(a) the particulars of specified end use, if any;
(b) the mine dossier containing particulars of the Schedule I coal mine;
(c) the terms and conditions associated with the allotment, including the reserve price, eligibility conditions, the process of conduct of allotment and other related information;
(d) agreements proposed to be entered into with the successful allottee.
(a) progress of development of coal blocks by the applicant in the past;
(b) financial details of the applicant, including the net-worth and turnover;
(c) technical capabilities of the applicant and the technology proposed to be used for mining;
(d) the end-use towards which the coal is proposed to be utilised;
(e) demand-supply gap;
(f) assessment of requirements of the State;
(g) in case of utilisation of the coal towards any specified end use
(i) state of preparedness of the end use facility;
(ii) proximity of the end use facility to the relevant coal mine;
(iii) in case of generation of power being the specified end-use, the per-capita power availability in the State of the applicant company.
Section 11 • The Coal Mines (Special Provisions) Rules, 2014
11. Allotment.
the-coal-mines-special-provisions-rules-2014-sec-11.json
•
Section 11
{
"act_title": "The Coal Mines (Special Provisions) Rules, 2014",
"act_slug": "the-coal-mines-special-provisions-rules-2014",
"section_label": "Section",
"section": {
"number": "11",
"title": "11. Allotment.",
"chapter": null,
"content": "(a) the particulars of specified end use, if any;\n(b) the mine dossier containing particulars of the Schedule I coal mine;\n(c) the terms and conditions associated with the allotment, including the reserve price, eligibility conditions, the process of conduct of allotment and other related information;\n(d) agreements proposed to be entered into with the successful allottee.\n(a) progress of development of coal blocks by the applicant in the past;\n(b) financial details of the applicant, including the net-worth and turnover;\n(c) technical capabilities of the applicant and the technology proposed to be used for mining;\n(d) the end-use towards which the coal is proposed to be utilised;\n(e) demand-supply gap;\n(f) assessment of requirements of the State;\n(g) in case of utilisation of the coal towards any specified end use\n(i) state of preparedness of the end use facility;\n(ii) proximity of the end use facility to the relevant coal mine;\n(iii) in case of generation of power being the specified end-use, the per-capita power availability in the State of the applicant company.",
"footnote": "",
"is_definition": false,
"sort_order": 10
},
"prev_section": "10",
"next_section": "12"
}