9. Duration of sanction of Building permit

9.1. An application for revalidation of sanction shall be made at least 60 days before the expiry of the period of such sanction.
9.2. However, nothing in Regulation no. 9.1 shall be deemed to affect the power of the Authority to revalidate the sanction on application given after the period thereof;
9.3. Revalidation of sanction before expiry of the sanction can be done for a period of one year at a time and such revalidations can be done only twice.
9.4. Revalidation shall be subject to the rules then in force.
9.5. Fees equal to 50 per cent of the original building permit fee shall be payable to the Authority with a minimum fee of Rs. 21.00.
9.6. The applicant shall have to send an application alongwith the original plan already sanctioned.