3. Form and manner of preparing budget estimates.

(b) The estimate of total expenditure shall not exceed the average of actual receipts of the previous three years or the estimated receipts of the budget year, whichever is less. The total provision of expenditure for recurring items shall not exceed the average of past three years' receipts on account of fixed demand or the estimated receipt for fixed demand of the budget year, if the fixed demand has been increased for that year:
(b) The Municipal Engineer or the Chief Municipal Officer in a Municipality where there is no Municipality Engineer, shall proceed to prepare detailed plans and estimates of all works consolidated by the Council and submit them for its final sanction. The Council shall then determine the works to be included in the budget and communicate the same to the Chief Municipal Officer.
(c) No work for which plans and estimates have not been prepared and sanctioned may, unless in exceptional circumstances, be included in the budget.
(d) Full particulars regarding all works costing over Rs. 500 shall be given in the annexures to the budget estimates.