It shall be the duty of a transmission licensee--
(a) to build, maintain and operate an efficient, co-ordinated and economical inter-State
transmission system or intra-State transmission system, as the case may be;
(b) to comply with the directions of the Regional Load Despatch Centre and the State Load
Despatch Centre, as the case may be;
(c) to provide non-discriminatory open access to its transmission system for use by--
(i) any licensee or generating company on payment of the transmission charges; or
(ii) any consumer as and when such open access is provided by the State Commission under
sub-section
(2)
of section 42, on payment of the transmission charges and a surcharge thereon, as
may be specified by the State Commission:
Provided that such surcharge shall be utilised for the purpose of meeting the requirement of current
level cross-subsidy:
Provided further that such surcharge and cross subsidies shall be progressively reduced
1
*** in the
manner as may be specified by the Appropriate Commission:
2
*
*
*
*
*
Provided also that the manner of payment and utilisation of the surcharge shall be specified by the
Appropriate Commission:
Provided also that such surcharge shall not be leviable in case open access is provided to a person
who has established a captive generating plant for carrying the electricity to the destination of his own
use.
Section 40 • The electricity act, 2003
Section 40. Duties of transmission licensees.
electricity-act-2003-chandigarh-sec-40.json
•
Section 40
{
"act_title": "The electricity act, 2003",
"act_slug": "electricity-act-2003-chandigarh",
"section_label": "Section",
"section": {
"number": "40",
"title": "Section 40. Duties of transmission licensees.",
"chapter": null,
"content": "It shall be the duty of a transmission licensee--\n(a) to build, maintain and operate an efficient, co-ordinated and economical inter-State\r\ntransmission system or intra-State transmission system, as the case may be;\n(b) to comply with the directions of the Regional Load Despatch Centre and the State Load\r\nDespatch Centre, as the case may be;\n(c) to provide non-discriminatory open access to its transmission system for use by--\n(i) any licensee or generating company on payment of the transmission charges; or\n(ii) any consumer as and when such open access is provided by the State Commission under\r\nsub-section\n(2)\nof section 42, on payment of the transmission charges and a surcharge thereon, as\r\nmay be specified by the State Commission:\nProvided that such surcharge shall be utilised for the purpose of meeting the requirement of current\r\nlevel cross-subsidy:\nProvided further that such surcharge and cross subsidies shall be progressively reduced\n1\n*** in the\r\nmanner as may be specified by the Appropriate Commission:\n2\n*\n*\n*\n*\n*\nProvided also that the manner of payment and utilisation of the surcharge shall be specified by the\r\nAppropriate Commission:\nProvided also that such surcharge shall not be leviable in case open access is provided to a person\r\nwho has established a captive generating plant for carrying the electricity to the destination of his own\r\nuse.",
"footnote": "1. The words and eliminated omitted by s. 6,\nibid\n. (w.e.f. 15-6-2007).\n2. The third proviso omitted by Act 26 of 2007, s. 6 (w.e.f. 15-6-2007)",
"is_definition": false,
"sort_order": 116
},
"prev_section": "39",
"next_section": "41"
}