60. Drill stem test.

(a) pressure test and function test of the blowout preventer assembly is conducted;
(b) fire-fighting equipment is kept readily available for immediate use;
(c) no person other than those required for the test is admitted on the drilling floor;
(d) the test line is securely anchored at each end and at each nine metre interval;
(e) thekelly hose is not used as part of the test line; and
(f) the test line and valves are examined by a competent person and no test is conducted if any defect is discovered until such defect is rectified.
Chapter VI
Production