9. Metering.

(a) Purchase the meter, MCB/CB and associated equipment himself from a vendor(s) provided the equipments are of a make and specification approved by the Distribution Licensee from time-to-time; or
(b) Require that the meter, MCB/CB and associated equipment be supplied by the Distribution Licensee.
(a) For LT connections - Electronic Meters with MDI
(b) For HT/EHT consumers - 3 Phase Tri-vector meters with MDI. The meters shall have a facility for "Time of the Day" metering and storage of at least 45 days. The consumer shall have the option to install meter having facility to record peak hours MDI in addition to above features
9.2 Supply and Installation of Meters and MCBs/CBs.
9.3 Reading of Meters.
9.4 Testing of Meters.
(a) Single phase meters: Once every five (5) years
(b) LT 3-phase meters: Once every three (3) years
(c) HT/EHT meters including MDI: At least once every year Wherever applicable, CT and PT shall also be tested along with meters
9.5 Replacement of Meters.
(a) If the meter was owned by the consumer, the Distribution Licensee shall inform the consumer to replace the meter and associated equipment as per provisions of clauses 9.1.1 to 9.1.5 of these Regulations within 7 days, after which the Distribution Licensee may be empowered to install a new meter and start charging meter rent, if applicable.
(b) If the meter was owned by the Distribution Licensee, the Distribution Licensee shall install a new meter at its own cost: Provided that in both the scenarios detailed in sub clauses 9.5.10 (a) and 9.5.10 (b), the Distribution Licensee shall recover the cost of the meter from the consumer in proportion of the remaining useful life of the meter (useful life of the meter as per the depreciation schedule of the Commission - no of years after date of first instalment of the aforesaid meter) that was rendered defective/burnt: