← Back to The U.P. Factories Rules, 1950

74. Weekly holidays and attendance register.

Overlapping shifts
[Sections 58(2) and 112]
75.
Overtime
[Section 59(5)]
[76.
(a) the total amount of the price payable at the concessional rates for the maximum quantity of food grains admissible to a standard family, as defined in Explanation 1 to sub-section (4) of the said section,
(b) from the total amount of the price payable for the same quantity of food grains and other articles at the average market rates which shall be determined either on the basis of the retail prices for such food grains and other articles prevailing in the nearest market or according to the rates published by the Labour Commissioner, for the different weeks of the wage period, in the table relating to the Consumers Price Index Number for working classes at Kanpur.
(b) The register prescribed under sub-rule (1) shall be produced on demand by an Inspector irrespective of the fact whether the Manager was present in the factory or not during inspection.]
Notice of period for work for adults
[Section 61(8)]
77.
Register of adult workers
[Section 62]
78.
Persons Holding Positions of Supervision or Management
[Section 64(1)]
[79.
(i) The Manager;
(ii) The Assistant Manager;
(iii) Mill Secretary;
(iv) Deputy Mill Secretary;
(v) Labour Officer;
(vi) Security Officer;
(vii) Heads of Technical Department;
(viii) Engineers;
(ix) Assistant Engineers;
(x) Foreman;
(xi) Assistant Foreman;
(xii) Chargeman;
(xiii) Overseers;
(xiv) Jobbers in Textile Factories;
(xv) Supervisors;
(xvi) Shift Officer;
(xvii) Shift Incharge;
(xviii) Paper makers;
(xix) Head Storekeepers provided they are employed solely in a supervisory capacity;
(xx) Any other person, who in the opinion of the State Government holds a position of supervision or management and is so declared by it in writing.
(i) The General Manager;
(ii) The Manager;
(iii) The Mill Secretary;
(iv) The Deputy Mill Secretary;
(v) The Cane Manager;
(vi) The Cane Superintendent, where there is no Cane Manager;
(vii) The Chief Chemist;
(viii) The Labour Welfare Officer;
(ix) The Chief Engineer;
(x) The Secretary to the Managing Agent or the Personal Assistant to the General Manager;
(xi) The Cane Development Officer;
(xii) Heads of Commercial Department, like accounts, purchase, store, legal catering, etc.;
(xiii) Any person who, in the opinion of the State Government, holds a position of supervision or management and is so declared by it in writing.
80.
(i) Stenographers;
(ii) Personal Assistants;
(iii) Personal Secretaries;
(iv) Office Superintendent;
(v) Head Clerk, where there is no Office Superintendent;
(vi) Head Munim where there is no Office Superintendent or Head Clerk;
(vii) Head Accountant;
(viii) Head Cashier;
(ix) Cashier;
(x) Head Time-keeper;
(xi) Telephone Operator;
(xii) Receptionist;
(xiii) Any other person, who in the opinion of the State Government, holds a confidential position and is so declared in writing by it.
81.
Urgent Repairs
[Section 64(2) (a)]
82.
Conditions
Conditions
(i) When the cast of urgent repairs has arisen, a notice shall be sent within 24 hours of the commencement of the employment of persons employed to carry out the said repairs to the inspector of factories of the region concerned in writing stating the names of persons employed, the precise nature of work and the exact time of commencement of such works. A copy of the said notice shall be affixed at the place mentioned in Section 108(2) before the workers are put on urgent repairs.
(ii) A rest period of one hour shall be given as work permits during the working hours.
(ii) No workers shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(iv) All the workers working in excess of nine hours a day or 48 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provision of sub-section (1) of Section 59 of the Act.
(v) Every worker shall be given compensatory holiday in accordance with Section 53 of the Act.
Note. - For the purpose of this rule expression "urgent repairs" means (a) any repair to the main driving machinery, and plant necessary to prevent or remedy a breakdown that may cause or has caused, a stoppage of the whole or part of manufacturing process or (b) repairs that are of such nature that failure to execute them would cause a stoppage or serious interruption of a public service :
Provided that periodical overhaul or repairs to any machinery in a factory shall not be deemed to be "Urgent Repairs".
Loading and Unloading of Railway Wages and Certain Categories of Clerical Staff
[Sections 64 (2) (1) and 112]
[83.
(i) Where possible a message by telegram or telephone shall be sent immediately after such work has arisen, followed by a notice which shall be sent, within 24 hours of the commencement of the employment of the workers employed to carry out such work, to the Inspector of Factories of the region concerned in writing stating the names of the workers employed, the precise nature of work and the exact time of commencement of such work. A copy of the said notice shall be affixed at the place mentioned in sub-section (2) of Section 108 of the Act before the workers are put on any such work.
(ii) Total daily hours of work shall not exceed 10 the total spread over being limited to 12 hours in any one day and total hours of overtime work shall not exceed 50 in any quarter.
(iii) The weekly hours of work shall not exceed 60.
(iv) A rest period of one hour shall be given as work permits during the working hours.
(v) No worker shall be employed for such work for more than 14 consecutive days without a holiday of 24 consecutive hours.
(vi) All the workers working in excess of 9 hours per day or 48 hours per week shall be paid in respect of such additional hours at the rate of twice the ordinary rate of wages in accordance with the provisions of sub-section (1) of Section 59 of the Act.
(vii) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.]
Maintenance Staff
[Section 64(2) (6)]
84.
(i) Engine drivers, firemen, coal men, oilmen, rope and belt men, fitters, welders, electricians, machine men, blacksmith, carpenters, masons and their assistants when employed solely for the purpose of maintenance of a power plant and transmission machinery of a factory, from the provisions of Sections 51, 55 and 56.
(ii) Workers employed solely in water supply lighting, ventilating, air conditioning, humidifying, fire extinguishing and the cleaning of blow room flues, from the provisions of Section 56.
(b) An exemption under this Rule shall be subject to the following conditions:
(i) A period of rest of one hour shall be given during each shift.
(ii) The total hours of overtime work shall not exceed 50 in any one quarter, the total spread over being limited to 12 hours in any one day.
(iii) All workers working in excess of 48 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of wages in accordance with the provisions of sub-section (1) of Section 59 of the Act.
(iv) The periods of work of maintenance staff shall be indicated before hand in Form No. 11.
Foundries
[Section 64(2)(b)]
85.
Conditions
Conditions
(i) A notice giving the names of such workers as are employed, showing their working hours on the day on which the exemption is availed of, should be displayed before the work beyond the hours fixed in Form No. 11 is commenced and a copy of the same should be sent to the Chief Inspector and the Inspector concerned.
(ii) Total daily hours of work shall not exceed 10 and the total hours of overtime work shall not exceed 50 in any one quarter, the total, spread over being limited to twelve hours in any one day.
(iii) A minimum interval of rest of half an hour shall be given at any time during the working hours.
(iv) The weekly hours shall not exceed 52.
(v) All workers working excess of 9 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provisions of sub-section (1) of Section 59 of the Act.
Brassware Factories
[Section 64(2) (b)]
85A.
Conditions
Conditions
(i) The notice giving the names of such workers as are employed and showing their working hours on the day on which the exemption is availed on by the occupier of the factory should be displayed before the work beyond the hours fixed in Form No. 11 is commenced and a copy of the same should be sent to the Chief Inspector and the Inspector concerned.
(ii) Total daily hours of work shall not exceed 10 and the total hours of overtime work shall not exceed 50 in any one quarter, the total spread over being limited to 12 hours on any one day.
(iii) An interval of rest of at least half an hour shall be given at any time during the working hours.
(iv) The weekly hours of work shall not exceed 52.
(v) All workers working in excess of 9 hours a day and 48 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provisions of subsection (1) of Section 59.
Shellac Factories
[Section 64(2) (c)]
85B.
Continuous Process Factories
[Section 64(2) (d)]
[86.
Classes of Factories
Class of work
(i) Electrical Generating stations and Distributing
substations.
Work of male adult workers attending to boilers
turbines, engines, generators, motors, boosters, switchboards,
transmission machinery, cables, batteries and auxiliaries.
(ii) Waterworks and water pumping stations.
Work of male adult workers attending to boilers,
engines, motors, switchboards, pumps and auxiliaries.
(iii) Sugar Factories and refineries working on the vacuum pan
system.
Work of male adult workers attending to-
(a)
boilers, engines, motors, switchboards and
pumps;
(b)
handling and crushing cane and handling gur to
melting blow-ups;
(c)
engaged in filtration, clarification and
crystallization and cane juice and gur liquor;
(d)
engaged in evaporation and concentration of cane
juice and gur liquor;
(e)
engaged in curing the massacuite;
(f)
engaged in drying, crushing and bagging of
sugar;
(g)
engaged in the burning of lime stone and
sulphur, for production of carbon dioxide and sulphur dioxide
gases, for the clarification of cane juice.
(iv) Distilleries
The work of male adult workers attending to-
(a)
boilers, engines, motors, switchboards and
pumps;
(b)
diffusion of mahua;
(c)
working of molasses;
(d)
fermentation of wash;
(e)
yeast propagation;
(f)
distillation process.
(v) Breweries
The work of male adult workers attending to-
(a)
boilers, engines and pumps;
(b)
melting, coppers, hopback, coolers and
refrigerators.
(vi) Rosin and Turpentine.
The work of male adult workers attending to-
(a)
boilers, engines, pumps, motors and
switch-board;
(b)
distillation of rosin;
(c)
refining of turpentine;
(d)
filtration and casting of rosin.
(vii) Ice factories
The work of male adult workers attending to-
(a)
boilers and ice-making machinery;
(b)
receptacles for the production of ice.
(viii) Chemical works
The work of male adult workers attending to-
(a)
boilers, pumps and compressors;
(b)
the manufacture of sulphuric, nitric and
hydrochloric acids, ammonia, magnesium sulphate, alum,
hyposulphite and sulphite of soda, sodium sulphate, sodium
sulphide, nitrate of potash, alumina and bichromate of potash.
(ix) Distillation of sandal wood and essential oils.
The work of male adult workers attending to
boilers and distillation processes.
(x) Plate and sheet glass factories and glass bangles
factories.
The work of the following classes of male adult
workers-
(a)
gas producers, window and plate glass
machinemen, tankmen, sheet-glass carriers and lift attendants and
workers employed on glass blowing machines in tank and pot
furnaces when run in conjunction with the glass furnace;
(b)
firemen, engine and boiler attendants.
(xi) Straw-boards factories.
The work of male adult workers attending to-
(a)
boilers, engines, turbines, generators, motors,
switch-boards and pumps;
(b)
cooking, milling, beating and straw-board
machines.
(xii) Kiln, seasoning of timber and bobbin stone enamelling.
The work of male adult workers attending to-
(a)
boilers, engines, pumps, motors, dynamos and
switch-boards;
(b)
Timber, seasoning Kiln.
(c)
stone-enamelling chamber.
(xiii) Vegetable oil Hydrogenation factories.
The work of male adult workers attending to-
(a)
boilers, generators, motors, transformers,
switch-boards and water softening plants;
(b)
refining, bleaching, distillation
(deodorization) and hardening plants, soldering, labelling,
packing and storing of containers;
(c)
the production and compression of hydrogen and
oxygen gases;
(xiv) Production and or compression of oxygen and acetylene
gases.
The work of male adult workers attending to
generator and compressors.
(xv) Soap factories
The work of male adult workers attending to-
(a)
boilers, generators, motors, switch-boards; and
(b)
boiling, scrutching and framing.
(xvi) Paper mills
The work of male adult workers attending to-
(a)
boilers, engines, turbines, generators, motors,
switch-boards and pumps;
(b)
cooking, milling, beating, straw-board and paper
manufacturing machines.
(xvii) Electrical steel smelting furnaces.
Work of male adult workers attending to
transformers, electrode controls, hydraulic pumps, scrap cutting
and transporting, furnacemen, ladenmen, pitside workers and
workers attending to moulds for ingot.
(xviii) Rolling mills
Ingot transporters, furnacemen, furnace coolies,
tongsmen working at various rolling mills (such as roughers and
loopers) workers on the cooling bed, motormen, straighteners,
workers engaged in stacking of finished material and attendants
of shares and other auxiliary machinery.
(xix) Starch factories
Work of male adult workers engaged in the
manufacture of starch and its by-products, except those employed
in the engineering departments and workshops.
(xx) Glue and Gelatine mills.
Work of male adult workers engaged in the
manufacture of glue and gelatine, including soaking, boiling,
spreading, chopping and drying.
(xxi) Biscuit factories
Work of male adult workers engaged in the mixing
of the dough, baking, drying, and packing biscuits.
(xxii) Cement factories
The work of male adult workers-
(a)
attending to boilers, engines, motors,
switch-boards and pumps;
(b)
engaged in preparation of raw materials, cement
mills, working in conjunction with the continuous kilns, cement
grinding, packing and storing.
(xxiii) Cold storage factories.
Work of male adult workers attending to motors
and compressors.
(xxiii-A) Capacitors making factories.
Work of male adult workers engaged in Anodic,
forming of Aluminium foils and other connected processes.
(xxiv) All factories
Work of male adult workers attending boilers.
(xxv) Manufacture of Audi-Video, magnetic tape
Work of male adult workers-
(a)
engaged in operations and process of mixing
coating, calendering, and utility services, and
(b)
attending to plane, tery mixing machine, high
speed dissolver, puddle mixer, media mill, tank mixer, sand mill
filter unit; coating machine, calendering machine; air
compressors, air handling unit, chilling plant and cooling
towers.
Conditions
Conditions
(i) Such workers shall be employed on three eight-hour shifts system. An interval for rest of half an hour shall be allowed to every such worker some time during each shift he is required to work.
(ii) No such workers shall be employed for more than fourteen consecutive days without a holiday of twenty-four consecutive hours.
(iii) The total daily hours of work shall not exceed 10 with a spread over of 12 hours except in an emergency when it is necessary to employ a shift worker for more than 8 hours in any day to enable him to work whole or part of the subsequent shift. In no case shall the worker be employed for more than 16 hours in a period of 24 hours from the commencement of work, and the total number of hours of overtime shall also not exceed 50 in any quarter:
(iv) The system of shifts shall be approved by an Inspector before enforcement.
(v) All workers working in excess of 9 hours a day or 48 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of any in -accordance with the provisions of sub-section (1) of Section 59 of the Act.
(vi) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.]
Wood Products (Cutch and Katha) Factories
[Section 64(2) (d)]
87.
[(i) The total daily hours of work shall not exceed 10 with a spreadover of 12 hours except in an emergency when it is necessary to employ a shift worker for more than 8 hours in any day to enable him to work the whole or part of the subsequent shift. In no case shall the worker be employed for more than 16 hours in a period of 24 hours from the commencement of work and the total number of hours of overtime shall also not exceed 50 in any quarter:
(ii) All the workers working in excess of 9 hours a day or 48 hours a week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provisions of sub-section (1) of Section 59 of the Act.
Glass Works
[Section 64(2) (d)]
88.
Conditions
Conditions
(i) The daily hours of work shall not exceed 8 and the weekly hours of work 56. The total hours of overtime shall not exceed 50 in any one quarter.
(ii) No persons shall be employed for more than 14 consecutive days4 without a holiday of 24 consecutive hours.
(iii) All workers working in excess of 18 hours per week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provisions of sub-section (?) of Section 59 of the Act.
(iv) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Vegetable Oil Mills
[Section 64(2) (d)]
89.
Conditions
Conditions
(i) The shift system shall be approved by an Inspector of Factories.
(ii) A rest period of half-an-hour shall be given to each worker during each shift.
[Rigid Polyvinyl Chloride Pipe Manufacturing Factories
[Section 64(2) (d)]
89A.
Conditions
Conditions
Sizing, Dyeing, Bleaching and Cloth Printing
[Section 64(2) (d)]
90.
Conditions
Conditions
(i) The daily hours of work shall not exceed 9 and the weekly hours of work 54. A rest interval of half an hour shall be given during each shift. The total hours of overtime shall not exceed 50 in any quarter.
(ii) All workers working in excess of 48 hours per week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of pay in accordance with the provisions of sub-section (1) of Section 59 of the Act.
Tanneries
[Section 64(2)(d)]
91.
Conditions
Conditions
(i) No worker shall be employed for more than 4 hours on any Sunday.
(ii) No worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(iii) The total hours of overtime work shall not exceed 50 in any one quarter.
(iv) All workers working in excess of 48 hours per week in a factory shall be paid in respect of such additional hours at the rate of twice the ordinary rate of the pay in accordance with the provisions of sub-section (1) of Section 59 of the Act.
(v) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Preparation, Packing and Despatch of Serum and Vaccine
[Section 64 (2) (e)]
92.
Conditions
Conditions
(i) No such worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(ii) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Dairies
[Section 64(2) (e)]
93.
Conditions
Conditions
(i) No such worker shall be employed for more than 8 hours on Sunday.
(ii) No such worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(iii) Every such worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Rice Mills
[Section 64 (2) (f)]
94.
Conditions
Conditions
(i) No such worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(ii) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Opium Factories
[Section 64(2) (g)]
95.
Conditions
Conditions
(i) No worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(ii) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Tea Factories
[Section 64(2) (g)]
96.
Conditions
Conditions
(i) The number of workers employed on a particular piece of work shall always be at least 25 per cent greater than the number actually required to do the work at any given time.
(ii) No worker shall be employed for more than 14 consecutive days without a holiday of 24 consecutive hours.
(iii) A rest interval of half-an-hour shall be given during the working hours.
(iv) Every worker shall be given a compensatory holiday in accordance with Section 53 of the Act.
Khandsari Factories
[Section 64(2) (g)]