(a) approve the Metering Procedure, with such conditions or modifications as the Commission may deem appropriate; or
(b) reject the Metering Procedure for reasons to be recorded in writing if the Metering Procedure is not in accordance with the Act or these Regulations or with the Grid Code specified under clause (h) of sub-section (1) of Section 79 of the Act and direct the STU to submit a revised draft Metering Procedure.
(a) provisions related to location and installation of meters;
(b) specifications and accuracy limits for the meters;
(c) rights, responsibilities and procedures related to recording, collection, transfer, processing and storage of data collected from meters;
(d) provisions related to ownership of metering data;
(e) calibration procedures to be carried out by each concerned agency to ensure conformance to the above accuracy limits;
(vi) procedures associated with maintenance of the meters in proper functioning state, safety of meters, testing of the new or replacement meters, sealing of meters and inspection of meters;
(f) provisions related to right of access to the meters;
(g) procedures to address metering discrepancies, defective equipments and meter failures;
(h) procedures for resolution of disputes on matters related to metering; and
(i) any other aspect considered appropriate, for inclusion in the Metering Procedure, by the STU or the Commission.
Chapter VII
Miscellaneous
Section 33 • Delhi Electricity Regulatory Commission (State Grid Code) Regulations, 2008
33. Metering requirements.
delhi-electricity-regulatory-commission-state-grid-code-regulations-2008-sec-33.json
•
Section 33
{
"act_title": "Delhi Electricity Regulatory Commission (State Grid Code) Regulations, 2008",
"act_slug": "delhi-electricity-regulatory-commission-state-grid-code-regulations-2008",
"section_label": "Section",
"section": {
"number": "33",
"title": "33. Metering requirements.",
"chapter": null,
"content": "(a) approve the Metering Procedure, with such conditions or modifications as the Commission may deem appropriate; or\n(b) reject the Metering Procedure for reasons to be recorded in writing if the Metering Procedure is not in accordance with the Act or these Regulations or with the Grid Code specified under clause (h) of sub-section (1) of Section 79 of the Act and direct the STU to submit a revised draft Metering Procedure.\n(a) provisions related to location and installation of meters;\n(b) specifications and accuracy limits for the meters;\n(c) rights, responsibilities and procedures related to recording, collection, transfer, processing and storage of data collected from meters;\n(d) provisions related to ownership of metering data;\n(e) calibration procedures to be carried out by each concerned agency to ensure conformance to the above accuracy limits;\n(vi) procedures associated with maintenance of the meters in proper functioning state, safety of meters, testing of the new or replacement meters, sealing of meters and inspection of meters;\n(f) provisions related to right of access to the meters;\n(g) procedures to address metering discrepancies, defective equipments and meter failures;\n(h) procedures for resolution of disputes on matters related to metering; and\n(i) any other aspect considered appropriate, for inclusion in the Metering Procedure, by the STU or the Commission.\nChapter VII\nMiscellaneous",
"footnote": "",
"is_definition": false,
"sort_order": 32
},
"prev_section": "32",
"next_section": "34"
}