(a) whether or not work has commenced on the contract:
(b) the stage of completion of contract activity; or
(c) the amount of profits expected to arise on other contracts which are not treated as a single construction contract in accordance with paragraphs.
Changes in Estimates
Disclosure
Section 35 • The Companies (Accounting Standards) Rules, 2006
35. When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.
the-companies-accounting-standards-rules-2006-sec-35.json
•
Section 35
{
"act_title": "The Companies (Accounting Standards) Rules, 2006",
"act_slug": "the-companies-accounting-standards-rules-2006",
"section_label": "Section",
"section": {
"number": "35",
"title": "35. When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.",
"chapter": null,
"content": "(a) whether or not work has commenced on the contract:\n(b) the stage of completion of contract activity; or\n(c) the amount of profits expected to arise on other contracts which are not treated as a single construction contract in accordance with paragraphs.\nChanges in Estimates\nDisclosure",
"footnote": "",
"is_definition": false,
"sort_order": 70
},
"prev_section": "34",
"next_section": "38"
}