(a) commissioning procedure is in place;
(b) pressure testing is completed for entire pipeline and associated station piping;
(c) pressure leak check of the above ground piping and flanged joints is completed;
(d) pipeline has been cleaned and debris has been removed;
(e) mainline sectionalising valves are installed as per requirement;
(f) all Golden joints are inspected and accepted;
(g) geometric survey of pipeline section is carried out, if applicable; and
(h) trained and experienced officials in adequate numbers are appointed for supervision of commissioning work of pipelines.
Section 85 • The Oil Mines Regulations, 2017
85. Preparatory works before commissioning of pipelines.
the-oil-mines-regulations-2017-sec-85.json
•
Section 85
{
"act_title": "The Oil Mines Regulations, 2017",
"act_slug": "the-oil-mines-regulations-2017",
"section_label": "Section",
"section": {
"number": "85",
"title": "85. Preparatory works before commissioning of pipelines.",
"chapter": null,
"content": "(a) commissioning procedure is in place;\n(b) pressure testing is completed for entire pipeline and associated station piping;\n(c) pressure leak check of the above ground piping and flanged joints is completed;\n(d) pipeline has been cleaned and debris has been removed;\n(e) mainline sectionalising valves are installed as per requirement;\n(f) all Golden joints are inspected and accepted;\n(g) geometric survey of pipeline section is carried out, if applicable; and\n(h) trained and experienced officials in adequate numbers are appointed for supervision of commissioning work of pipelines.",
"footnote": "",
"is_definition": false,
"sort_order": 84
},
"prev_section": "84",
"next_section": "86"
}