85. Preparatory works before commissioning of pipelines.

(a) commissioning procedure is in place;
(b) pressure testing is completed for entire pipeline and associated station piping;
(c) pressure leak check of the above ground piping and flanged joints is completed;
(d) pipeline has been cleaned and debris has been removed;
(e) mainline sectionalising valves are installed as per requirement;
(f) all Golden joints are inspected and accepted;
(g) geometric survey of pipeline section is carried out, if applicable; and
(h) trained and experienced officials in adequate numbers are appointed for supervision of commissioning work of pipelines.