(a) in the case of Preliminary Scheme, within a period of thirty days from the date of its receipt, and
(b) in the case of final scheme, within a period of sixty days from the date of its receipt, by notification, sanction the preliminary scheme or the final scheme or refuse to give sanction, provided that in sanctioning any such scheme, the Government may make such modifications as may, in its opinion, be necessary for the purpose of correcting an error, irregularity or informality.
(a) the place at which the scheme shall be kept open for inspection by the public, and
(b) a date on which all the liabilities created by the scheme shall come into force:
Section 82 • Andhra Pradesh Capital Region Development Authority Act, 2014
82. Power of the Government to sanction or refuse to sanction the scheme and effect of sanction.
andhra-pradesh-capital-region-development-authority-act-2014-sec-82.json
•
Section 82
{
"act_title": "Andhra Pradesh Capital Region Development Authority Act, 2014",
"act_slug": "andhra-pradesh-capital-region-development-authority-act-2014",
"section_label": "Section",
"section": {
"number": "82",
"title": "82. Power of the Government to sanction or refuse to sanction the scheme and effect of sanction.",
"chapter": null,
"content": "(a) in the case of Preliminary Scheme, within a period of thirty days from the date of its receipt, and\n(b) in the case of final scheme, within a period of sixty days from the date of its receipt, by notification, sanction the preliminary scheme or the final scheme or refuse to give sanction, provided that in sanctioning any such scheme, the Government may make such modifications as may, in its opinion, be necessary for the purpose of correcting an error, irregularity or informality.\n(a) the place at which the scheme shall be kept open for inspection by the public, and\n(b) a date on which all the liabilities created by the scheme shall come into force:",
"footnote": "",
"is_definition": false,
"sort_order": 78
},
"prev_section": "81",
"next_section": "83"
}