I. The execution, supervision and audit of works entrusted to the Public Works Department will, as heretofore, continue to be subject to the rules of that Department as published in the Public Works Code.
II. The rules hereinafter following apply only to works to be constructed independently of the Public Works Department by local authorities authorised under the Local Authorities Loans Act, 1914, to raise money in the open market or by taking a loan from the State Government for the purpose.
III. It shall be the duty of the Executive Engineer in whose district such works are being constructed out of loans raised by local authorities in the open market or be taking a loan from the State Government under the Local Authorities Loans Act, 1914, or of any person specially authorised by the State Government in this behalf, to inspect such works and the accounts connected therewith at such intervals as the State Government or the Chief or the Superintending Engineer may direct.
IV. Such inspection shall ordinarily be conducted quarterly by the Executive Engineer and monthly by the Public Works Department Sub-Divisional Officer in whose charge the work may be and shall be chiefly directed to ascertaining that the quantity and quality of the work executed and the progress made in construction are fairly commensurate with the outlay charged in the accounts.
V. (i) For the purpose of sub-rule IV under rule 12 the local authority shall cause a continuous record of expenditure to be maintained and posted monthly in the Public Works Department "Register of Works" - Form 'A' appended to these rules. The measurements for the month and for the year and upto date must be shown for each item, but corresponding expenditure on items need only be given for those works estimated to cost over Rs. 5,000. The expenditure for the work for the month, the expenditure for the year and the total expenditure should be shown. Columns should be provided for "Materials at site" and for liabilities. With the above information the quantities and cost (calculated on the normal cost system*) may, at any time, be compared with the estimate. With the sanction of the State Government the account forms may be modified and actual expenditure by items omitted in any special cases in which this is deemed desirable.
* Note. - The normal cost is the cost at estimated rates of all works actually executed.
(ii) If a loan is raised for the construction of roads, a return of road material should be prepared for the inspection by the Public Works Department officers.
VI. Every deviation from any project as sanctioned, which in the opinion of the inspecting officer is likely to entail, any increase in the outlay exceeding five per cent, on the estimates approved, or to impair or diminish the utility of the works under construction, shall be reported to the State Government and also to the local authority concerned, and no such deviation shall in any case be proceeded with or without the sanction of the State Government and of such local authority, or otherwise than in accordance with such requirements as the State Government or such local authority with the approval of the State Government may impose as to additions, alterations and amendments in the estimates.
VII. Every inspecting officer shall furnish the Chief or Superintending Engineer with a brief report of the inspections performed by him with such remarks on the construction and progress of the works as he may deem necessary. The Chief or Superintending Engineer shall bring to the notice of the State Government any points on which the orders of the State Government are considered to be necessary.
VIII. In regard to the loan accounts of local authorities whose accounts are subject to an official audit by the Accountant General a test audit shall be conducted by the Local Fund Audit Department of the Accountant General's office. In all other cases the test audit shall be carried out once a year as the Accountant General may direct, and shall be confined exclusively to the accounts of expenditure from the loan.
Section 12 • The Bombay Local Authorities Loans Rules, 1923
12. Control and inspection of works and accounts.
the-bombay-local-authorities-loans-rules-1923-sec-12.json
•
Section 12
{
"act_title": "The Bombay Local Authorities Loans Rules, 1923",
"act_slug": "the-bombay-local-authorities-loans-rules-1923",
"section_label": "Section",
"section": {
"number": "12",
"title": "12. Control and inspection of works and accounts.",
"chapter": null,
"content": "I. The execution, supervision and audit of works entrusted to the Public Works Department will, as heretofore, continue to be subject to the rules of that Department as published in the Public Works Code.\nII. The rules hereinafter following apply only to works to be constructed independently of the Public Works Department by local authorities authorised under the Local Authorities Loans Act, 1914, to raise money in the open market or by taking a loan from the State Government for the purpose.\nIII. It shall be the duty of the Executive Engineer in whose district such works are being constructed out of loans raised by local authorities in the open market or be taking a loan from the State Government under the Local Authorities Loans Act, 1914, or of any person specially authorised by the State Government in this behalf, to inspect such works and the accounts connected therewith at such intervals as the State Government or the Chief or the Superintending Engineer may direct.\nIV. Such inspection shall ordinarily be conducted quarterly by the Executive Engineer and monthly by the Public Works Department Sub-Divisional Officer in whose charge the work may be and shall be chiefly directed to ascertaining that the quantity and quality of the work executed and the progress made in construction are fairly commensurate with the outlay charged in the accounts.\nV. (i) For the purpose of sub-rule IV under rule 12 the local authority shall cause a continuous record of expenditure to be maintained and posted monthly in the Public Works Department \"Register of Works\" - Form 'A' appended to these rules. The measurements for the month and for the year and upto date must be shown for each item, but corresponding expenditure on items need only be given for those works estimated to cost over Rs. 5,000. The expenditure for the work for the month, the expenditure for the year and the total expenditure should be shown. Columns should be provided for \"Materials at site\" and for liabilities. With the above information the quantities and cost (calculated on the normal cost system*) may, at any time, be compared with the estimate. With the sanction of the State Government the account forms may be modified and actual expenditure by items omitted in any special cases in which this is deemed desirable.\n* Note. - The normal cost is the cost at estimated rates of all works actually executed.\n(ii) If a loan is raised for the construction of roads, a return of road material should be prepared for the inspection by the Public Works Department officers.\nVI. Every deviation from any project as sanctioned, which in the opinion of the inspecting officer is likely to entail, any increase in the outlay exceeding five per cent, on the estimates approved, or to impair or diminish the utility of the works under construction, shall be reported to the State Government and also to the local authority concerned, and no such deviation shall in any case be proceeded with or without the sanction of the State Government and of such local authority, or otherwise than in accordance with such requirements as the State Government or such local authority with the approval of the State Government may impose as to additions, alterations and amendments in the estimates.\nVII. Every inspecting officer shall furnish the Chief or Superintending Engineer with a brief report of the inspections performed by him with such remarks on the construction and progress of the works as he may deem necessary. The Chief or Superintending Engineer shall bring to the notice of the State Government any points on which the orders of the State Government are considered to be necessary.\nVIII. In regard to the loan accounts of local authorities whose accounts are subject to an official audit by the Accountant General a test audit shall be conducted by the Local Fund Audit Department of the Accountant General's office. In all other cases the test audit shall be carried out once a year as the Accountant General may direct, and shall be confined exclusively to the accounts of expenditure from the loan.",
"footnote": "",
"is_definition": false,
"sort_order": 14
},
"prev_section": "11",
"next_section": "13"
}