(a) pressure test and function test of the blowout preventer assembly is conducted;
(b) fire-fighting equipment is kept readily available for immediate use;
(c) no person other than those required for the test is admitted on the drilling floor;
(d) the test line is securely anchored at each end and at each nine metre interval;
(e) thekelly hose is not used as part of the test line; and
(f) the test line and valves are examined by a competent person and no test is conducted if any defect is discovered until such defect is rectified.
Chapter VI
Production
Section 60 • The Oil Mines Regulations, 2017
60. Drill stem test.
the-oil-mines-regulations-2017-sec-60.json
•
Section 60
{
"act_title": "The Oil Mines Regulations, 2017",
"act_slug": "the-oil-mines-regulations-2017",
"section_label": "Section",
"section": {
"number": "60",
"title": "60. Drill stem test.",
"chapter": null,
"content": "(a) pressure test and function test of the blowout preventer assembly is conducted;\n(b) fire-fighting equipment is kept readily available for immediate use;\n(c) no person other than those required for the test is admitted on the drilling floor;\n(d) the test line is securely anchored at each end and at each nine metre interval;\n(e) thekelly hose is not used as part of the test line; and\n(f) the test line and valves are examined by a competent person and no test is conducted if any defect is discovered until such defect is rectified.\nChapter VI\nProduction",
"footnote": "",
"is_definition": false,
"sort_order": 59
},
"prev_section": "59",
"next_section": "61"
}