6. Procedure for providing fresh Electricity Service Connection.

(i) Issue a duly authorized acknowledgement of each application form accepted.
(ii) Inform an applicant upon request of the status of his application and the reasons if any, for non-disposal of the application.
6.2 Processing Application and effecting Electricity supply.
Time schedule for disposal of application for fresh electricity supply or additional supply.
Time schedule for disposal of application for fresh electricity supply or additional supply.
Sl.No.
Sl.No.
Item of Disposal
Item of Disposal
Category of service
Category of service
Time limit for disposal
Time limit for disposal
1
Notice of inspection on receipt of application.
(a) L.T service
Within 3 days of receipt of application.
(b) H.T service
Within 7 days of receipt of application.
(c) E.H.T service
Within 15 days of receipt of application.
2
Inspection for fixing position of distribution
line/service line and meter and accessories in consumer premises.
(a) L.T service
Urban
Within 10 days of receipt of application.
Rural
Within 15 days of receipt of application.
(b) H.T service
Within 15 days of receipt of application.
(c) E.H.T service
Within 30 days of receipt of application.
3
Issue of 15 days notice for deposit of charges
and security amount and execution of agreement.
(a) LT service without extension &
upgradation
Within 3 days after inspection
(b) LT service with LT extension &
installation of D/S/S and or upgradation.
Within 7 days after inspection
(c) L.T. service with extension &
installation of D/S/S and /or upgradation of system.
Within 15 days after inspection
(d) H.T. service
Within 30 days after inspection
(e) E.H.T service
Within 45 days after inspection
4
Time allowed for deposit of charges and security
amount and execution of agreement.
All categories L.T, H.T and EHT.
Within 15 days of issue of notice.
5
Notice for intimation that supply is available
and testing consumer for installation.
(a) L.T. service
without Ext. and upgradation.
(i) Urban
Within 7 days of deposit of charges
(ii) Rural
Within 15days of deposit of charges
(b) L.T service with L.T line EXT only
(i) Urban
30 days of deposit of charges
(ii) Rural
45 days of deposit of charges
(c) L.T Service with L.T extension installation
of and Dist Sub-station and/or upgradation.
(i) Urban
45 days of deposit of charges
(ii) Rural
60 days of deposit of charges
(d) HT without Extension
Within 27 days of deposit of charges.
(e) HT with Extension
Within 90 days of deposit of charges.
(f) EHT (this will necessarily entail Extension)
Within 180 days
6
Energization and commencement of electricity
supply.
L.T. service
Within 2 days after testing
HT service Within
3 days after testing
EHT service Within
3 days after testing
[ Note - The time for providing new connection which does not require any extension should be limited to 30 days from the receipt of application.]
Note
6.3 Temporary supply.
(a)
Premises/site inspection and issue of notice to
deposit charges in advance.
LT service within 7 days of receipt of
application. H.T service within 15 days of receipt of application
(b)
Maximum time allowed to the applicant to deposit
charges.
LT service 7 days from the date of notice. HT
service 15 days from the date of notice.
(c)
Carrying out works, testing of installation and
effecting electricity supply.
LT without extension within 7 days of deposit
of charges. LT with extension within 15 days of deposit of
charges. HT without extension within 15 days of deposit of
charges HT with extension within 30 days of deposit of charges.