, Government organization, Public Sector Undertaking, Autonomous body, Company registered under Company Act.):

Section 2

3. Whether the organization has been declared as a competent person under any other status, if so, give details:

Section 3

5. Particulars of equipments, gauges etc. available with the Organization for carrying out the inspection/Testing:

Section 5

6. Details of the procedures followed in carrying out stage by stage inspection/test for certification:

Section 6

7. Any other information:

Section 7

8. Declaration:

Section 8

1. Name:

Section 1

2. Date of birth:

Section 2

3. Name of the organization:

Section 3

4. Designation:

Section 4

5. Educational qualification (Copies of testimonials to be attached):

Section 5

6. Particulars of professional experience (in chronological order):

Section 6

7. Membership, if any, of professional bodies:

Section 7

8. Details of facilities (examination, testing etc.) at his disposal:

Section 8

9. Purpose for which competency certificate is sought (specify the rules):

Section 9

10. Whether the applicant has been declared as a competent person under any statute (if so, give details):

Section 10

11. Any other relevant information:

Section 11

12. Declaration by the applicant:

Section 12

1. Design code for design and fabrication of the Vessel shall be as per BIS 2825, ASME Section VIII Div. 1 or Div. 2 or PD 5500 or any other standard accepted by the Chief Controller. A single code shall be applied for design, fabrication, inspection and testing. Specific considerations shall be given for internal pressure, internal vacuum and external loading. Design pressure shall be adequate for vapour pressure at 55 deg C plus static head. The design shall also include a minimum corrosion al

Section 1

2. In case of LPG, design pressure shall be 14.5 Kg/sq. cm at top of the vessel & temperature of -27OC to + 55OC and the material selection in case of refinery installation shall be suitable for the traces of hydrogen sulphide.

Section 2

3. The installation shall conform to a recognized Indian or International standard accepted by the Chief Controller. The vessels shall be placed horizontally and the central axis of the vessels shall be parallel to one another and inter distance between the vessels, distance of boundary line of the installation shall be as per the Table 3. A road/clear area of width (See Table A of this schedule) on three sides shall be provided around the mound for moving and firefighting equipment. The facilit

Section 3

4. The mounded pressure vessels installation shall be done on concrete or compacted sand base foundation. The selection of the type of foundation shall have considerations for sufficient load bearing capacity, depending on the site conditions and the soil mechanics. In case bottom nozzle has been provided for the vessel, an access to the connection, like a tunnel opening of minimum 0.9 m X 1.2 m shall be provided. The bottom level of the vessel shall be above the top of the inspection tunnel. Th

Section 4

5. The mound shall be of earth, sand or other non-combustible material of a thickness (as per Table A of this schedule) of the cover for the vessel. The cover material shall be free from any abrasive particles that may damage the anti-corrosive coating provided on the vessel. The mound shall provide adequate protection from the thermal radiation, and shall be sufficiently robust to remain in place in the event of jet flame impingement. The mound shall be protected from erosion, caving in from wa

Section 5

6. The external surface of the vessels shall be suitably protected from corrosion by providing suitable external coatings and cathodic protection. The design shall conform to NACE RP 169 or any other standard accepted by the Chief Controller. The protected vessel shall be isolated from the unprotected structures and piping. The calculated life of the cathodic protection shall not be less than 15 years, considering coating defect of minimum 30% on vessel surface. The monitoring of the cathodic pr

Section 6

7. Vessels shall be provided with fire safe remote operated valves (ROVs) at the first flange on the liquid lines and the closing time shall not exceed 30 seconds. Each vessel shall be provided with minimum two types of level indicators of which one shall be electronic with High level switch and shall indicate a remote display of the level at the fill point, one additional independent high level switch shall be provided for the Category 3 type of the vessel, two safety relief valves (SRVs), pres

Section 7

8. Provision shall be made for Gas leak detection system. Fire fighting facility shall be provided with fire hydrant or monitor (See Table A of this schedule) in addition to the Water sprinklers to provide a water cover to the exposed surfaces of the vessel and pipelines. Such hydrants and monitors shall not be located within the distances specified in Table A from the exposed surface of vessel, fittings and pipelines. In addition minimum 2 Nos. of fire extinguishers of capacity 75 Kgs. and shal

Section 8

9. The mounded Vessels installation shall be inspected and certified by an inspector at every important stage of construction, including the design and fabrication of the vessel, foundation, mound covering, cathodic protection, NDT and hydraulic testing of vessels and piping and final certification of safety under Rule 33.

Section 33

10. The vessel shall be subjected to internal inspection once in 5 years under Rule 19 and shall include the Non Destructive Tests comprising of ultrasonic thickness measurement check evenly spread over the entire inner surface including both dish ends and the openings, 100% wet fluorescent magnetic particle test of all weld joints, ultrasonic flaw detection of welds not less than 25% of weld seams including all the T-joints of middle circumferential seams and both dish ends weld seams & nozzle

Section 19

11. The vessels shall be subject to hydraulic test pressure as per the design code in addition to the above nondestructive tests once in 10 years, or when subjected to any repairs involving hot work. Settlement of the vessel, if any, shall be measured during the first water fill.

Section 11

12. The safety relief valves shall be inspected and tested under Rule 18 once in a year and the excess flow valves and the remote operated valves shall be inspected and tested once in 5 years during the periodic test under Rule 19.

Section 18

1. Design code for design and fabrication of the vessel shall be as per BIS-2825, ASME Section VIII Div.1 or Div. 2 or PD 5500 or any other standard accepted by the Chief Controller. A single code shall be applied for design, fabrication, and inspection & testing. Specific considerations shall be given for internal pressure and external loading. Design pressure shall be adequate for vapour pressure at 55 deg C plus static head.

Section 1

2. The design shall also include a corrosion allowance of 1.5mm and stress relieving of complete vessel irrespective of its thickness.

Section 2

3. The underground vessels shall be placed within a concrete or brick masonry pit with a distance of 1 mtr between the walls of the pit and the vessel and inter distance between the vessels. Soil cover of at least 500 mm shall be provided over the top surface of the vessel. The vessels shall be installed on a firm RCC foundation and anchored adequately to prevent the floatation of the vessel due to up-lift force of buoyancy in case of a worst scenario of no load of the product and overburden. Th

Section 3

4. The external surface of the Vessels shall be suitably protected from corrosion by providing external coatings and cathodic protection. The design shall conform to NACE RP 169 or any other standard acceptable to Chief Controller and shall consider negative cathodic potential of not more than (-) 850 mV and not less than (-) 1200 mV between the vessel surface and the electrolyte, the potential being measured with reference standard copper/copper sulphate reference cell. A minimum polarized shif

Section 4

5. The underground vessels installation shall be undertaken by the recognized installers and inspected and certified by an inspector at every important stage of construction, including the design and fabrication of the vessel, foundation, mound covering, cathodic protection, NDT and hydraulic testing of vessels and piping and final certification of safety under Rule 33.

Section 33

6. Each storage vessel shall have at least two safety relief valves, two independent level indicating devices of which one shall be electronic with High level switch and shall indicate a remote display of the level at the fill point, suitable arrangement for water draining etc. remote operated valves (ROVs) shall be provided on all liquid and vapour lines connected to the storage vessel that is, filling, discharge, pump by pass and vapour return lines except those of safety relief valves and dra

Section 6

7. Excess flow check valve (EFCV) shall be provided on all the liquid lines (above 3 mm) and vapour lines (above 8 mm) except those of safety relief valves, drain lines and instruments. Closing flow rate of EFCV shall not be more than 20% of the rated flow of the line.

Section 7

8. Fill point shall be provided with non-return valve and quick shut off isolation valve.

Section 8

9. Proper arrangement shall be made for earthing and bonding of the road tanker.

Section 9

10. Vent pipes shall have 3 M height and 6 M away from source of ignition.

Section 10

11. ALDS with underground and mounded LPG storage vessels shall have two 75 Kg and two 9 Kg DCP fire extinguishers. At ALDS with above ground LPG Vessels, hydrants with minimum water pressure of 7 Kg/sq. cm. shall be provided at convenient location for all round coverage of the storage vessels and handling area, and water sprinklers with spray density of 10 lpm. The fire water shall be preferably diesel driven with capacity to deliver water at rate and pressure specified above. The minimum fire

Section 11

12. The vessel shall be subjected to internal inspection once in 5 years, and shall include the Non Destructive Tests comprising of ultrasonic thickness measurement check evenly spread over the entire inner surface and the openings, 100% wet fluorescent magnetic particle test of all weld joints, ultrasonic flaw detection of all the T-joints, Liquid Penetrant Inspection of all the fillet welds, nozzle joints. The vessel shall be tested pneumatically at a pressure of 1.1 times the design pressure.

Section 12

13. The vessels shall be subjected to hydraulic test pressure as per the design code in addition to the above nondestructive tests once in 10 years, or when subject to any repairs involving hot work.

Section 13

14. The safety relief valves shall be inspected and tested under Rule 18 once in a year and the excess flow valves and the remote operated valves shall be inspected and tested once in 5 years during the period test under Rule 19.

Section 18

15. The periodic testing under Rule 19 to be conducted for a multi-vessel installation shall be so conducted that both the vessels are tested simultaneously.

Section 19

16. The underground vessels or aboveground vessels covered by earth mound shall-

Section 16

Section 1

Section 1

Section 1

Section 1

2. The LNG installation shall be designed to withstand the following without loss of structural or functional integrity-

Section 2

3. The structural members of the impoundment system must be designed and constructed to prevent impairment of the impoundments reliability and structural integrity as a result of the following

Section 3

4. Impoundment or dyke areas must be designed so that all areas drain completely to prevent water collection. Drainage pumps and piping must be provided to remove water from collecting in the impoundment area. Where automatically controlled drainage pumps are used they shall be provided with cut off devices that prevent their operation when exposed to LNG temperature.

Section 4

5. The impounding system for LNG storage vessel must have a minimum volumetric liquid capacity of -

Section 5

6. The height of the impoundment wall shall be adequate to contain spillage of any LNG. A minimum height of 1 m. is recommended for the impoundment/dyke wall.

Section 6

7. No other flammable liquid or storage vessel shall be located within an LNG impounding area.

Section 7

8. A clear space of at least 0.9 mtrs. shall be provided for access to all isolation valves serving multiple vessels. The isolation valve of LNG tank piping should be as close to outer vessel as possible.

Section 8

9. LNG vessels, cold boxes, piping and pipe supports and other cryogenic apparatus installed within dyke shall be designed and constructed in a manner to prevent damage to these structures and equipments due to freezing or frost heaving in the soil.

Section 9

10. Proper lighting arrangement shall be done for facilities transferring LNG during night.

Section 10

11. Electrical grounding and bonding shall be provided.

Section 11

12. Lightning protection shall not be required on LNG storage containers except that lightning protection ground rods shall be provided for tanks supported on non-conductive foundations.

Section 12

1. LNG vessels foundations shall be designed by a qualified engineer and constructed in accordance with recognized structural engineering practices. Prior to the start of design and construction of the foundation, a subsurface investigation shall be conducted by a qualified soil engineer to determine the stratigraphy and physical properties of the soil underlying the site.

Section 1

2. The design of saddles and legs for the LNG vessel shall include erection load, wind loads and thermal loads.

Section 2

3. Foundation and support shall have a fire resistance rating of not less than two hrs.

Section 3

4. LNG vessels installed in areas subject to flooding shall be secured to prevent release of LNG or floatation of the vessel in the event of a flood.

Section 4

1. The vessel meant for storage of LNG including piping between inner and outer vessel shall be designed in accordance with ASME Section VIII Div. 1 or Div. 2/EN13458/ASME:B.31.3, process piping or equivalent code acceptable to Chief Controller.

Section 1

2. The inner vessel shall be designed for the most critical combination of loading resulting from internal pressure and liquid heads. The inner vessel supports system shall be designed for shipping, seismic, and operating loads.

Section 2

3. The outer vessel shall be equipped with a relief or other device to release internal pressure and shall have discharge area of at least 0.0034 cm2/kg of the water capacity of the inner vessel but not exceeding 2000 cm2 and have pressure setting not exceeding 25psi..

Section 3

4. Thermal barriers shall be provided to prevent outer tank from falling below its design temperature.

Section 4

5. Those parts of LNG vessels which come in contact with LNG and all materials used in contact with LNG or cold LNG vapour shall be physically and chemically compatible with LNG and intended for service at -1620C.

Section 5

6. All piping that is a part of LNG vessel including all piping internal to the container, within void space, and external piping connected to the vessel up to the first circumferential external joint of the piping shall be in accordance with ASME Boiler and Pressure Vessel Code, Section VIII or ASME B 31.3 or equivalent.

Section 6

7. LNG vessels shall be designed to accommodate both top and bottom filling unless other positive means are provided to prevent stratification.

Section 7

8. Any portion of the outer surface area of an LNG vessel that could accidentally be exposed to low temperatures resulting from the leakage of LNG or cold vapour from flanges, valves etc. shall be intended for such temperatures or protected from the effects of such exposure.

Section 8

9. Seismic loads shall be considered in the design of the LNG vessel support systems.

Section 9

1. Each LNG double walled vessel shall have at least 2 Nos. of safety relief valves capable of achieving the required relief capacity on standalone basis and shall be sized to relieve the flow capacity determined for the largest single contingency or any reasonable and probable combination of contingencies and shall include conditions resulting from operational upset, vapour displacement and flash vaporization.

Section 1

2. Relief devices shall be vented directly to the atmosphere. Each safety relief valve for LNG vessel shall be able to be isolated from the vessel for maintenance or other purposes by means of a manual full opening stop valve.

Section 2

3. Safety relief valve shall be designed and installed to prevent any accumulation of water, or other foreign matter at its end.

Section 3

4. The minimum pressure relieving capacity in kg/hr shall not be less than 3% of the full tank contents in 24 hrs.

Section 4

5. All liquid connections to the LNG vessel except relief valve and instrumentation connection shall be equipped with automatic fail safe product retention valves.

Section 5

6. The automatic shut off valves shall be designed to close on occurrence of any of the following conditions:

Section 6

7. Such of the automatic shutoff valves that require excessive time to operate during emergency i.e. sizes exceeding 200 mm shall be pneumatically operated and also have means of manual operation.

Section 7

8. All LNG vessels shall have a device that prevents the vessel from becoming liquid full or from covering the inlet of the relief valve with liquid when the pressure in the vessel reaches the set pressure of relieving device under all conditions.

Section 8

9. Every LNG vessel may be provided with one independent high liquid level alarm which may be part of the liquid level gauging devices. However, the high liquid level flow cut-off device shall not be considered as a substitute for the alarm.

Section 9

10. Every LNG vessel shall be equipped with at least one liquid level gauging device. The devices shall be designed and installed so that they can be replaced without taking the tank out of operation.

Section 10

11. Each LNG vessel shall be equipped with a high liquid level flow cut-off device,

Section 11

12. Each LNG vessel shall be equipped with pressure gauge connected to the vessel at a point above the maximum intended liquid level.

Section 12

13. Instrumentation for storage and vaporization facilities shall be so designed so that if a power or instrument air failure occurs, the system will proceed to a fail safe condition and maintain that condition until the operator takes appropriate action to reactivate or secure the system

Section 13

1. Pumps and compressors employed in LNG source shall be provided with a pressure relieving device on the discharge to limit the pressure to the maximum safe working pressure of the casing and downstream piping and equipment.

Section 1

2. Each pump shall be provided with adequate vent, relief valve, or both that will prevent over-pressuring the pump case during the maximum possible rate of cool down.

Section 2

3. The discharge valve of each vaporizer and the piping components and relief valves installed upstream of each vaporizer discharge valve shall be designed for operation at LNG temperatures.

Section 3

4. Two inlet valves shall be provided to isolate an idle manifolded vaporizer to prevent leakage of LNG into the vaporizer. A safe means of disposing of the LNG or gas that can accumulate between the valves shall be provided in case the vaporisers are of size having inlets more than 50 mm diameter.

Section 4

6. A distance of minimum 1 meter shall be maintained between vaporizers.

Section 6

7. Vaporisers shall be designed, fabricated and inspected as per the requirements of ASME Boiler & Pressure Vessel Code, Section VIII Division 1. or any other equivalent acceptable code to Chief Controller.

Section 7

8. Manifolded vaporisers shall be provided with both inlet and discharge block valves for each set of vaporizer.

Section 8

9. Any ambient vaporiser installed within 15 mtrs. of the LNG vessel shall be equipped with an automatic shutoff valve in the liquid line. This valve shall be located minimum at least 3 mtrs. from the vaporisers and shall close when loss of line pressure occurs or abnormal temperature is sensed in the immediate vicinity of the vaporizer or when low temperature in the vaporizer discharge line occurs.

Section 9

10. Each set of vaporiser shall be provided with a safety relief valve(s) sized in accordance with the following requirements:

Section 10

11. Automation shall be provided to prevent the discharge of either LNG or vaporizer gas into a distribution system at the temperature either above or below the design temperature of the send out system.

Section 11

12. Vaporizers shall be provided with outlet temperature monitors.

Section 12

1. All piping system and components shall be designed -

Section 1

2. Piping material including gaskets and thread compounds shall be compatible throughout the range of temperature to which they are subjected.

Section 2

3. The valves provided in the installation shall be of extended bonnet type with packing seals in a position that prevents leakage or malfunction due to freezing.

Section 3

4. Shutoff valves shall be provided for all tank connections except connections for liquid level alarms and connections that are blind flanged or plugged.

Section 4

5. All the piping section between the two valves where the liquid may be trapped shall have the thermal relief valve.

Section 5

6. Aluminum shall be used only downstream of a product retention valve in vaporizer service.

Section 6

1. Isolation valves shall be installed so that each transfer system can be isolated at its extremities. Where power-operated isolation valves are installed, an analysis shall be made to determine the closure time so that it does not produce a hydraulic shock capable of causing line or equipment failure.

Section 1

2. Adequate check valves shall be provided to prevent backflow and shall be located as close as practical to the point of connection to any system from which backflow might occur.

Section 2

1. The tank vehicle unloading area shall be of sufficient size to accommodate the vehicles without excessive movement or turning.

Section 1

2. Transfer piping, pumps, and compressors shall be located or protected by barriers so that they are safe from damage by vehicle movements.

Section 2

3. Isolation valves and bleed connections shall be provided at the unloading manifold for both liquid and vapour return lines so that hoses and arms can be blocked off, drained of liquid, and depressurized before disconnecting. Bleeds or vents shall discharge in a safe area.

Section 3

4. The hose connecting point and center of tanker hard stand shall maintain a minimum of 9 mtr. from the protected boundary

Section 4

1. Each LNG facility shall incorporate an ESD system that when operated isolates or shuts off sources of LNG and shuts down equipment that add or sustain an emergency if continued to operate.

Section 1

2. The ESD system shall be of a fail-safe design and shall be installed, located, or protected from becoming inoperative during an emergency or failure at the normal control system.

Section 2

3. Initiation of the ESD system shall be manual, automatic, or both manual and automatic. Manual actuators shall be located in an area accessible in an emergency and at least 15 mtrs. away from the equipment they serve, and shall be distinctly marked with their designated function.

Section 3

1. Each LNG storage facility shall be provided with continuously monitored low-temperature sensors or flammable gas detectors, which must activate visual and audible alarms at the plant site and at an constantly attended location if the facility is not attended continuously.

Section 1

2. Flammable gas detection system shall activate an audible and a visual alarm at level not no higher than 25% of the LEL of the gas being monitored.

Section 2

3. Fire detectors shall activate an alarm at the plant site and at a constantly attended location if the plant site is not attended continuously. If determined by an evaluation that it is necessary then fire detectors shall be permitted to activate the ESD system.

Section 3

4. A fire water supply and delivery system must be provided, unless the fire protection evaluation indicates that the fire water is unnecessary or impractical.

Section 4

5. Portable or wheeled fire extinguishers, shall be made available at strategic locations. At least 4 such extinguishers of 10 kg. capacity each shall be provided.

Section 5

Section 2

Section 2

Section 2

Section 2

Section 3

Section 3

Section 3

Section 3

1. Name in which license is required:*

Section 1

2. Status of applicant(individual/company/partnership/Society):

Section 2

3. Licensee's complete postal address with pin code

Section 3

4. Location of the premises where compressed gas in vessel(s) is to be stored:

Section 4

5. Chemical name and nature of compressed gas proposed to be stored:**

Section 5

6. Chemical name of compressed gas already stored in the premises:***

Section 6

8. Particulars of the license held for the premises under SMPV(U) Rules and Petroleum Rules, if any and full name of the licensee:

Section 8

1.     Name in which license required

Section 1

2.     Particulars of storage license held by the applicant under SMPV(U) Rules, 2016 & Gas Cylinders Rules, 2016 :

Section 2

3.     Description of the pressure vessel to be imported:

Section 3

4.     Registration number of vehicle, if applicable

Section 4

5.     Name of the port

Section 5

6.     Remarks

Section 6

3. In case vessel is desired to be imported duly filled with gas, filler's certificates in respect of items 3(viii) and (ix) shall be furnished.

Section 3

4. Copy of RC book.

Section 4