1. Short Title and Commencement.

Section 1

2. Scope and Extent of Application.

Section 2

3. Definitions.

Section 3

4. Multi-Year Tariff Framework.

Section 4

5. Business Plan.

Section 5

6. Forecast.

Section 6

7. Specific trajectory for certain variables.

Section 7

8. Annual Review of Performance and True-up.

Section 8

9. Controllable and uncontrollable factors.

Section 9

10. Mechanism for pass-through of gains or losses on account of uncontrollable factors.

Section 10

11. Mechanism for sharing of gains or losses on account of controllable factors.

Section 11

12. Procedures relating to making of an application for determination of Tariff.

Section 12

13. Order approving the Business Plan and Tariff Order.

Section 13

14. True-Up Order.

Section 14

15. Adherence to Tariff Order.

Section 15

16. Metered Sales forecast.

Section 16

17. Un-metered Sales Forecast.

Section 17

18. Treatment of Distribution Loss.

Section 18

19. Power Purchase Quantum and Cost.

Section 19

20. Treatment of Incremental Power procurement cost.

Section 20

1. Own generation if the Distribution Licensee has its own generation.

Section 1

2. Cost due to variation in cost of power purchase on account of increase in fuel cost.

Section 2

21. Components of ARR.

Section 21

22. Operation & Maintenance Expenses.

Section 22

23. Treatment of Depreciation.

Section 23

24. Contribution to Contingency Reserve.

Section 24

25. Treatment of Interest on loan.

Section 25

26. Interest on Working Capital.

Section 26

27. Treatment of Return on equity.

Section 27

28. Bad and Doubtful Debts.

Section 28

29. Income Tax.

Section 29

30. Non-Tariff Income.

Section 30

31. Income from Other Business.

Section 31

32. Treatment of Regulatory Assets.

Section 32

33. Segregation of Wheeling Business and Retail Supply Business.

Section 33

34. Target Availability and Recovery of ARR.

Section 34

35. Subsidy.

Section 35

36. Cross Subsidy, Allocation of Cost to Serve and Tariff Design.

Section 36

37. Power to amend.

Section 37

38. Power to remove difficulties.

Section 38

39. Right to vary terms and conditions.

Section 39

40. Limitation of Power of Commission.

Section 40

41. Repeal and savings.

Section 41