    "section": {
        "number": "85",
        "title": "85. Preparatory works before commissioning of pipelines.",
        "chapter": null,
        "content": "(a) commissioning procedure is in place;\n(b) pressure testing is completed for entire pipeline and associated station piping;\n(c) pressure leak check of the above ground piping and flanged joints is completed;\n(d) pipeline has been cleaned and debris has been removed;\n(e) mainline sectionalising valves are installed as per requirement;\n(f) all Golden joints are inspected and accepted;\n(g) geometric survey of pipeline section is carried out, if applicable; and\n(h) trained and experienced officials in adequate numbers are appointed for supervision of commissioning work of pipelines.",
        "footnote": "",
        "is_definition": false,
        "sort_order": 84
    },