Section 59. Completion of final land pooling scheme

(1) The Commissioner shall, duly furnishing the details of completion of the works along with the necessary infrastructure plans, publish a notice of completion of the final land pooling scheme within the period as may be prescribed.
(2) The Commissioner shall also publish the details of re-allotment of reconstituted plots / lands along with land mutation records and land pooling ownership certificates.
(3) On verification of the details in sub-section (1) and sub-section (2), the Commissioner shall issue the Completion Certificate along with layout of final land pooling scheme.