18. Completion of Construction.

18.2.1 Three copies of as built building plans.
18.2.2 A fee of Rs. 1000/-.
18.2.3 Copy of approved plan and approval letter as or case may be approval letter.
18.2.4 Certificate of installation of fire safety appliances by the nominated authority/agency wherever applicable.
18.2.5 Evidence to the effect of all public utility services, and in particular, sewerage, drainage, water supply, and electricity have been linked to the main public utility system.
18.2.6 A certificate obtained from concern structural Engineer certifying the structural safety and stability of the building.
18.2.7 A certificate from concern architect that the building has been constructed as per the provision of these bye-laws.
18.4.1 Number of floors
18.4.2 Building height
18.4.3 External Setbacks
18.4.4 Building Line, if any
18.4.5 Parking space provision
18.4.6 Abutting road width
18.4.7 FAR
18.4.8 Coverage percentage
18.4.9 Tree Cover
18.4.10 Water harvesting structures
18.4.11 Land if required to be surrendered.
18.4.12 Lifts, water pumps and storage tanks,
18.4.13 Internal roads/paving
18.4.14 Parking areas and external lighting
18.4.15 Lightening arrestors
18.4.16 Fire Fighting installations
18.4.17 Lifts
18.4.18 Water pump
18.4.19 Drainage and arrangement for waste water and sewerage disposal
18.4.20 Copy of agreement with the apartment Owner's Association/Society if any.
18.4.21 The team shall record and report to the Authority the deviations made from the approved plan.