    "act_title": "The electricity act, 2003",
    "act_slug": "electricity-act-2003-chandigarh",
    "section_label": "Section",
    "section": {
        "number": "40",
        "title": "Section 40.  Duties of transmission licensees.",
        "chapter": null,
        "content": "It shall be the duty of a transmission licensee--\n(a) to build, maintain and operate an efficient, co-ordinated and economical inter-State\r\ntransmission system or intra-State transmission system, as the case may be;\n(b) to comply with the directions of the Regional Load Despatch Centre and the State Load\r\nDespatch Centre, as the case may be;\n(c) to provide non-discriminatory open access to its transmission system for use by--\n(i) any licensee or generating company on payment of the transmission charges; or\n(ii) any consumer as and when such open access is provided by the State Commission under\r\nsub-section\n(2)\nof section 42, on payment of the transmission charges and a surcharge thereon, as\r\nmay be specified by the State Commission:\nProvided that such surcharge shall be utilised for the purpose of meeting the requirement of current\r\nlevel cross-subsidy:\nProvided further that such surcharge and cross subsidies shall be progressively reduced\n1\n*** in the\r\nmanner as may be specified by the Appropriate Commission:\n2\n*\n*\n*\n*\n*\nProvided also that the manner of payment and utilisation of the surcharge shall be specified by the\r\nAppropriate Commission:\nProvided also that such surcharge shall not be leviable in case open access is provided to a person\r\nwho has established a captive generating plant for carrying the electricity to the destination of his own\r\nuse.",
        "footnote": "1. The words and eliminated omitted by s. 6,\nibid\n. (w.e.f. 15-6-2007).\n2. The third proviso omitted by Act 26 of 2007, s. 6 (w.e.f. 15-6-2007)",
        "is_definition": false,
        "sort_order": 116
    },
    "prev_section": "39",
    "next_section": "41"
}