3. Reporting requirement

(ii) Where a Port charge below the ceiling notified herein is to be implemented, the Service Provider may implement the proposed Port charges after the mandatory notice period of 45 working days, unless the Authority within such period directs otherwise.
(iii) Port charges whenever implemented as per Schedule I herein, shall be reported to the Authority within 45 days of their implementation.
(iv) When an Interconnection Provider informs the Interconnection Seeker that it cannot provide the Ports as sought for by the latter, the Interconnection Seeker within 45 days of being so informed, may approach the Authority for seeking its intervention.
(v) No Service Provider shall alter any Port charge, or any part thereof, without complying with the reporting requirement.
Section IV