← Back to Directory
The M.P. Electricity Reforms First Transfer Scheme Rules, 2003
The M.P. Electricity Reforms First Transfer Scheme Rules, 2003
Sections
1. Short title, extent and commencement.
Section 12. Application of Rule to the Assets and Liabilities.
Section 23. Definitions.
Section 34. Classification of Undertakings of the Board.
Section 45. Transfer of property to the State.
Section 56. Transfer of Undertakings by the State.
Section 67. Transfer of Personnel.
Section 78. Rights and obligations of third parties restricted.
Section 89. Pending suits, proceedings, etc.
Section 910. Classifications and transfer of property, rights, liabilities and proceedings to be provisional in the first instance.
Section 1011. Transfer by operation of law.
Section 1112. Rights and Powers of the Transferees during the provisional period.
Section 1213. Decision of State Government to be final.
Section 13
the-m-p-electricity-reforms-first-transfer-scheme-rules-2003.json
•
13 Sections
•
Madhya Pradesh
{
"id": 19097,
"slug": "the-m-p-electricity-reforms-first-transfer-scheme-rules-2003",
"title": "The M.P. Electricity Reforms First Transfer Scheme Rules, 2003",
"short_title": "The M.P. Electricity Reforms First Transfer Scheme Rules, 2003",
"act_number": "Published vide Notification No. 6259/FRS/17/13/200",
"act_year": 2003,
"act_type": "STATE",
"location": "Madhya Pradesh",
"law_status": "unknown",
"enactment_date": null,
"description": "The M.P. Electricity Reforms First Transfer Scheme Rules, 2003",
"preamble": "",
"section_label": "Section",
"sections": [
{
"number": "1",
"title": "1. Short title, extent and commencement.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 0
},
{
"number": "2",
"title": "2. Application of Rule to the Assets and Liabilities.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 1
},
{
"number": "3",
"title": "3. Definitions.",
"chapter": null,
"content": "(a) \"Act\" for the purpose of these Scheme Rules means the Madhya Pradesh Vidyut Sudhar Adhiniyam, 2000 (No. 4 of 2001);\n(b) \"Board\" means Madhya Pradesh State Electricity Board constituted under Section 5 of the Electricity (Supply) Act, 1948 (54 of 1948);\n(c) \"Central Act\" means the Electricity Act, 2003 (36 of 2003);\n(d) \"Company\" means the company formed and registered under the Companies Act, 1956 (1 of 1956);\n(e) \"Commission\" means the Madhya Pradesh Electricity Regulatory Commission, constituted under Section 3 of the Madhya Pradesh Vidyut Sudhar Adhiniyam, 2000 (No. 4 of 2001) and recognized under Section 82 of the Central Act;\n(f) \"Date of the transfer\" means the date notified by the State Government rue118 transfer of factions, properties, interest, rights and liabilities proceedings or personnel of the Board to the relevant Transferee in accordance with the Act and these Scheme Rules;\n(g) \"Distribution Companies\" means Discom 1, Discom 2 and Discom 3 for distribution and retail supply of electricity;\n(h) \"Discom 1\" means Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited, a company incorporated with the main object of undertaking electricity distribution and retail supply in the Commissioneries of Jabalpur, Rewa, and Sagar of the State of Madhya Pradesh;\n(i) \"Discom 2\" means Madhya Pradesh Madhya Kshetra Vidvut Vitaran Company Limited, a company incorporated with the main object of undertaking electricity distribution and retail supply in the Commissioneries of Bhopal, Chambal and Gwalior of the State of Madhya Pradesh;\n(j) \"Discom 3\" means Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited, a company incorporated with the main object of undertaking electricity distribution and retail supply in the Commissioneries of Indore and Ujjain of the State of Madhya Pradesh;\n(k) \"Genco\" means the Madhya Pradesh Power Generating Company Limited, a company incorporated with the main object of generation of electricity in the State of Madhya Pradesh;\n(l) \"Liabilities\" include all liabilities, debts duties, obligations and other outgoing including statutory liabilities and Government levies of whatever nature and contingent liabilities which may arise in regard to the dealings before the date of the transfer in respect of the undertaking transferred under the Rules;\n(m) \"Personnel\" means workmen employees, staff and officers of the Board by whatever name called and includes trainees, if any of the recruitment in the Board and those on deputation from the Board to other organizations or institutions;\n(n) \"Proceeding\" means the proceedings of whatever nature including suits, appeals, complaints, petitions, applications, conciliatory, arbitration whether civil or criminal or otherwise;\n(o) \"Properly\" means all assets includes power systems, plant, machinery, land, building, offices, stores furnitures, fixtures, vehicles, residential quarters and guest houses and amenities and installations pertaining and attached thereto and other movable an immovable assets, cash in hand, cash at bank, investments, book debts-corporeal and incorporeal, tangible and intangible assets, benefits, licenses, consents, authorities, registrations, patents, trade marks and powers of every kind, nature and description whatsoever, privileges, liberties, easements, advantages, benefits and approvals, contracts, deeds, schemes, bonds, agreements and other instruments and interest of whatever nature and wherever, situate;\n(p) \"Schedule\" means the Schedule appended to these Scheme Rules;\n(q) \"Shite\" means the State of Madhya Pradesh;\n(r) \"Transco\" means the Madhya Pradesh Power Transmission Company Limited, a company incorporated with the main object of undertaking the transmission of electricity in the State of Madhya Pradesh;\n(s) \"Transferee\" means TRANSCO or GENCO or DISCOM-1, or D1SCOM-2 or DISCOM-3, as the case may be in whom the functions and undertakings of the Board are vested in terms of the provisions of the Act read with these Scheme Rules;\n(t) \"Undertaking\" means the functions of the Board and a block or blocks of properties, interest, rights and liabilities to the extent and in the manner specified as a part of the undertakings and such other properties, interest, rights and liabilities as specified in these Scheme Rules relevant to the functions;\n(u) Words and expressions used in this Scheme rules and defined in the Act and Central Act but not specifically defined in these scheme rules shall have the same meaning as assigned to them in the Act and Central Act.",
"footnote": "",
"is_definition": true,
"sort_order": 2
},
{
"number": "4",
"title": "4. Classification of Undertakings of the Board.",
"chapter": null,
"content": "(a) General Undertakings as set out in Schedule-'A';\n(b) Transmission Undertakings as set out in Schedule-'B';\n(c) For DISCOM 1, the Distribution Undertakings as set out in Schedule-'C';\n(d) For DISCOM 2, the Distribution Undertakings as set out in Schedule-'D';\n(e) For DISCOM 3, the Distribution Undertakings as set out in Schedule-'E'; and\n(f) The Undertaking as set out in Schedule-'F'.",
"footnote": "",
"is_definition": false,
"sort_order": 3
},
{
"number": "5",
"title": "5. Transfer of property to the State.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 4
},
{
"number": "6",
"title": "6. Transfer of Undertakings by the State.",
"chapter": null,
"content": "(b) The value of the assets to be transferred to the Transferees shall be the fair value determined in any one or more of the following basis.\n(i) Revenue earning potential, or\n(j) Depreciated replacement value, or\n(k) Book value\n(c) The opening balance-sheet of the Transferees may be finalised and notified by the State Government at any time during the provisional period mentioned in Rule 10 of these Scheme Rules.",
"footnote": "",
"is_definition": false,
"sort_order": 5
},
{
"number": "7",
"title": "7. Transfer of Personnel.",
"chapter": null,
"content": "(b) The State Government may issue orders from time to time directing the personnel rendering services in the Board relating to Undertakings classified in two or more of the Schedules, to be assigned to the Undertakings classified under a specified schedule and thereupon such personnel shall be deemed to have assigned to the services of such Undertakings for all intent and purposes.\n(i) \"Existing Pensioner\" means all the persons eligible for the pension as on the date of the transfer from the Board and shall include family members of the personnel, and\n(ii) \"Terminal Benefits\" means the gratuity, pension, dearness and other applicable relief, medical benefit, and other applicable benefits including the right to have the appropriate revisions in the above benefits consistent with the practice that were prevalent in the Board.",
"footnote": "",
"is_definition": false,
"sort_order": 6
},
{
"number": "8",
"title": "8. Rights and obligations of third parties restricted.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 7
},
{
"number": "9",
"title": "9. Pending suits, proceedings, etc.",
"chapter": null,
"content": "(b) Such proceedings may be continued in the same manner and to the same extent as it would or might have been continued, prosecuted and enforced by or against the Board if the transfers specified in these Scheme Rules had not been made.",
"footnote": "",
"is_definition": false,
"sort_order": 8
},
{
"number": "10",
"title": "10. Classifications and transfer of property, rights, liabilities and proceedings to be provisional in the first instance.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 9
},
{
"number": "11",
"title": "11. Transfer by operation of law.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 10
},
{
"number": "12",
"title": "12. Rights and Powers of the Transferees during the provisional period.",
"chapter": null,
"content": "",
"footnote": "",
"is_definition": false,
"sort_order": 11
},
{
"number": "13",
"title": "13. Decision of State Government to be final.",
"chapter": null,
"content": "Schedule 'A'\nGeneration Undertakings\nGeneration Undertakings\nI. Existing Power Stations :\nThermal :\nA. Satpura Station wit PH II 1 x 200 MW plus 1 x 210 MW and PH III 2 x 210 MW generating units and with all associated and related equipment such as generators, turbines, boilers, condensers, electrostatic precipitators, controls and instrumentation, Railway Sidings, coal handling system, ash handling system, ash pond, raw water supply and treatment system, DM water plant, secondary fuel oil storage facilities and its handling system, switch yard including step up transformers, service transformers, auxiliary unit transformers circuit breakers, HT & LT switchgears, control and protection system, overhead cranes, chimney, Stores, spare parts, consumables, raw materials etc. and works in progress.\nB. Birsingpur Station with 4 generating units of 210 MW capacity each with all associated and related equipment such as generators, turbines, boilers, condensers, electrostatic precipitators, controls and instrumentation, Railway Sidings, coal handling system, ash handling system, ash pond, raw water supply and treatment system, DM water plant, secondary fuel oil storage facilities and its handling system, switch yard including step up transformers service transformers, auxiliary unit transformers circuit breakers, HT & LT switchgears, control and protection system, overhead cranes, chimney, Stores, spare parts, consumables, raw materials etc, and works in progress.\nC. Amarkantak Station with 1 x 30 MW, 1 x 20 MW and 2 x 120 MW and with all associated and related equipment such as generators, turbines, boilers, condensers, electrostatic precipitators, controls and instrumentation, Railway Sidings, coal handling system, ash handling system, ash pond, raw water supply and treatment system, DM water plant, secondary fuel oil storage facilities and its handling system, switch yard including step up transformers, service transformers, auxiliary unit transformers circuit breakers, HT & LT Switchgears, control and protection system, overhead cranes, chimney, Stores, spare parts, consumables, raw materials etc, and works in progress.\nHydel Power Stations :\n(a) Bansagar-PH-II (Silpara Station) : Penstocks at the intake structure, penstock gates, draft tube gate, tail race channel, power house with 2 units of 15 MW capacity each a long with generators turbines, and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\n(b) Bargi Station : Penstock at the intake structure, penstock gates, draft tube gate, tail race channel, power house with 2 units of 45 MW capacity each along with generators, turbines and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\n(c) Bansagar PH I and PH III Station ; Penstocks at the intake structure, penstock gates, draft tube gate, tail race channel, power house with 3 units of 105 MW capacity each (Bansagar PH-I, Tons Hydel Power Station) and 3 units of 20 MW each (Bansagar PH-III, Deolond) along with generators, turbines and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\n(d) Birsinghpur Station : Penstocks at the intake structure, penstock gates, draft tube gate, tail race channel, power house with 1 unit of 20 MW capacity each along with generators, turbines and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\nShared Generating Stations :\n(a) Satpura Thermal Power Station ; (an interstate project shared between Madhya Pradesh and Rajasthan) with 60% share of Madhya Pradesh having five units of 62.5 MW capacity each along with all associated and related equipment such as generators, turbines, boilers auxiliary units with controls and instrumentation, Railway sidings social handling system, ash handling system, ash pond, raw water supply and treatment system, cooling towers, secondary fuel oil storage facilities and its handling system and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, overhead cranes, stores, spare parts, consumables, raw materials etc. and, works in progress.\n(b) Chambal Complex : (an interstate project shared between Madhya Pradesh and Rajasthan) with 50% share of Madhya Pradesh, with 50% share of Rajasthan, on cost and benefits with 5 unit of 23 MW of Gandhi Sagar, 4 units of 43 MW of Rana Pratap Sagar and 3 units of 33 MW of Jawahar Sagar. All assets are owned by both the Electricity Boards in the same ratio O & M expenses are being met by both the Electricity Boards and reaping the power benefits based on their share.\n(c) [Pench Station] : Penstocks at the intake structure, penstock gates, draft tube gate, tail race channel, power house with 2 units of 80 MW capacity each along with generators, turbines and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, pen stock and draft tube gates, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\n(d) [Rajghat Station] : Penstocks at the intake structure, penstock, gates, draft tube gate, tail race channel, power house with 3 units of 15 MW capacity each along with generators, turbines and all associated and related equipment and switch yard including step up transformers, step down transformers, circuit breakers, control and protection system, pen stock and draft tube gates, overhead cranes, gantry cranes, hydraulic hoists, power house stores, spare parts, consumables, raw materials etc. and works in progress.\nII. Power Projects Under Construction :\n(a) Bansagar Hydel Power Station PH-IV (2 x 10 MW)\n(b) Madikheda Hydel Power Station (2 x 20 + 1 x 20 MW)\n(c) Proposed SGTPS, Birsinghpur Extention (500 MW)\nIII. General Assets :\n(a) The following, if they exclusively or primarily pertain to the generating stations or projects referred to in Paras I and II above or activities related to such generating stations or projects :\nSpecial tools and equipment, material handling equipment, earth movers, bulldozers, concrete mixtures, cranes, trailers, heavy and light vehicles, furniture, fixtures, office equipment, air conditioners, refrigerators, computers and signal systems, spares, consumables, raw materials, land and civil works installations including dams, barrages, canals roads, buildings, staff quarters, rest houses, properties and structures and their associated buildings, schools, dispensaries, testing laboratories and equipment,training centres, workshops, works in progress, machinery and equipment sent for repairs, scraps and obsolete.\n(b) The office establishment and other buildings and lands, not covered elsewhere in this schedule, which are predominantly occupied/ used for the activities of Generation Undertakings as on the effective date of transfer.\nIV. Miscellaneous:\n(1) Contracts, agreements, interest and arrangements to the extent they are associated with or related to Generation activities or to the Undertakings or assets referred to in Paras I to III above.\n(2) Loans, secured and unsecured to the extent they are associated with or related to Generation activities or to the Undertakings or assets referred to in Paras I to III above.\n(3) Other current assets to the extent they are associated with or related to Generation activities or to the Undertakings or assets referred to in Paras I to III above.\n(4) Other current liabilities and provisions to the extent they are associated with or related to Generation activities or to the Undertakings or Assets referred to in Paras I to III above.\n(5) Contingent liabilities to the extent they are recognised and are associated with or related to Generation activities or to the undertakings or Assets referred to in Paras I to III above.\n(6) Other liabilities to the extent they are associated with or related to Generation activities or to the Undertakings or Assets referred to in Paras I to III above.\n(7) Proceedings to the extent they are associated with or related to Generation activities or to the Undertakings or Assets referred to in Paras I to III above.\nV. General:\n(1) The assets of the generating Undertaking shall vest in GENCO.\n(2) The State Government shall before the end of the provisional period mentioned in Rule 10 allocate the liabilities of MP SEB to GENCO to the extent and in such manner, as the State Government may deem proper.\n(3) in consideration of the transfer mentioned above, the State Government may, direct GENCO to issue instruments such as equity shares, preference shares, debentures and other securities in favour of the State Government or in other Company as the State Government may direct taking into account the assets and liabilities transferred from MESEB to GENCO.\nSchedule 'B'\nTransmission Undertaking\nTransmission Undertaking\nI. Transmission Assets :\nII. General Assets :\n(a) The following, if they exclusively or primarily pertain to the above mentioned transmission systems properties or projects or activities related to such transmission systems, properties or projects :\nSpecial tools and equipment, material handling equipment, earth movers, bulldozers, concrete mixtures, cranes, trailers, heavy and light vehicles, furniture, fixtures, office equipment, air conditioners, refrigerators, computers and signal systems, spares, consumables, raw materials, lands and civil works installations including roads, buildings, staff quarters, rest houses, properties and structures and their associated buildings, schools, dispensaries, testing laboratories and equipment, training centers, workshops, works in progress, machinery and equipment sent for repairs, scraps and obsolete.\n(b) The following pertaining to the shared Sub-stations to the extent of rights which vested in the Board.\nSpecial tools and equipment, material handling equipment, earth movers, bulldozers, concrete mixtures, cranes, trailers, heavy and light vehicles, furniture, fixtures, office equipment, air conditioners, refrigerators, computers and signal systems, spares, consumables, raw materials, lands and civil works installations including roads, buildings, staff quarters, rest houses, properties and structures and their associated buildings, schools, dispensaries, testing laboratories and equipment, training centers, workshops, works in progress, machinery and equipment sent for repairs, scraps and obsolete.\n(c) All independent and stand-alone Rest houses, which are not part of sub-stations/installations of the Board.\n(d) The office establishment and other buildings and lands, not covered elsewhere in this schedule, which are predominantly occupied/ used for the activities of Generation Undertakings as on the effective date of transfer.\nIII. Miscellaneous :\n(1) Contracts, agreements, interest and arrangements to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(2) Loans, secured and unsecured to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(3) Other Current Assets to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(4) Other Current liabilities and provisions to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(5) Contingent liabilities to the extent they are recognised and are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(6) Other liabilities to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\n(7) Proceedings to the extent they are associated with or related to transmission activities or to the Undertakings or Assets referred to in Paras I and II above.\nIV. General :\n(1) The assets of the transmission Undertaking shall vest in TRANSCO.\n(2) The State Government shall before the end of the provisional period mentioned in Rule 10 allocate the liabilities of MPSEB to TRANSCO to the extent and in such a manner, as the State Government may deem proper.\n(3) In consideration of the transfer mentioned above, the State Government may, direct TRANSCO to issue instruments such as equity shares, preference shares, debentures and other securities in favour of the State Government or in other Company as the State Government may direct taking into account the assets and liabilities transferred from MPSEB to TRANSCO.\nSchedule 'C'\nDistribution Undertaking of Discom 1\nDistribution Undertaking of Discom 1\nI. Distribution Assets :\nII. General Assets :\nIII. Miscellaneous :\n(1) Contracts, agreements, interest and arrangements to the extent they are associated with or related to distribution activities or to the Undertakings or assets referred to in Paras I and II above.\n(2) Loans, secured and unsecured to the extent they are associated with or related to distribution activities or to the Undertakings or assets referred to in Paras I and II above.\n(3) Other Current Assets to the extent they are associated with or related to distribution activities or to the Undertakings or assets referred to in Paras I and II above.\n(4) Other current liabilities and provisions to the extent they are associated with or related to distribution activities of the Undertakings or Assets referred to in Paras I and II above.\n(5) Contingent liabilities to the extent they are recognised and are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(6) Other liabilities to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(7) Proceedings to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\nIV. General :\n(1) The assets of the distribution Undertaking shall vest in DISCOM 1.\n(2) The State Government shall before the end of the provisional period mentioned m Rule 10 allocate the liabilities of MPSEB to DISCOM 1 to the extent and in such a manner, as the State Government may deem proper.\n(3) In consideration of the transfer mentioned above, the State Government may, direct DISCOM 1 to issue instruments such as equity shares, preference shares, debentures and other securities in favour of the State Government or in other Company as the State Government may direct taking into account the assets and liabilities transferred from MPSEB to DISCOM 1.\nSchedule 'D'\nDistribution Undertaking of Discom 2\nDistribution Undertaking of Discom 2\nI. Distribution Assets :\nII. General Assets :\nIII. Miscellaneous:\n(1) Contracts, agreements, interest and arrangements to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(2) Loans, secured and unsecured to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(3) Other Current Assets to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(4) Other current liabilities and provisions to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras 1 and II above.\n(5) Contingent liabilities to the extent they are recognised and are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(6) Other liabilities to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(7) Proceedings to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\nIV. General :\n(1) The assets of the distribution Undertaking shall vest in DISCOM 2.\n(2) The State Government shall before the end of the provisional period mentioned in Rule 10 allocate the liabilities of MPSEB to DISCOM 2 to the extent and in such a manner as the State Government may deem proper.\n(3) In consideration of the transfer mentioned above, the State Government may, direct DISCOM 2 to issue instruments such as equity shares, preference shares, debentures and other securities in favour of the State Government or in other Company as the State Government may direct taking into account the assets and liabilities transferred from MPSEB to DISCOM 2.\nSchedule 'E'\nDistribution Undertaking of Discom 3\nDistribution Undertaking of Discom 3\nI. Distribution Assets :\nII. General Assets :\nIII. Miscellaneous :\n(1) Contracts, agreements, interest and arrangements to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(2) Loans, secured and unsecured to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(3) Other Current Assets to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(4) Other Current liabilities and provisions to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(5) Contingent liabilities to the extent they are recognized and are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(6) Other liabilities to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\n(7) Proceedings to the extent they are associated with or related to distribution activities or to the Undertakings or Assets referred to in Paras I and II above.\nIV. General :\n(1) The assets of the distribution undertaking shall vest in DISCOM 3.\n(2) The State Government shall before the end of the provisional period mentioned in Rule 10 allocate the liabilities of MPSEB to DISCOM 3 to the extent and in such a manner, as the State Government may deem proper.\n(3) In consideration of the transfer mentioned above, the State Government may, direct DISCOM 3 to issue instruments such as equity shares, preference shares, debentures and other securities in favour of the State Government or in other Company as the State Government may direct taking into account the assets and liabilities transferred from MPSEB to DISCOM 3.\nSchedule 'F'\nFunctions and Undertakings Retained in MPSEB\nFunctions and Undertakings Retained in MPSEB\n(1) The bulk purchase and bulk supply functions, namely, purchase of electricity in bulk from the generating companies including GENCO and supply of electricity in bulk to the DISCOMS. MPSEB will not, however, undertake the activity of supply of electricity to any consumer in the State of Madhya Pradesh from such date as the State Government may direct in this behalf.\n(2) The liabilities to the extent to be retained as per the direction the State Government may issue in this behalf.\n(3) The assets in the form of amounts, which the State Government may direct as payable by the transferee to MPSEB to the extent and in the manner as the State Government may consider appropriate to compensate MPSEB for the liabilities, retained as per clause (2) above.\n(4) Cash and Bank Balance to be retained and shall be given to the transferees to the extent they are associated with or related to them, or as per the direction the State Government may issue in this behalf.\n(5) Fixed Deposits lying with State Bank of India being the amount taken as security deposit from independent power producers.",
"footnote": "",
"is_definition": false,
"sort_order": 12
}
],
"metadata": {
"Act ID": "mp234",
"Act Number": "Published vide Notification No. 6259/FRS/17/13/2002, dated the 30th September, 2003, in M.P. Rajpatra (Asadharan)",
"Enactment Date": "",
"Act Year": "2003",
"Short Title": "The M.P. Electricity Reforms First Transfer Scheme Rules, 2003",
"Type": "STATE",
"Location": "Madhya Pradesh"
},
"updated_at": "2026-09-29 21:55:20"
}