(i) For generating stations - On the basis of hourly generation data available at State Load Despatch Centre.
(ii) For interface points of Discoms -The data shall be assessed on the basis of data available for previous week of the ABT meter installed at the same interface point and shall be adjusted in line with load pattern of the adjoining transformers/feeder.
(iii) For Open Access Customers (OAC) - In case of OAC's, if ABT meter data of main meter / check meter / standby meter or any other meter is not available, then State Load Despatch Centre shall substitute the actual with schedule while calculating the deviation charges.
Section 6 • Madhya Pradesh Electricity Balancing and Settlement Code, 2015
6. Energy Metering.
madhya-pradesh-electricity-balancing-and-settlement-code-2015-sec-6.json
•
Section 6
{
"act_title": "Madhya Pradesh Electricity Balancing and Settlement Code, 2015",
"act_slug": "madhya-pradesh-electricity-balancing-and-settlement-code-2015",
"section_label": "Section",
"section": {
"number": "6",
"title": "6. Energy Metering.",
"chapter": null,
"content": "(i) For generating stations - On the basis of hourly generation data available at State Load Despatch Centre.\n(ii) For interface points of Discoms -The data shall be assessed on the basis of data available for previous week of the ABT meter installed at the same interface point and shall be adjusted in line with load pattern of the adjoining transformers/feeder.\n(iii) For Open Access Customers (OAC) - In case of OAC's, if ABT meter data of main meter / check meter / standby meter or any other meter is not available, then State Load Despatch Centre shall substitute the actual with schedule while calculating the deviation charges.",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
"prev_section": "5",