Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019
Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019
Sections
central-electricity-regulatory-commission-power-system-development-fund-regulations-2019.json
•
8 Sections
•
India (Central)
{
"id": 10073,
"slug": "central-electricity-regulatory-commission-power-system-development-fund-regulations-2019",
"title": "Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019",
"short_title": "Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019",
"act_number": "Published vide Notification No. L-1/247/2019/CERC,",
"act_year": 2019,
"act_type": "CENTRAL",
"location": "India (Central)",
"law_status": "unknown",
"enactment_date": null,
"description": "Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. Short title and commencement.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 0
},
{
"number": "2",
"title": "2. Definitions.",
"chapter": null,
"content": "(a) \"Act\" means the Electricity Act, 2003 (36 of 2003);\n(b) \"Appraisal Committee\" means the Committee constituted by the Central Government as per the Guidelines for the purpose of scrutiny (techno-economic appraisal) and prioritization of project proposals for funding from PSDF;\n(c) \"Congestion Amount\" has the same meaning as assigned to it in Regulation 33 of the Power Market Regulations;\n(d) \"Congestion Charge\" has the same meaning as assigned to it under Congestion Relief Regulations;\n(e) \"Congestion Relief Regulations\" means Central Electricity Regulatory Commission (Measures to relieve congestion in real time operation) Regulations, 2009;\n(f) \"Deviation Settlement Charges\" has the same meaning as assigned to it in the Deviation Settlement Mechanism Regulations;\n(g) \"Deviation Settlement Mechanism Regulations\" means the Central Electricity Regulatory Commission (Deviation Settlement and related matters) Regulations, 2014;\n(h) \"Grid Code\" means the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010;\n(i) \"Guidelines\" means the procedures approved by the Central Government for disbursement of funds from PSDF issued vide Office Memorandum dated 18th September, 2014;\n(j) \"Monitoring Committee\" means the Committee constituted by the Central Government as per the Guidelines for the purpose of sanctioning of projects or schemes, release of funds from PSDF and overall supervision and monitoring of the implementation of projects or schemes, as the case may be;\n(k) \"Nodal Agency\" means the agency as designated under clause (1) of Regulation 5 of these regulations;\n(l) \"Power Market Regulations\" means Central Electricity Regulatory Commission (Power Market) Regulations, 2010;\n(m) \"Project Entity\" means the agency that submits proposals for funding of projects from PSDF and shall include Regional Power Committees, Generating Companies, Transmission Licensees, Distribution Licensees, Load Despatch Centers;\n(n) \"PSDF\" or \"Power System Development Fund\" means the funds constituted under Regulation 3 of these regulations;\n(o) \"Reactive Energy Charges\" has the same meaning as assigned to it in the Grid Code;",
"footnote": "",
"is_definition": true,
"sort_order": 1
},
{
"number": "3",
"title": "3. Constitution of the Fund.",
"chapter": null,
"content": "(a) Congestion charges standing to the credit of the \"Congestion Charge Account\" after release of amounts payable to Regional Entities entitled to receive congestion charges along with interest, if any, in accordance with the Congestion Relief Regulations;\n(b) Congestion amount arising from the difference in the market prices of different regions as a consequence of market splitting in power exchanges in accordance with Power Market Regulations;\n(c) Deviation Settlement Charges standing to the credit of the \"Regional Deviation Pool Account Fund\" after final settlement of claims in accordance with Deviation Settlement Mechanism Regulations;\n(d) Reactive Energy Charges standing to the credit of \"Reactive Energy Charges Account\" in accordance with the Grid Code;\n(e) Additional Transmission Charges arising out of the explicit auction process in Short-Term Open Access Advance Bilateral transactions in accordance with the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008; and\n(f) Such other charges as may be notified by the Commission from time to time.",
"footnote": "",
"is_definition": false,
"sort_order": 2
},
{
"number": "4",
"title": "4. Utilization of the PSDF.",
"chapter": null,
"content": "(a) Creating necessary transmission systems of strategic importance based on operational feedback by Load Despatch Centers for relieving congestion in inter-State transmission system and intra-State Systems which are incidental to the ISTS;\n(b) Installation of shunt capacitors, series compensators and other reactive energy generators for improvement of voltage profile in the Grid;\n(c) Installation of standard and special protection schemes, pilot and demonstrative projects and for setting right the discrepancies identified in the protection audits on regional basis;\n(d) Renovation and Modernization of transmission and distribution systems for relieving congestion; and\n(e) Any other project in furtherance of the above objectives such as conducting technical studies and capacity building.",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "5",
"title": "5. Nodal Agency and its functions.",
"chapter": null,
"content": "(a) Keep a record of business transacted out of PSDF;\n(b) Prepare procedure for preparation of Budget, Accounting and Audit:\n(c) Prepare Annual Report of PSDF; and\n(d) Perform such other functions as may be assigned to it by the Central Government.",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "6",
"title": "6. Sanction of funds from PSDF.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "7",
"title": "7. Annual Report.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "8",
"title": "8. Repeal and Savings.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 7
}
],
"metadata": {
"Act ID": "Last Updated 29th November, 2019 [act3545]",
"Act Number": "Published vide Notification No. L-1/247/2019/CERC, dated 28.8.2019",
"Enactment Date": "",
"Act Year": "2019",
"Short Title": "Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019",
"Type": "CENTRAL",
"Location": "India (Central)"
},
"updated_at": "2026-09-29 21:55:17"
}