← Back to Directory

The M.P. Irrigation Rules, 1974

The M.P. Irrigation Rules, 1974

Raw JSON API

Sections

1. Short title.

Section 1

2. Definitions.

Section 2

1. To pay Abi Rates and canal water crop rates in addition to Abi rates as specified by Government from time to time, on all our lands under Rules 62 and 63 of the Madhya Pradesh Irrigation Rules, 1974.

Section 1

2. We agree that we will not claim any compensation for the period of submergence of our lands and will not interfere in any way for opening of the gates etc. before specified time.

Section 2

3. In year of scarcity if it is considered that the tank should not be emptied for the welfare of the general public, we shall have no objection for such submergence except demanding the privileges whatsoever admissible under the rules in force.

Section 3

4. Should any dispute arise, as regards terms and conditions or anything to be done thereunder, the dispute shall unless it is otherwise provided for, be referred for the decision of the Superintending Engineer and his decision shall be final.

Section 4

1. Name of Village:.......................................................

Section 1

2. Work under which situated ............................................

Section 2

3. Name of distributary of minor from which water is required :

Section 3

4. Change of outlet from which water is required :........................

Section 4

5. Name of crop to be irrigated .........................................

Section 5

6. Approximate area demanding irrigation :................................

Section 6

7. In the case of rice, approximate area of rice in the chak or block concerned ........................................................

Section 7

8. Date on which irrigation is required:..........................

Section 8

1. Name of Village ......................................................

Section 1

2. Work under which situated ............................................

Section 2

3. Name of distributary of minor from which water is required :

Section 3

4. Change of outlet from which water is required :........................

Section 4

5. Name of crop to be irrigated .........................................

Section 5

6. Approximate area demanding irrigation :................................

Section 6

7. In the case of rice, approximate area of rice in the chak or block concerned ................................................................

Section 7

8. Date on which irrigation is required :.................................

Section 8

9. Date of submission of application to the amin :........................

Section 9

1. The agreement will be accepted to the extent of the area proposed.

Section 1

2. The right to accept or reject the agreement of the defaulters and of all those who persistently fail to clean and maintain their water courses in a fit state of repairs rests with the department.

Section 2

3. The water will be given on turn under [warabandi] /programme.

Section 3

1. Name of village Tahsil...................

Section 1

2. Name of work and Distributary under which it is situated.

Section 2

3. Reasons for requesting remission Le. why crop has failed.

Section 3

4. Details of area on which remission is requested.

Section 4

1. Report No................Dated Month Year.............................

Section 1

2. Name of the offender, parentage, caste, residence etc.................

Section 2

3. Kind of offence; under sub-section of Section 94 of M.P. Irrigation Act.

Section 94

4. Place of offence.

Section 4

5. Date of offence.

Section 5

6. Details of goods forfeited and further proceeding taken...............

Section 6

7. Names and addresses of Witnesses :

Section 7