(a) land record is in conformity with the proposed construction;
(b) the level of the land is not lower than the level of the crown of the nearest public street;
(c) the land is capable of being well-drained by means of drainage facilities leading to existing public drains or drainage channels;
(d) the soil of the building site is likely to sustain the construction of a building thereon;
(e) where the site is within 5.00 metres of any side of a tank, the owner will take such measures as shall prevent any risk of drainage from such building passing into the tank;
Section 3 • West Bengal Municipal (Building) Rules, 2007
3. Criteria of using a piece of land as a building site
west-bengal-municipal-building-rules-2007-sec-3.json
•
Section 3
{
"act_title": "West Bengal Municipal (Building) Rules, 2007",
"act_slug": "west-bengal-municipal-building-rules-2007",
"section_label": "Section",
"section": {
"number": "3",
"title": "3. Criteria of using a piece of land as a building site",
"chapter": null,
"content": "(a) land record is in conformity with the proposed construction;\n(b) the level of the land is not lower than the level of the crown of the nearest public street;\n(c) the land is capable of being well-drained by means of drainage facilities leading to existing public drains or drainage channels;\n(d) the soil of the building site is likely to sustain the construction of a building thereon;\n(e) where the site is within 5.00 metres of any side of a tank, the owner will take such measures as shall prevent any risk of drainage from such building passing into the tank;",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
"prev_section": "2A",
"next_section": "4"
}