← Back to Directory

Madhya Pradesh Electricity Supply Code, 2013

Madhya Pradesh Electricity Supply Code, 2013

Raw JSON API

Sections

1. Consumer -

Section 1

2. Built-up area of the premises/plot area

Section 2

3. Category of supply

Section 3

4. Purpose of supply

Section 4

5. Type of Supply

Section 5

6. Proposed Load -

Section 6

7. Any electricity dues outstanding in the licensee's area of operation in the consumer's name           Yes/No

Section 7

8. Any electricity dues outstanding for the premises for which connection applied for           Yes/No

Section 8

9. Any electricity dues outstanding with the licensee against any firm/company with which the consumer is associated as an Owner, Partner, Director or Managing Director           Yes/No

Section 9

10. Whether the boundary within which electricity shall be consumed is clearly shown in the Plan (Map) of the premises.           Yes/No

Section 10

11. I/We hereby declare that -

Section 11

1. Consumer -

Section 1

2. Built-up area of the premises/plot area

Section 2

3. Category of supply

Section 3

4. Purpose of supply

Section 4

5. Type of Supply

Section 5

6. Proposed Load (fill up the following) -

Section 6

7. Voltage at which supply is required (KV) :

Section 7

8. Type of supply : Temporary/Permanent/standby/synchronization of CPPs or Generators with Grid

Section 8

9. Steps taken by the consumer so far to set-up the installation

Section 9

10. Basis of projection of Contract Demand required -

Section 10

11. Whether connection is required in phases :.....................................................

Section 11

12. Phasing of contract demand (CD) :.....................................................

Section 12

13. Purpose of installation :..........................................................

Section 13

14. Category of tariff opted for :..........................................................

Section 14

15. Probable date of production :..............................................................

Section 15

16. Category of Industry : SSI/MSI/LSI

Section 16

17. Status of land acquisition :............................................................

Section 17

18. Expected date by which finance would be available : ..........................................

Section 18

19. Whether the requisite consent/NOC (where applicable according to the list of Pollution Control Board) has been obtained from M.P. State Prevention and Control of Water Pollution Boards, Bhopal as per statutory requirements

Section 19

20. Any electricity dues outstanding in the licensee's area of operation in the consumer's name        Yes/No

Section 20

21. Any electricity dues outstanding for the premises for which connection applied for :        Yes/No

Section 21

22. Any electricity dues outstanding with the licensee against any firm/company with which the consumer is associated as an Owner, Partner, Director or Managing Director         Yes/No

Section 22

23. Whether the boundary within which electricity shall be consumed is clearly shown in the Plan (Map) of the premises.        Yes/No

Section 23

24. I/We hereby declare that -

Section 24

1. Proof of ownership/legal occupancy of the premises.

Section 1

2. A map indicating therein in the proposed location of the plant/office and the point where supply is required. The map should normally be of the scale of 1cm representing 1200cm for EHT/HT connection.

Section 2

3. Licensee/NOC from statutory authority, if required or a declaration by the applicant is that his connection does not fall under the requirement of NOC under any statute.

Section 3

4. In case of a proprietary firm, an affidavit to be submitted stating that the applicant is the sole proprietor of the firm.

Section 4

5. In case of partnership firm, a certified copy of partnership deed.

Section 5

6. In case of Limited Company, Memorandum and Articles of Association and Certificate of Incorporation.

Section 6

7. In case of agricultural consumer, copy of Khasra/Bahi be attached.

Section 7

8. Proof of permanent residential address of the consumer and PAN Number, if any. If there is any change at a later date, the same shall be intimated by the consumer to the Licensee immediately.

Section 8

9. Letter of intent for production/enhancement in production for industrial connection.

Section 9

10. List of equipment proposed to be installed along with their connected load.

Section 10

11. Resolution for authorization in respect of where connection required in name of firm, limited/Pvt. Ltd. firm, company etc.

Section 11

12. Registration from Industries Department wherever applicable.

Section 12

13. Extract of project report relevant to power and process requirement (in case of industries).

Section 13

14. Copy of the relevant section of the current tariff order that provides details of the tariff category opted by the consumer and duly signed by him. This will be appended with agreement after completion of formalities.

Section 14

12. Stamp Duty. The consumer agrees to bear the cost of the stamp duty and all costs incidental to the execution of this Agreement in full.

Section 12

13. Disputes. This agreement shall be deemed to be entered into at the location of registered office of the licensee and all disputes and claim, if any, in respect of this contract are to be settled at such locations as mentioned in the Guidelines for Redressal of Consumer Grievances or be triable only in any competent court situated within the area of operation of the licensee.

Section 13

4. The energy supplied to the Consumer by the............ Discom shall be on 3 phase, 50 cycles, alternating current system at a normal pressure of ____ volts. The frequency and pressure of the electrical energy at the point of supply to the feeders of the Consumer shall be subject to the fluctuations that are ordinary, usual and incidental to the generation and transmission of electrical energy, but such fluctuations shall not, except for reasons beyond the control of the ............ Discom, b

Section 4

10. All transformers, switch-gear and other electrical equipments in the installation of the Consumer and also those directly connected to the feeders or lines of the ............ Discom shall be of suitable design and be maintained to the reasonable satisfaction of the ............ Discom. The setting of fuses and relays on the Consumer's control-gear as well as the rupturing capacity of any of his circuit breakers shall be subject to the approval of the ............ Discom. The starting curren

Section 10

11. Save as provided herein the supply shall be available continuously except in cases of force majeure as provided in Electricity Supply Code 2013 as in force from time to time, or any cause over which the ............ Discom has no control and in any such case the ............ Discom shall not be responsible for any loss or damages for such discontinuance of the energy but shall recommence the supply as soon as it reasonably can.

Section 11

14. The readings/MRI of the meter referred to in clause 7 hereof shall be taken by the authorised representative of the Consumer and the ............ Discom as specified in Electricity Supply Code 2013 as in force from time to time and the reading so taken shall be binding and conclusive between the Consumer, and the ............ Discom as to the amount of electrical energy supplied to the Consumer. In the event of the main meter or the ancillary equipment forming a part thereof being found defe

Section 7

15. The Consumer shall at all times allow the officer or servant of the ............ Discom generally or specially authorised by the Chief Engineer in this behalf to inspect the electrical equipment of the Consumer for all or any of the purposes connected with the supply of electrical energy to the Consumer under this Agreement.

Section 15

16. The meters shall be re-calibrated and standardised if so desired, by either party, by means of standard instruments by the ............ Discom in the presence of the Consumer or his representative; provided however that the ............ Discom may; conduct test-checks of the metering equipments at intervals of six months or such other period as specified in the Electricity Supply Code 2013 as in force from time to time.

Section 16

17. The Consumer shall be entitled on application to the ............ Discom or its authorised representative in this behalf to have a special test of the meters carried out at any time and the expense of such test shall be borne by the ............ Discom or the Consumer according as the meters are found to be defective or correct as a result of such a test, such meters shall be deemed to be correct if the limits of error do not exceed those laid down in the Indian Electricity Rules, 1956, as a

Section 17

18. For the purpose of this Agreement the maximum demand of the supply to Consumer in each month shall be equal to four times the largest amount of Kwh/kvah delivered at the point of supply of the consumer in the premises during any consecutive fifteen minutes in that month as per sliding window principle of measurement of demand.

Section 18

19. The Consumer shall pay to the ............ Discom every month, charges for the electrical energy supplied to the Consumer during the preceding month at the ............ Discom's tariff applicable to the class of service and in force from time to time. A copy of the current H.T. Tariff order no. ________________ dated____ issued by MPERC as amended applicable to the Consumer is set out in the Schedule attached to this Agreement.

Section 19

21. Special conditions and/or charges.

Section 21

23. The average monthly power factor of the Consumer's installation shall not be less than 90 percent. Should it, however, fall below 90 per cent or as may be specified in tariff the Consumer shall pay such additional charges as may be specified in the tariff. Should the average power, factor fall below 70 percent, the ............ Discom may, without prejudice to its right to recover the minimum charges under the Agreement, disconnect the Consumer's installation till the arrangements are made t

Section 23

29. Where more than one method of charging of the electricity consumed exist in the tariffs applicable to the class of service, the consumer shall exercise his option for one of them at the time of commencement of this Agreement as defined in clause 2 (a) hereof. After the commencement of the Agreement no further option in the selection of alternative tariffs will be allowed except twice during the period the Agreement remain in force. Any automatic change in category that may be forced by such

Section 2

30. The Consumer shall not without the previous consent in writing of the ............ Discom assign, transfer or part with the benefit of this Agreement either wholly or partially in favour of any person.

Section 30

31. In the event of the Consumer failing to comply with the terms of this Agreement or any of them then in addition to the powers conferred on the ............ Discom by the Acts, Rules and Regulations referred to in clause 36 hereof, it shall be lawful for the ............ Discom after giving due notice in writing to the Consumer to discontinue the supply of energy to the Consumer or even disconnect supply forthwith where permitted under law, rules & regulations. The ............ Discom shall h

Section 36

32. In the event of the supply of energy being discontinued by the ............ Discom in consequence of any breach or default on the part of the consumer entitling the ............ Discom so to do under the provisions of the Acts, Rules and Regulations referred to in clause 38 hereof, the amount of charges for the electrical energy already supplied and all other moneys then payable under this Agreement shall become due and recoverable forthwith; Provided always and it is hereby expressly agreed

Section 38

33. If at any time during the continuance of this Agreement the Consumer shall-

Section 33

34. This Agreement for supply of electrical energy supersedes all previous contracts for supply of energy to the premises entered into and executed by the ............ Discom and the Consumer namely:-

Section 34

35. Notwithstanding that the ............ Discom may not have taken advantage of some previous breach, defaults or event of like nature on the part of the Consumer, it shall be lawful for the ............ Discom to enforce the terms and conditions of these presents in the event of a subsequent breach, default or event of like nature.

Section 35

38. Where any expression used in this Agreement is not defined in it or the Electricity Act, 2003, Central Electricity Authority (Measures relating to Safety and Electric Supply)Regulations, 2010, MP Vidyut Sudhar Adhiniyam 2000 and Regulations framed thereunder or in General Clause Act, 1897, such expression shall have the meaning generally assigned to it in the Electricity Supply Industry.

Section 38

39. This Agreement shall be deemed to be entered into at ............. and all disputes and claim, if any out of and in respect of this contract are to be settled at .............. or be triable only in any competent court situated at ...........

Section 39