Table 1
Table 1
( See Rule 3, 5 (4) (5) and Rule 6)
Sl. No.
Name of the Clearance/Activity
Time Limit Prescribed
1
2
3
1.
Preliminary meeting with the Convener after
expression of intent by investor
7 Days
2.
Arranging site visit for identification of land
for investor's project after preliminary meeting
21 Days
3.
Provisional registration of small scale industry
at district Trade & Industries Centre
3 Days
4.
Issuance of letter of Intent for allotment of
CSIDC industrial land
21 Days
5.
Forwarding of investor's proposal by
CSIDC/Directorate of Industries to District Collector for
transfer of government land
21 Days
6.
Forwarding of investor's proposal by
CSIDC/Directorate of Industries for acquisition of private land
to the Government
21 Days
7.
Approval by Government to land acquisition
proposal
30 Days
8.
Issuance of notification by the District
Collector under section 4 of the Land Acquisition Act, 1894 :
30 Days
(A) Intimation of anticipated compensation
amount to the investor
30 Days
(B) Publication of section 4 notification after
deposit of anticipated compensation amount
7 Days
9.
Issuance of Certificate for exemption from
payment of stamp duty by :
(A) District Trade & Industries Centre
7 Days
(B) Directorate of Industries
15 Days
10.
Issuance of No Objection Certificate from local
bodies for establishment of industry
30 Days
11.
Grant of permission for building construction
from Gram Panchayat
30 Days
12.
Grant of permission for development of land
under the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973
60 Days
13.
Grant of permission of Land Diversion
90 Days
14.
Grant of permission to develop, errect, re-erect
or to make alteration in any place in a Building under
Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973
30 Days
15.
Sanction of allotment of water from Water
Resource Department:
(A) At the applied site
60 Days
(B) At different site
90 Days
16.
Issuance of Power availability certificate by
CSEB
30 Days
17.
Sanction of power supply for L.T. connection by
CSEB
45 Days
18.
Sanction of power supply for H.T. connection by
CSFB
60 Days
19.
Approval of drawings by Electrical Inspector
15 Days
20.
Environment consent for Small Scale Industry
under simplified procedures by District Trade & Industries
Centre
10 Days
21.
Consent for Establishment of Industry under
Water (Prevention & Control of Pollution) Act, 1974
120 Days
22.
Consent for Establishment of Industry under The
Air (Prevention & Control of Pollution) Act, 1981
120 Days
23.
Registration &. grant of licence under The
Factories Act, 1948
90 Days
24.
Approval of plans & permission to
construct/extend/or take into use any building as a factory under
The Factories Act, 1948
90 Days
25.
Approval of site for hazardous process factory
under The Factories Act, 1948
90 Days
26.
Registration of establishment under the Central
Labour (Regulation & Abolition) Act, 1970
30 Days
27.
Registration of Boiler Under Indian Boiler Act,
1953
30 Days
28.
Registration under Chhattisgarh Vanijyik Kar
Adhiniyam, 1994
1 Day
29.
Registration under The Central Sales Tax Act,
1956
1 Day
30.
Permission for use of forest land for non-forest
purposes under Forest (Conservation) Act, 1980
(A) New application
90 Days
(B) Renewal of application
30 Days
31.
Permanent registration of Small Scale Industry
at District Trade & Industries Centre
21 Days
32.
Production Certificate for medium & large
scale industry from District Trade & Industries Centre
21 Days
Form I
Form I
( See Rule 4 (2))
Common Application Form
Part 1-A
Investor's Information
Investor's Information
1.
Investor's Details
1.1
Name of Investor/Company
..........................................................................................................
1.2
Address of Read.
Office....................................................................................................................................................................................................
Tel....................................................................Fax...................................
Email..........................................................................
Website........................................................................
1.3
Name of
Chairman/MD.....................................................................................
Address.....................................................................................................................................................................................................
Tel...................................................................Fax.........................................
Email.......................................................................................
1.4
Nature of Organization (Please lick)
Section 7 • Chhattisgarh Audyogik Nivesh Protsahan Niyam, 2004
7. Monitoring.
chhattisgarh-audyogik-nivesh-protsahan-niyam-2004-sec-7.json
•
Section 7
{
"act_title": "Chhattisgarh Audyogik Nivesh Protsahan Niyam, 2004",
"act_slug": "chhattisgarh-audyogik-nivesh-protsahan-niyam-2004",
"section_label": "Section",
"section": {
"number": "7",
"title": "7. Monitoring.",
"chapter": null,
"content": "Table 1\nTable 1\n( See Rule 3, 5 (4) (5) and Rule 6)\nSl. No.\nName of the Clearance/Activity\nTime Limit Prescribed\n1\n2\n3\n1.\nPreliminary meeting with the Convener after\n\t\t\t\texpression of intent by investor\n7 Days\n2.\nArranging site visit for identification of land\n\t\t\t\tfor investor's project after preliminary meeting\n21 Days\n3.\nProvisional registration of small scale industry\n\t\t\t\tat district Trade & Industries Centre\n3 Days\n4.\nIssuance of letter of Intent for allotment of\n\t\t\t\tCSIDC industrial land\n21 Days\n5.\nForwarding of investor's proposal by\n\t\t\t\tCSIDC/Directorate of Industries to District Collector for\n\t\t\t\ttransfer of government land\n21 Days\n6.\nForwarding of investor's proposal by\n\t\t\t\tCSIDC/Directorate of Industries for acquisition of private land\n\t\t\t\tto the Government\n21 Days\n7.\nApproval by Government to land acquisition\n\t\t\t\tproposal\n30 Days\n8.\nIssuance of notification by the District\n\t\t\t\tCollector under section 4 of the Land Acquisition Act, 1894 :\n30 Days\n(A) Intimation of anticipated compensation\n\t\t\t\tamount to the investor\n30 Days\n(B) Publication of section 4 notification after\n\t\t\t\tdeposit of anticipated compensation amount\n7 Days\n9.\nIssuance of Certificate for exemption from\n\t\t\t\tpayment of stamp duty by :\n(A) District Trade & Industries Centre\n7 Days\n(B) Directorate of Industries\n15 Days\n10.\nIssuance of No Objection Certificate from local\n\t\t\t\tbodies for establishment of industry\n30 Days\n11.\nGrant of permission for building construction\n\t\t\t\tfrom Gram Panchayat\n30 Days\n12.\nGrant of permission for development of land\n\t\t\t\tunder the Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973\n60 Days\n13.\nGrant of permission of Land Diversion\n90 Days\n14.\nGrant of permission to develop, errect, re-erect\n\t\t\t\tor to make alteration in any place in a Building under\n\t\t\t\tChhattisgarh Nagar Tatha Gram Nivesh Adhiniyam, 1973\n30 Days\n15.\nSanction of allotment of water from Water\n\t\t\t\tResource Department:\n(A) At the applied site\n60 Days\n(B) At different site\n90 Days\n16.\nIssuance of Power availability certificate by\n\t\t\t\tCSEB\n30 Days\n17.\nSanction of power supply for L.T. connection by\n\t\t\t\tCSEB\n45 Days\n18.\nSanction of power supply for H.T. connection by\n\t\t\t\tCSFB\n60 Days\n19.\nApproval of drawings by Electrical Inspector\n15 Days\n20.\nEnvironment consent for Small Scale Industry\n\t\t\t\tunder simplified procedures by District Trade & Industries\n\t\t\t\tCentre\n10 Days\n21.\nConsent for Establishment of Industry under\n\t\t\t\tWater (Prevention & Control of Pollution) Act, 1974\n120 Days\n22.\nConsent for Establishment of Industry under The\n\t\t\t\tAir (Prevention & Control of Pollution) Act, 1981\n120 Days\n23.\nRegistration &. grant of licence under The\n\t\t\t\tFactories Act, 1948\n90 Days\n24.\nApproval of plans & permission to\n\t\t\t\tconstruct/extend/or take into use any building as a factory under\n\t\t\t\tThe Factories Act, 1948\n90 Days\n25.\nApproval of site for hazardous process factory\n\t\t\t\tunder The Factories Act, 1948\n90 Days\n26.\nRegistration of establishment under the Central\n\t\t\t\tLabour (Regulation & Abolition) Act, 1970\n30 Days\n27.\nRegistration of Boiler Under Indian Boiler Act,\n\t\t\t\t1953\n30 Days\n28.\nRegistration under Chhattisgarh Vanijyik Kar\n\t\t\t\tAdhiniyam, 1994\n1 Day\n29.\nRegistration under The Central Sales Tax Act,\n\t\t\t\t1956\n1 Day\n30.\nPermission for use of forest land for non-forest\n\t\t\t\tpurposes under Forest (Conservation) Act, 1980\n(A) New application\n90 Days\n(B) Renewal of application\n30 Days\n31.\nPermanent registration of Small Scale Industry\n\t\t\t\tat District Trade & Industries Centre\n21 Days\n32.\nProduction Certificate for medium & large\n\t\t\t\tscale industry from District Trade & Industries Centre\n21 Days\nForm I\nForm I\n( See Rule 4 (2))\nCommon Application Form\nPart 1-A\nInvestor's Information\nInvestor's Information\n1.\nInvestor's Details\n1.1\nName of Investor/Company\n\t\t\t\t..........................................................................................................\n1.2\nAddress of Read.\n\t\t\t\tOffice....................................................................................................................................................................................................\nTel....................................................................Fax...................................\nEmail..........................................................................\nWebsite........................................................................\n1.3\nName of\n\t\t\t\tChairman/MD.....................................................................................\nAddress.....................................................................................................................................................................................................\nTel...................................................................Fax.........................................\nEmail.......................................................................................\n1.4\nNature of Organization (Please lick)",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
"prev_section": "6",
"next_section": "1"
}