(a) The augmentation of ports is already permitted at STM-1 level and therefore requires no regulatory prescription.
(b) The augmentation at STM-1 or other levels should be mutually agreed upon by the Parties instead of being mandated.
(c) Depending upon traffic requirement, augmentation may be allowed at STM-1 level also.
(d) When the existing POI exceeds 63 E1s, further augmentation may be done on STM-1 Level subject to technical feasibility in both the TSPs' nodes.
(e) The Telecommunication Interconnection (Port Charges) Regulation, 2001 prescribes port charges on the basis of E1 ports.
(f) Augmentation of ports must be entirely based on capacity required on both sides.
(g) The augmentation of ports may be allowed at higher levels such as STM-1 in place of E1. It leads to lower hardware costs and much better bit rates and capable of carrying both circuit switched and packet switched calls. For smaller requirements, the existing practice of E1 level ports should be allowed to be continued.
(a) Most of the interconnect equipment (viz. Media Gateways, MSCs etc.) of the TSPs is equipped with STM-1 ports. The proportion of STM-1 ports vis-à-vis E1 ports on such equipment is growing in favour of STM-1 ports.
(b) The STM-1 ports are not only economical but also require much less rack space. As a result, the same rack/shelf of equipment can accommodate much higher interconnection capacity if it contains STM-1 ports as against the scenario when it contains only E1-ports. Thus interconnection at STM-1 level may be a win-win proposition for both the interconnecting TSPs.
Section 14 • Telecommunication Interconnection Regulations, 2018
14. Whether augmentation of ports be allowed at higher levels such as STM-1 in place of E1s?
telecommunication-interconnection-regulations-2018-sec-14.json
•
Section 14
{
"act_title": "Telecommunication Interconnection Regulations, 2018",
"act_slug": "telecommunication-interconnection-regulations-2018",
"section_label": "Section",
"section": {
"number": "14",
"title": "14. Whether augmentation of ports be allowed at higher levels such as STM-1 in place of E1s?",
"chapter": null,
"content": "(a) The augmentation of ports is already permitted at STM-1 level and therefore requires no regulatory prescription.\n(b) The augmentation at STM-1 or other levels should be mutually agreed upon by the Parties instead of being mandated.\n(c) Depending upon traffic requirement, augmentation may be allowed at STM-1 level also.\n(d) When the existing POI exceeds 63 E1s, further augmentation may be done on STM-1 Level subject to technical feasibility in both the TSPs' nodes.\n(e) The Telecommunication Interconnection (Port Charges) Regulation, 2001 prescribes port charges on the basis of E1 ports.\n(f) Augmentation of ports must be entirely based on capacity required on both sides.\n(g) The augmentation of ports may be allowed at higher levels such as STM-1 in place of E1. It leads to lower hardware costs and much better bit rates and capable of carrying both circuit switched and packet switched calls. For smaller requirements, the existing practice of E1 level ports should be allowed to be continued.\n(a) Most of the interconnect equipment (viz. Media Gateways, MSCs etc.) of the TSPs is equipped with STM-1 ports. The proportion of STM-1 ports vis-à-vis E1 ports on such equipment is growing in favour of STM-1 ports.\n(b) The STM-1 ports are not only economical but also require much less rack space. As a result, the same rack/shelf of equipment can accommodate much higher interconnection capacity if it contains STM-1 ports as against the scenario when it contains only E1-ports. Thus interconnection at STM-1 level may be a win-win proposition for both the interconnecting TSPs.",
"footnote": "",
"is_definition": false,
"sort_order": 27
},
"prev_section": "13",
"next_section": "15"
}