63. Procedure for lodging complaint:.

(ii) All complaints received shall be immediately acknowledged by providing a complaint number to the complainant. The Centralised Complaint Receiving Centre shall keep a detailed log of all complaints received in a database/ register.
(iii) In case the Centralised Complaint Receiving Center is aware that the complaint is due to any of the reasons listed at (e) – (j) in para 62(iii) above, he shall inform the complainant the reason(s) for power failure and also indicate the approximate time required for restoration of power supply. Nevertheless, he shall register each complaint received and issue a unique complaint number for such complaints also.
(iv) The Centralised Complaint Receiving Center shall communicate the complaint to the mobile service groups at the concerned Complaint Centers. The mobile service group would then proceed to the address provided by the complainant, investigate the cause of complaint and resolve the problem. Upon resolution of the complaint, the Centralised Complaint Receiving Center shall be informed of the status who would log the same in the record.
(v) In case, the cause of the complaint is more severe, due to any reason(s) listed at (e)–(j) above, the Mobile service group shall inform the nature of the fault and approximate time required for rectification to the complainant and also to the Centralized Complaint Receiving Center. He shall also inform the next higher authority to take appropriate action to deploy additional resources and materials to resolve the complaint.
(vi) All complaints shall be monitored by the Centralized Complaint Receiving Center regarding resolution of the complaint within the stipulated time limit as given below:
Table 8
Table 8
Nature of cause of power supply failure
Nature of cause of power supply failure
Maximum Time Limit for restoration.
Maximum Time Limit for restoration.
Fuse blown out or MCB tripped
Within three hours for Urban areas Within eight hours for
Rural areas
Service line broken
Within six hours for Urban areas
Service line snapped from the pole
Within twelve hours for Rural areas
Fault in distribution mains
Temporary Supply to be restored within four hours from
alternate source, wherever feasible. Rectification of fault
and thereafter Restoration of normal power supply within twelve
hours
Distribution transformer failed/burnt
Temporary Restoration of supply through mobile transformer or
another backup source within eight hours, wherever
feasible Replacement of failed transformer within forty-eight
hours
HT mains failed
Temporary restoration of power supply within four hours,
wherever feasible. Rectification of fault within twelve hours
Problem in grid (33 kV or 66 kV) substation
Restoration of supply from alternate source, wherever feasible
within six hours Roster load shedding may be carried out to
avoid overloading of alternate source. Repair and restoration
of supply within forty-eight hours
Failure of Power Transformer
Restoration of supply from alternate source, wherever feasible
within six hours Roster load shedding may be carried out to
avoid overloading of alternate source. Replacement action to
be intimated to the Commission within seventy-two hours and
replacement of power transformer within 20 days
Burnt meter
Restoration of supply by bypassing the burnt meter within six
hours Replacement of burnt meter within three days
Street light complaint
Restoration within seventy-two hours
(vii) In case no information is received from Mobile Service Group by the Complaint Center/Centralized Call Center within the stipulated time given above, the Call Center/Complaint Center shall escalate the complaint to the concerned Authorized Officer/District Manager.
(viii) The escalation process shall be inbuilt within the system and shall escalate automatically every two hours up to the level of GM (Operations) using the server-based system until the resolution of the complaint is logged. All complaint-handling officers shall be provided with mobile wireless based communication devices for the dissemination of complaint related information.
Voltage Complaints
(x) In the case of Low / High voltage, the complaint should be lodged at the Centralised Call Center/Complaint Center giving name, address, telephone no., if any, of the complainant along with brief nature of the problem faced. The operator on duty shall register the complaint and intimate the complaint number in every case.
(xi) The Centralized Call Center/Complaint Center shall communicate the complaint to the mobile service groups at the concerned Service Centres. The mobile service group would then proceed to the address provided by the complainant, investigate the cause of complaint and resolve the problem.
(xii) In case problem is local e.g. due to loose connection of service line, the mobile group shall rectify the fault themselves. In case the voltage problem is due to some other reason(s), such as, deficiency in the system, the mobile group shall bring this to the notice of the Area Assistant Manager/Designated Officer.
(xiii) The Area Assistant Manager/Designated Officer shall ascertain if the problem can be rectified by changing the Tap position of the transformer or proper control of the capacitors installed in the system and if possible, he shall do so. However, in case the Assistant Manager finds that problem is due to deficiency in the distribution system requiring up-gradation of distribution lines, transformers, capacitors etc., he shall inform the District Manager for taking further necessary action.
(xiv) The consumer shall also be informed of the need to switching on or switching off of the capacitors installed in his premises when the connected load is not in operation which shall also help the consumer to extend the life of the capacitors besides avoiding over voltage problems, if the capacitors are not controlled automatically.
(xv) The voltage problem shall be resolved with the time limits specified in Table given below:
Table 9
Table 9
No.
No.
Cause of problem related to voltage variation
Cause of problem related to voltage variation
Time limit for the rendering service
Time limit for the rendering service
Authorised Person
Authorised Person
Next higher level for complaint
Next higher level for complaint
1.
Local problem
Within 4 hours
Assistant Manager
District Manager
2.
Tap of transformer
Within 3 days
Assistant Manager
District Manager
3.
Repair of distribution line / transformer / capacitor
Within 30 days
Assistant Manager
District Manager
4.
Installation and Up-gradation of HT / LT System
Within 90 days
Assistant Manager
District Manager
(xvi) The Licensee shall submit to the Commission monthly MIS reports giving category-wise number of complaints received and the complaints, which could not be resolved within the stipulated time and reasons thereof,
(xvii) Scheduled outages/load shedding:
Metering and Billing Complaints
(xviii) Metering and billing complaints could be due to one of the following reasons:
(a) Delay in providing new connection.
(b) Delay in transfer of connection.
(c) Delay in enhancement/reduction of load.
(d) Replacement of defective/burnt meter.
(e) Change of category.
(f) Disconnection and restoration of supply.
(g) Seals missing.
(h) Wrong billing.
(i) Vacation of premises/change of occupancy.
(xix) In case of metering and billing complaints, these shall be referred to Commercial Manager. These shall be resolved in the time frame allowed as per these Regulations and consumer shall be apprised accordingly.
(xx) Monitoring of Complaints
(a) Daily MIS reports shall be provided to the CEO, and GM (Operations) giving the number and status of pending complaints.
(b) MIS reports, giving category-wise total number of complaints received and details of the complaints which could not be attended within the stipulated time, along with reasons thereof, shall be submitted to the Commission on monthly basis both for power supply and metering, billing and other commercial complaints.