61. Exemption of certain hoists and lifts.

(i) Date of examination,
(ii) Number of hoists and lifts,
(iii) Details of tests made,
(iv) Results of examination,
(v) Signature of examiner, and
(vi) Designation and qualification of the examiner.
Schedule
(1)
(2)
Class or description of hoist or lift.
Requirements which shall not apply.
Hoists or lifts mainly used for raising materials for
charging blasts furnaces or lime-kilns.
Sub-section (1) (b) in so far as requires a gate at the
bottom landing; sub-section (1) (d) sub-section (1) (e).
Hoists not connected with mechanical power and which are not
used for carrying person.
Sub-section (1) (b) in so far as it requires the hoistway or
liftway enclosure to be so constructed as to prevent any person
or thing from being trapped between any part of the hoist or
lift and any fixed structure or moving part; sub-section (1)
(e).
Rules prescribed under sub-section (2) of Section 29
Rules prescribed under sub-section (2) of Section 29
[62. Cranes and other lifting machines.
(b) A table showing the safe working loads of every kind and size of chain, rope or lifting tackle in use and in the case of multiple sling. The safe working loads at different angles of the legs, shall be posted in the store room or place or in which the chains, ropes or lifting tackles are kept, and in prominent position on the premises and no rope, chain or lifting tackle not shown in the table shall be used. The foregoing provisions of this paragraph shall not apply in respect of any lifting tackle if the safe working load thereof, or, in the case of multiple sling, the safe working load at different angles of the legs, is plainly marked upon it.
Indication of safe loads
Indication of safe loads
[63.
(i) Name of Occupier of Factory..................
(ii) Address of the Factory........................
(iii) Distinguishing number or mark, if any, and description sufficient to identify the lilting machine, chain, rope or the lifting tackle...........
(iv) Date when the lifting machine, chain, rope or lifting tackle was first taken into use in the factory.........................
(v) Date and number of the certificate relating to any test and examination made under Rule 62 (1) and 66 together with the name and address of the person who issued the certificate.........................
(vi) Date of each periodical thorough examination made under clause (a) (iii) of sub-section (1) of Section 29 of the Act and Rule 65 (2), and by whom it was carried out.........................
(vii) Date of annealing or other heat treatment of the chain and other lifting tackle made under Rule 65 (1) and by whom it was carried out...........................
(viii) Particulars of any defect affecting the safe working load found at any such thorough examination or after appealing and of the steps taken to remedy such defects..............
[64. Strength of Crane Tracks.
(i) To provide access to rail tracks of over-head travelling cranes suitable passage-ways of at least 50 cm. (23 in.) width with toe, boards and double hand rails, 90 cm. (3 f.) high shall be provided alongside, and clear of, rail tracks of over-head travelling cranes, such that no moving part of the crane can strike persons on the ways, and the passage-ways shall be at the lower level than the crane tract itself, Safe access laders shall be provided at suitable intervals to afford access to these passage-ways, and from passageways to the rail tracks.
(ii) The State Government may in writing exempt any existing factory from the provisions of sub-rule (1) if by virtue of the construction of the factory it is impossible to provide such a passage-way.]
[65. Maintenance of lifting tackles.
(i) All chains, slings, rings, hooks, shackles and swivels used in connection with molten metal or molten slag or when they are made of half inch bar or smaller, once at least in every six months.
(ii) All other chains, rings, hooks, shackles and swivels in general use once at least in every twelve months :
(i) Chains made of malleable cast iron.
(ii) Plate link chains.
(iii) Chains, rings, hooks, shackles and swivels made of steel or of non-ferrous metal.
(iv) Pitched chains working on sprocket or pocketed wheels,
(v) Kings, hooks, shackles and swivels permanently attached to pitched chains, pulley blocks or weighing machines.
(vi) Hooks and swivels having screw threaded part; or ball bearing or other case hardened parts.
(vii) Sockets shackles secured to wire ropes by white metal capping.
(viii) Bordeaux connections.
[66. Precautions in lifting appliances.
[66A. Examination of eye sight of certain workers.
Rules prescribed under Section 31
Rules prescribed under Section 31
[67. Pressure Vessels of Plants.
(a) "design pressure" means the maximum pressure that a pressure vessel or plant is designed to withstand safety when operating normally;
(b) "maximum permissible working pressure" is the maximum pressure at which a pressure vessel or plant is permitted to be operated or used under this rule;
(c) "plant" means a system of piping that is connected to a pressure vessel and is used to contain a gas, vapour of liquid under pressure greater than the atmospheric pressure and includes that pressure vessel;
(d) "pressure vessel" means an unfired vessel that may be used for containing, storing, distributing, transferring, distilling, processing or otherwise handling any gas, or liquid under pressure greater than the atmospheric pressure and includes any pipe line fitting or other equipment attached thereto or used in connection therewith; and.
(e) "competent person" means a person who is, in the opinion of the Chief Inspector, capable by virtue of his qualification, training and experience conducting a thorough examination and pressure tests, as required on a pressure vessel or plant, and of making a full report on its condition.
(2) Exceptions.
[(a) deleted;]
(b) vessels made of ferrous materials having an internal maximum permissible working pressure not exceeding 1 Kg/sq. cm. (15 Lbs./ sq. inch.);
(c) steam boilers, steam and feed pipes and their fitting coming under the purview of Indian Boilers Act, 1923 (V of 1923);
(d) metal bottles or cylinders used for storage of transport of compressed gases or liquified or dissolved gases under pressure covered by the Gas Cylinder Rule, 1940 framed under the Indian Explosives Act, 1884 (IV of 1884);
(e) vessels is which internal pressure is due solely to the static head of liquid;
(f) vessels with a nominal water capacity not exceeding 500 liters connected in a water pumping system containing air that is compressed to serve as a cushion;
(g) vessels for unclear energy applications;
(h) refrigeration plant having a capacity of 3 tons or less or refrigeration in 24 hours; and
(i) working of cylinders of steam engines or prime mover feed pumps and steam steps; turbine casings; compressor cylinders; steam separators of dryers; steam stramers; steam; de-super heaters; oil seed operators; air receivers for fire sprinkler installations; air receivers; of monotype machines provided the maximum working pressure of the air receiver does not exceed 1.33 Kg. f/ cm 2 (20 Lbs/ sq. in) and the capacity 84.95 liters (3 cu.ft.); air receivers electrical breakers; air receiver of electrical relay; air vessels on pumps pipe/coils, accessories of instruments and appliances such as cylinders and piston assemblies use for operating relays and interlocking appear of guards; vessels with liquids subjected to static head only; and hydraulically operating cylinders other than any cylinder communicating with an air loaded accumulator.
(3) Design and construction.
(a) shall be properly designed on sound engineering practice;
(b) shall be of good construction, sound material, adequate strength and free from any patent defects; and
(c) shall be properly maintained in a safe condition :
(4) Safety devices.
(a) suitable safety valve of other effective pressure relieving device of adequate capacity to ensure that the maximum permissible working pressure of the pressure vessel shall not be exceeded. It shall be set to operate at a pressure not exceeding the maximum permissible working pressure and when more than one protective device are provided, only one of the devices need be set to operate at the maximum permissible working pressure and the additional device shall be set to discharge at a pressure not more than 5 per cent in excess of the maximum permissible working pressure;
(b) a suitable pressure gauge with a dial range not less than 1.5 times the maximum permissible working pressure, easily visible and designed to show at all times correct internal pressure and marked with a prominent red mark at the maximum permissible working pressure of the pressure vessel;
(c) a suitable nipple and globe value connected for the exclusive purpose of attaching a test pressure gauge for clerking the accuracy of the pressure gauge referred to in clause (b) of this sub-rule;
(d) a suitable stop valve or valves by which the pressure vessel may be isolated from other pressure vessel or plant or source of supply of pressure such a stop valve or valves shall be located as close to the pressure vessel as possible and shall be easily accessible; and
(e) a suitable drain cock or valve at the lowest part of the pressure vessel for the discharge of the liquid or other substances that may-collect in the pressure vessel :
(5) Pressure reducing devices.
(b) To further protect the pressure vessel in the event of failure of the reducing value or device, at least one safety value having a capacity sufficient to release all the steam, vapour or gas without undue pressure rise as determined by the pressure at the source of supply and the size of the pipe connected the source of supply, shall be fitted on the low pressure side of the reducing valve.
(6) Pressure vessel or plant being taken into use.
(b) No pressure vessel or plant shall be used in a factory unless there has been obtained from the maker of the pressure vessel or plant or from the competent person a certificate specifying the design pressure or maximum permissible working pressure thereof, and stating, the nature of tests of which the pressure vessel or plant and its fittings (if any) have been subjected and every pressure vessel or plant so used in a factory shall be marked so as to enable it to be indemnified as to be the pressure vessel or plant to which the certificate relates and the certificate shall be kept available for perusal by the Inspector;
(c) No pressure vessel or plant shall be permitted to be operated or used at a pressure higher than its design pressure or maximum permissible working pressure as shown in the certificate.
(7) Service test and examination.
(a) externally, once in every six months;
(b) internally, once in every twelve months;
(c) hydrostatically tested once in every four years :
(d) the hydrostatic test pressure to be carried out for the purposes of this rule shall be 1.25 times the design pressure or 1.50 times the maximum permissible working pressure vessel whichever is less.
(8) Thin walled pressure vessel or plant.
(b) If any information as to the date of construction, the thickness of walls, or maximum permissible working pressure is not available, the age of such pressure vessel or plant shall be determined by the competent person in consultation with the Chief Inspector from the other particulars available with the manager;
(c) Every new and second hand pressure vessel of plant or thin walls to which repairs likely to affect its strength, or safety have been carried out, shall be tested before use to atleast 1-5 times its maximum permissible working pressure.
(9) Report by competent person.
(b) A report of the result of every examination or test carried out shall be completed in the prescribed Form No. 9 and shall be signed by the person making the examination or test, and shall be kept available for perusal by the Inspector at all hours when the Factory or any part thereof is working;
(c) Where the report of any examination under these rules specified any condition for securing the safe working of any pressure vessel or plant, the pressure vessel or plant shall not be used unless the specified conditions is fulfilled;
(d) The competent person making report of any examination under this Rule, shall within seven days of the completion of the examination sent to the Inspector a copy of the report in every case where the maximum permissible working pressure reduced or the examination shows that the pressure vessel or plant or any part thereof can not continue to be used with safety unless certain repairs are carried out or unless any other safety measure is taken.
(10) Application of other laws.
(b) Certificates or reports of any examination or test of any pressure vessel or plant to which sub-rules (7) to (9) do not apply, conducted or required to be conducted under any other law in force and other relevant record relating to such pressure vessel or plant, shall be properly maintained as required under the said law and shall be produced on demand by the Inspector.]
[67A. Water Sealed Gas Holder.
(ii) A permanent register in Form 9-A duly signed by the occupier or manager shall be maintained giving the following particulars :
(a) The serial number of the gasholder, vide Rule 3 above and the particulars of manufacture i.e. maker's name, date of manufacture, capacity, number of lifts, pressure thrown by holder when full of gas.
(b) The dates of inspections carried out as required under Rules 4 and 5 above and by whom carried out.
(c) The method of Inspection used.
(d) Date of painting etc.
(e) Nature of repairs and name of person carrying out repairs, and
(f) Remarks.
(iii) The results of examinations by a competent person carried out under sub-rule (4) and (5) shall be in the Form No. 9-A.
(iv) A copy of the report shall be kept in the register and both the register and the report shall be readily available for inspection.]
Rule prescribed under sub-section (2) of Section 34