[131. Supervision
(ii) The electrical supervisor so appointed shall be the person holding a valid Electrical Supervisor's Certificate of Competency, covering mining installation issued under sub-rule (1) of rule 45.
(iii) If the Inspector considers necessary for the compliance with the duties specified in this rule, he may direct the owner or agent of the mine to appoint one or more electricians who shall be persons holding license under sub-rule (1) of rule 45.
(a) thorough examination of all apparatus (including the testing of earth conductors and metallic coverings for continuity) as often as may be necessary to prevent danger;
(b) examination and testing of all new apparatus, and of all apparatus, re-erected in the mine before it is put into service in a new position.
(ii) The results of all tests carried out in accordance with the provisions of sub-rule (3) shall be recorded in the log-sheets prepared in the form set out in Annexure XII.]
Section 130 • The Indian Electricity Rules, 1956
130. Earthing of neutral points
the-indian-electricity-rules-1956-sec-130.json
•
Section 130
{
"act_title": "The Indian Electricity Rules, 1956",
"act_slug": "the-indian-electricity-rules-1956",
"section_label": "Section",
"section": {
"number": "130",
"title": "130. Earthing of neutral points",
"chapter": null,
"content": "[131. Supervision\n(ii) The electrical supervisor so appointed shall be the person holding a valid Electrical Supervisor's Certificate of Competency, covering mining installation issued under sub-rule (1) of rule 45.\n(iii) If the Inspector considers necessary for the compliance with the duties specified in this rule, he may direct the owner or agent of the mine to appoint one or more electricians who shall be persons holding license under sub-rule (1) of rule 45.\n(a) thorough examination of all apparatus (including the testing of earth conductors and metallic coverings for continuity) as often as may be necessary to prevent danger;\n(b) examination and testing of all new apparatus, and of all apparatus, re-erected in the mine before it is put into service in a new position.\n(ii) The results of all tests carried out in accordance with the provisions of sub-rule (3) shall be recorded in the log-sheets prepared in the form set out in Annexure XII.]",
"footnote": "",
"is_definition": false,
"sort_order": 125
},
"prev_section": "129",
"next_section": "132"
}