    "section": {
        "number": "60",
        "title": "60. Drill stem test.",
        "chapter": null,
        "content": "(a) pressure test and function test of the blowout preventer assembly is conducted;\n(b) fire-fighting equipment is kept readily available for immediate use;\n(c) no person other than those required for the test is admitted on the drilling floor;\n(d) the test line is securely anchored at each end and at each nine metre interval;\n(e) thekelly hose is not used as part of the test line; and\n(f) the test line and valves are examined by a competent person and no test is conducted if any defect is discovered until such defect is rectified.\nChapter VI\nProduction",
        "footnote": "",
        "is_definition": false,
        "sort_order": 59
    },
    "prev_section": "59",
    "next_section": "61"
}