(a) point indications for all facing points in the route show the points to be set and locked in the correct position;
(b) any points not showing an indication shall be traversed in the trailing direction.
Chapter IV
Working of Trains
Section 24 • The Bangalore Metro Railway (General) Rules, 2011
24. Failure of route setting.
the-bangalore-metro-railway-general-rules-2011-sec-24.json
•
Section 24
{
"act_title": "The Bangalore Metro Railway (General) Rules, 2011",
"act_slug": "the-bangalore-metro-railway-general-rules-2011",
"section_label": "Section",
"section": {
"number": "24",
"title": "24. Failure of route setting.",
"chapter": null,
"content": "(a) point indications for all facing points in the route show the points to be set and locked in the correct position;\n(b) any points not showing an indication shall be traversed in the trailing direction.\nChapter IV\nWorking of Trains",
"footnote": "",
"is_definition": false,
"sort_order": 23
},
"prev_section": "23",
"next_section": "25"
}