4. Utilization of the PSDF.

(a) Creating necessary transmission systems of strategic importance based on operational feedback by Load Despatch Centers for relieving congestion in inter-State transmission system and intra-State Systems which are incidental to the ISTS;
(b) Installation of shunt capacitors, series compensators and other reactive energy generators for improvement of voltage profile in the Grid;
(c) Installation of standard and special protection schemes, pilot and demonstrative projects and for setting right the discrepancies identified in the protection audits on regional basis;
(d) Renovation and Modernization of transmission and distribution systems for relieving congestion; and
(e) Any other project in furtherance of the above objectives such as conducting technical studies and capacity building.