(a) Wind Electricity Generator (WEG) shall be permitted in all land use zones.
(b) The minimum required land size shall be not less than 150m x 150m
(c) The minimum width of public road or uninterrupted access way/passage shall be not less than 7mtrs.
(d) The reservation of land for community recreational purposes shall not be insisted for development of Wind Electricity Generator (WEG).
(e) Subdivision rules shall not be applicable
(a) Chief Electrical Inspector to Government (CEIG) Approval under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2010.
(b) Location Clearance Approval or Noted for Record, as applicable, issued by Tamil Nadu Generation and Distribution Corporation (TANGEDCO).
(c) No Objection Certificate issued by the Civil Aviation and Defence Authorities concerned, as applicable for WEG height clearance.
Schedule I
Form
Form
Application for Planning Permission/Building Permit for installation of Wind Electricity Generator
Application for Planning Permission/Building Permit for installation of Wind Electricity Generator
........................
Signature of the applicant
(continued)
Section 45 • Tamil Nadu Combined Development and Building Rules, 2019
45. Wind Electricity Generator.
tamil-nadu-combined-development-and-building-rules-2019-sec-45.json
•
Section 45
{
"act_title": "Tamil Nadu Combined Development and Building Rules, 2019",
"act_slug": "tamil-nadu-combined-development-and-building-rules-2019",
"section_label": "Section",
"section": {
"number": "45",
"title": "45. Wind Electricity Generator.",
"chapter": null,
"content": "(a) Wind Electricity Generator (WEG) shall be permitted in all land use zones.\n(b) The minimum required land size shall be not less than 150m x 150m\n(c) The minimum width of public road or uninterrupted access way/passage shall be not less than 7mtrs.\n(d) The reservation of land for community recreational purposes shall not be insisted for development of Wind Electricity Generator (WEG).\n(e) Subdivision rules shall not be applicable\n(a) Chief Electrical Inspector to Government (CEIG) Approval under the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2010.\n(b) Location Clearance Approval or Noted for Record, as applicable, issued by Tamil Nadu Generation and Distribution Corporation (TANGEDCO).\n(c) No Objection Certificate issued by the Civil Aviation and Defence Authorities concerned, as applicable for WEG height clearance.\nSchedule I\nForm\nForm\nApplication for Planning Permission/Building Permit for installation of Wind Electricity Generator\nApplication for Planning Permission/Building Permit for installation of Wind Electricity Generator\n........................\nSignature of the applicant\n(continued)",
"footnote": "",
"is_definition": false,
"sort_order": 45
},
"prev_section": "44",
"next_section": "1"
}