1. Short title.

Section 1

3. Definition.

Section 3

4. Forest contractor entitled only to the forest produce so purchased.

Section 4

5. Forest contractor to respect private rights.

Section 5

6. Accessory licence to forest contracts.

Section 6

7. Time to be the essence of forest contract.

Section 7

8. Security deposit.

Section 8

9. Power of Forest Officer to stop extraction of forest's produce.

Section 9

10. Local agent.

Section 10

11. Unsuitable persons not to be employed.

Section 11

12. Inspection of boundaries.

Section 12

13. Permit for removal of forest produce.

Section 13

14. Extraction along forest roads.

Section 14

15. Forest produce to be removed by day light.

Section 15

16. Forest produce to be removed by prescribed route and to be checked at depots.

Section 16

17. Liability of forest contractors for damage.

Section 17

19. Liability of forest contractors in respect of forest offences.

Section 19

20. Forest contractor's accounts.

Section 20

23. Progressive work by Sections.

Section 23

24. Property marks.

Section 24

25. Verification of standard.

Section 25

26. Manufacture of charcoal.

Section 26

27. Liability of Illicit fellings.

Section 27

28. Completion report.

Section 28

35. Execution of contracts.

Section 35

36. Suspension of work or determination of contracts.

Section 36

37. Appeal against suspension of work or determination of contract.

Section 37

38. Penalty for breach of conditions.

Section 38

39. Rules regarding release of security deposits.

Section 39

40. Government not responsible for losses in certain circumstances.

Section 40

42. Payment of Depot Rent.

Section 42

44. Assignments of forest contract.

Section 44

45. Arbitration.

Section 45

46. Power to black-list contractor.

Section 46

3. Other faults in felling and cleaning, e.g. conditions of standards or other felling of which is prohibited, leaving of high stumps in timber and bamboo coupes, overfelling of bamboo clumps, etc.

Section 3

4. I have further to report the following breaches of the conditions of the agreement.

Section 4

5. The cost of rectifying the faults found above will be roughly:

Section 5