13. Application for Connection.

(a) such further information as shall be reasonably necessary to enable any person seeking Use of System to identify and evaluate the opportunities available when connecting to and making use of such system; and
(b) a commentary prepared by the STU indicating its views as to those parts of the STS most suited to new connections and transport of further quantities of electricity.
(a) Report stating the purpose of the proposed connection and/or modification, Transmission Licensee to whose system connection is proposed, description of apparatus to be connected or modification of the apparatus already connected and beneficiaries of the proposed connection;
(b) Construction schedule and target completion date; and
(c) Confirmation that the Transmission Licensee or the User shall abide by the provisions of DGC, Indian Electricity Rules, 1956 (until the Regulations under Section 53 of the Act are made and such Regulations specified by the Authority thereafter) and various standards including Grid Connectivity Standards made pursuant to the Act.
(a) accept the application with such modification or such conditions as may be laid down by the STU;
(b) reject the application for reasons to be recorded in writing if such application is not in accordance with the provisions of these Regulations.