Schedule
Serial. No.
Section of the Act empowering grant of exemption
Class of factories
Nature of work exempted
Extent of exemption
Conditions
1
2
3
4
5
6
1
64 (2)(a) and 64(3)
All factories
Urgent repairs
Secs. 51, 52, 53, 54, 55, 56 and 61
(i) Total hours of work done by any
worker including the hours of normal work, if any, shall not
exceed 15 on any one day, 39 during any three consecutive days or
66 during each period of seven consecutive days commencing from
his first employment on such repairs.
(ii) No worker shall be employed
for more than 14 consecutive days without a rest period of 24
consecutive hours, and as the work permits a rest period of one
hour shall be permitted to each worker during his daily working
hours.
(iii) Within 24 hours of the commencement of the work, a
notice shall be sent to the Inspector describing the nature of
the urgent repairs, stating the names of the persons employed,
the exact time of commencement of work and the period probably
required for its completion. A copy of the above notice shall be
displayed in accordance with Section 108 (2) of the Act before
the workers are engaged on urgent repairs.
2
64 (2)(b) and 64 (3)
All factories
(1) Maintenance work in the
mechanic shop, the smithy or the foundry or in connection with
the mill-gearing, the electric driving or lighting apparatus, the
mechanical or electrical lifts or the steam or water pipe or
pumps of a factory.
(2) Work of examining or repairing
any machinery or other part of the plan which is necessary to
earn on the work in factory.
(3) Work in boiler houses and engine rooms, such a lighting
fires in order to raise steam or generate gas preparatory to the
commencement of regular work in the factory.
Secs 51, 54 55, 56 and 61
(i) These exemptions shall apply in
case of the limited number of maintenance staff approved in
writing by the Chief inspector of Factories. The occupier or
manager of the factories before; availing of these exemptions
shall apply to the Chief Inspector for necessary approval of
staff.
(ii) No worker shall be employed
for more than 10 hours in any one day, and spread over hours
shall be limited to 12 in any day.
(iii) Total number of hours of overtime work done by any
worker shall not exceed 50 in any one quarter.
3
64 (2)(c) and 64(3)
All factories
Work performed by drivers on lighting, ventilating and
humidifying apparatus, work performed by live pumpmen, work of
loading, unloading or transporting raw materials in factories
where such work is intermittent and mainly outside the factory
premises
Secs. 51, 54, 58, 61
(i) The exemption shall apply to a
limited number of adult male workers to be approved by the Chief
Inspector of Factories. A list of such workers shall be submitted
to the Chief Inspector of Factories for approval prior to the
exemptions being availed.
(ii) No worker shall be employed
for more than 10 hours in any one day.
(iii) Total number of hours of
overtime work done by any worker shall not exceed 50 in any one
quarter.
(iv) Spread over hours shall not exceed 12.
4
64(2)(d) and 64(3)
Oil tank installations
Work in connection with pumping operation
Secs. 51, 52, 54, 55, 56 and 61
(i) The worker shall ordinarily be
employed on daily eight hours shifts.
(ii) No such worker shall be employed for more than 14
consecutive days without a rest period of 24 consecutive hours.
Oil Refineries
All continuous process work in refining crude petroleum
Do
(iii) No worker shall be employed for more than 10 hours in
any one day except to enable a shift worker to work a part or the
whole of a subsequent shift in the absence of a worker who has
failed to report for duty in time for a part of the whole shift,
in which case the daily maximum hours of work shall be limited to
16.
Iron and Steel factory
All work on steel furnace
Do
(iv) Total number of hours of over time work done by any
worker shall not exceed 50 in any one quarter.
Calcining work
Continuous process of Calcination of Coke
Do.
(v) The system of shift used in the
factory shall have the approval of the Chief Inspector.
(vi) Spread over hours shall not exceed 12 except to enable a
shift worker to work a part or the whole of a. subsequent shift
in the absence of a worker who has failed to report for duty inn
time or for the whole shift.
Hydroelectric Public supply factory
Operation and maintenance of prime movers and auxiliaries,
transformers and switches
Sections 51, 52, 54, and 61
(i) No worker shall be employed for more than 14 consecutive
days without a rest period of 24 consecutive hours.
Public Electric Supply companies generating
electricity with thermal power
Workers attending to boilers, turbine, engine, generators,
motors, switch boards, pumps, batteries and auxiliaries.
Do.
(ii) No worker shall be employed
for more than 10 hours in any one day except to facilitate a
change of shift.
(iii) Total overtime hours of work shall not exceed 50 in any
quarter.
Electrical Transforming Factories
Operation and maintenance of transforming plant, switches and
synchronous condensers
Do.
Do.
Water works and water pumping station
The work of attending to boilers, prime movers, pumps and
auxiliaries.
Do.
Do.
Distilleries
Attendance of boilers, Prime movers and pumps, extraication of
sugar from various bases, fermentation of sugar juice and wash
distillation processes.
Do.
Do.
Chemical factories.
Work on sulphur burners, chambers, concentrators and pumps,
roasting furnace, manufacture of hydrochloric acid, nitric acid,
sulphuric acid, sulphates, sulphides, nitrates, chlorides,
superphosphates work on steam service.
Do.
(i) No worker shall be employed for
more than 14 consecutive days without a rest period of 24
consecutive hours.
(ii) No worker shall be employed
for more than 10 hours in any one day except enable a shift
worker to a part of the whole of a subsequent shift in the
absence of worker who has failed to report for duty in time or
for the whole shift.
(iii) Total overtime hours of work shall not exceed 50 in any
quarter.
Vegetable oil Hydrogeneration factories
Work of refining, bleaching, filtering, generation of
hydrogen. Hydrogeneration and deodorising processes, compressing
of oxygen,charging of cylinders, work on power equipment.
Do.
(i) No worker shall be employed;
for more than 14 consecutive days without a rest period of 24
consecutive hours.
(ii) No worker shall be employed
for more than 10 hours in any one day except to enable a shift
worker to work a part or the whole of subsequent shift in the
absence of a worker who has failed to report for duty in time or
for the whole shift.
(iii) Total overtime hours of work shall not exceed 50 in any
one quarter.
Ice factories
Work of engine and compressor drivers, assistants and oilers,
work on ice making machinery.
Do.
Do.
Glass factories
Work in attending to furnace. All process work from mixing of
batch to removal of manufactured glass ware from the lears.
Sections 52 and 55. Section 52
No worker shall be employed for more than 14 consecutive days
without a rest period of 24 consecutive hours.
Paper factories
All work on paper making machinery and on the generation and
supply of power connected therewith.
Sections 54 and 55
No worker shall be employed for more the 10 hours in any one
day, and for more than 14 consecutive days without a rest period
of 24 consecutive hours.
Paper factories
Work on choppers, digesters, kneaders, strainers and washers,
beaters, paper making machines, pumping plant, reelers, cutters
and power plant.
Sections 52, 54 and 55
Do.
Plywood factories
The continuous process work of cutting, gumming, pressing and
drying of plywood.
Section 83 • The Assam Factories Rules, 1950
83. Exemption of certain adult male workers.
the-assam-factories-rules-1950-1950-sec-83.json
•
Section 83
{
"act_title": "The Assam Factories Rules, 1950",
"act_slug": "the-assam-factories-rules-1950-1950",
"section_label": "Section",
"section": {
"number": "83",
"title": "83. Exemption of certain adult male workers.",
"chapter": null,
"content": "Schedule\nSerial. No.\nSection of the Act empowering grant of exemption\nClass of factories\nNature of work exempted\nExtent of exemption\nConditions\n1\n2\n3\n4\n5\n6\n1\n64 (2)(a) and 64(3)\nAll factories\nUrgent repairs\nSecs. 51, 52, 53, 54, 55, 56 and 61\n(i) Total hours of work done by any\n\t\t\t\tworker including the hours of normal work, if any, shall not\n\t\t\t\texceed 15 on any one day, 39 during any three consecutive days or\n\t\t\t\t66 during each period of seven consecutive days commencing from\n\t\t\t\this first employment on such repairs.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 14 consecutive days without a rest period of 24\n\t\t\t\tconsecutive hours, and as the work permits a rest period of one\n\t\t\t\thour shall be permitted to each worker during his daily working\n\t\t\t\thours.\n(iii) Within 24 hours of the commencement of the work, a\n\t\t\t\tnotice shall be sent to the Inspector describing the nature of\n\t\t\t\tthe urgent repairs, stating the names of the persons employed,\n\t\t\t\tthe exact time of commencement of work and the period probably\n\t\t\t\trequired for its completion. A copy of the above notice shall be\n\t\t\t\tdisplayed in accordance with Section 108 (2) of the Act before\n\t\t\t\tthe workers are engaged on urgent repairs.\n2\n64 (2)(b) and 64 (3)\nAll factories\n(1) Maintenance work in the\n\t\t\t\tmechanic shop, the smithy or the foundry or in connection with\n\t\t\t\tthe mill-gearing, the electric driving or lighting apparatus, the\n\t\t\t\tmechanical or electrical lifts or the steam or water pipe or\n\t\t\t\tpumps of a factory.\n(2) Work of examining or repairing\n\t\t\t\tany machinery or other part of the plan which is necessary to\n\t\t\t\tearn on the work in factory.\n(3) Work in boiler houses and engine rooms, such a lighting\n\t\t\t\tfires in order to raise steam or generate gas preparatory to the\n\t\t\t\tcommencement of regular work in the factory.\nSecs 51, 54 55, 56 and 61\n(i) These exemptions shall apply in\n\t\t\t\tcase of the limited number of maintenance staff approved in\n\t\t\t\twriting by the Chief inspector of Factories. The occupier or\n\t\t\t\tmanager of the factories before; availing of these exemptions\n\t\t\t\tshall apply to the Chief Inspector for necessary approval of\n\t\t\t\tstaff.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 10 hours in any one day, and spread over hours\n\t\t\t\tshall be limited to 12 in any day.\n(iii) Total number of hours of overtime work done by any\n\t\t\t\tworker shall not exceed 50 in any one quarter.\n3\n64 (2)(c) and 64(3)\nAll factories\nWork performed by drivers on lighting, ventilating and\n\t\t\t\thumidifying apparatus, work performed by live pumpmen, work of\n\t\t\t\tloading, unloading or transporting raw materials in factories\n\t\t\t\twhere such work is intermittent and mainly outside the factory\n\t\t\t\tpremises\nSecs. 51, 54, 58, 61\n(i) The exemption shall apply to a\n\t\t\t\tlimited number of adult male workers to be approved by the Chief\n\t\t\t\tInspector of Factories. A list of such workers shall be submitted\n\t\t\t\tto the Chief Inspector of Factories for approval prior to the\n\t\t\t\texemptions being availed.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 10 hours in any one day.\n(iii) Total number of hours of\n\t\t\t\tovertime work done by any worker shall not exceed 50 in any one\n\t\t\t\tquarter.\n(iv) Spread over hours shall not exceed 12.\n4\n64(2)(d) and 64(3)\nOil tank installations\nWork in connection with pumping operation\nSecs. 51, 52, 54, 55, 56 and 61\n(i) The worker shall ordinarily be\n\t\t\t\temployed on daily eight hours shifts.\n(ii) No such worker shall be employed for more than 14\n\t\t\t\tconsecutive days without a rest period of 24 consecutive hours.\nOil Refineries\nAll continuous process work in refining crude petroleum\nDo\n(iii) No worker shall be employed for more than 10 hours in\n\t\t\t\tany one day except to enable a shift worker to work a part or the\n\t\t\t\twhole of a subsequent shift in the absence of a worker who has\n\t\t\t\tfailed to report for duty in time for a part of the whole shift,\n\t\t\t\tin which case the daily maximum hours of work shall be limited to\n\t\t\t\t16.\nIron and Steel factory\nAll work on steel furnace\nDo\n(iv) Total number of hours of over time work done by any\n\t\t\t\tworker shall not exceed 50 in any one quarter.\nCalcining work\nContinuous process of Calcination of Coke\nDo.\n(v) The system of shift used in the\n\t\t\t\tfactory shall have the approval of the Chief Inspector.\n(vi) Spread over hours shall not exceed 12 except to enable a\n\t\t\t\tshift worker to work a part or the whole of a. subsequent shift\n\t\t\t\tin the absence of a worker who has failed to report for duty inn\n\t\t\t\ttime or for the whole shift.\nHydroelectric Public supply factory\nOperation and maintenance of prime movers and auxiliaries,\n\t\t\t\ttransformers and switches\nSections 51, 52, 54, and 61\n(i) No worker shall be employed for more than 14 consecutive\n\t\t\t\tdays without a rest period of 24 consecutive hours.\nPublic Electric Supply companies generating\n\t\t\t\telectricity with thermal power\nWorkers attending to boilers, turbine, engine, generators,\n\t\t\t\tmotors, switch boards, pumps, batteries and auxiliaries.\nDo.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 10 hours in any one day except to facilitate a\n\t\t\t\tchange of shift.\n(iii) Total overtime hours of work shall not exceed 50 in any\n\t\t\t\tquarter.\nElectrical Transforming Factories\nOperation and maintenance of transforming plant, switches and\n\t\t\t\tsynchronous condensers\nDo.\nDo.\nWater works and water pumping station\nThe work of attending to boilers, prime movers, pumps and\n\t\t\t\tauxiliaries.\nDo.\nDo.\nDistilleries\nAttendance of boilers, Prime movers and pumps, extraication of\n\t\t\t\tsugar from various bases, fermentation of sugar juice and wash\n\t\t\t\tdistillation processes.\nDo.\nDo.\nChemical factories.\nWork on sulphur burners, chambers, concentrators and pumps,\n\t\t\t\troasting furnace, manufacture of hydrochloric acid, nitric acid,\n\t\t\t\tsulphuric acid, sulphates, sulphides, nitrates, chlorides,\n\t\t\t\tsuperphosphates work on steam service.\nDo.\n(i) No worker shall be employed for\n\t\t\t\tmore than 14 consecutive days without a rest period of 24\n\t\t\t\tconsecutive hours.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 10 hours in any one day except enable a shift\n\t\t\t\tworker to a part of the whole of a subsequent shift in the\n\t\t\t\tabsence of worker who has failed to report for duty in time or\n\t\t\t\tfor the whole shift.\n(iii) Total overtime hours of work shall not exceed 50 in any\n\t\t\t\tquarter.\nVegetable oil Hydrogeneration factories\nWork of refining, bleaching, filtering, generation of\n\t\t\t\thydrogen. Hydrogeneration and deodorising processes, compressing\n\t\t\t\tof oxygen,charging of cylinders, work on power equipment.\nDo.\n(i) No worker shall be employed;\n\t\t\t\tfor more than 14 consecutive days without a rest period of 24\n\t\t\t\tconsecutive hours.\n(ii) No worker shall be employed\n\t\t\t\tfor more than 10 hours in any one day except to enable a shift\n\t\t\t\tworker to work a part or the whole of subsequent shift in the\n\t\t\t\tabsence of a worker who has failed to report for duty in time or\n\t\t\t\tfor the whole shift.\n(iii) Total overtime hours of work shall not exceed 50 in any\n\t\t\t\tone quarter.\nIce factories\nWork of engine and compressor drivers, assistants and oilers,\n\t\t\t\twork on ice making machinery.\nDo.\nDo.\nGlass factories\nWork in attending to furnace. All process work from mixing of\n\t\t\t\tbatch to removal of manufactured glass ware from the lears.\nSections 52 and 55. Section 52\nNo worker shall be employed for more than 14 consecutive days\n\t\t\t\twithout a rest period of 24 consecutive hours.\nPaper factories\nAll work on paper making machinery and on the generation and\n\t\t\t\tsupply of power connected therewith.\nSections 54 and 55\nNo worker shall be employed for more the 10 hours in any one\n\t\t\t\tday, and for more than 14 consecutive days without a rest period\n\t\t\t\tof 24 consecutive hours.\nPaper factories\nWork on choppers, digesters, kneaders, strainers and washers,\n\t\t\t\tbeaters, paper making machines, pumping plant, reelers, cutters\n\t\t\t\tand power plant.\nSections 52, 54 and 55\nDo.\nPlywood factories\nThe continuous process work of cutting, gumming, pressing and\n\t\t\t\tdrying of plywood.",
"footnote": "",
"is_definition": false,
"sort_order": 86
},
"prev_section": "82",
"next_section": "55"
}