(a) define the processes that enable all parties to meet their obligations;
(b) monitor performance by the Parties of their respective obligations under the contract or the Concession Agreement;
(c) manage differences through proactive relationship management;
(d) manage unanticipated developments and mitigating risks through efficient risk management; and
(e) resolve disputes in an expeditious manner, with minimal impact on service delivery.
(a) The Contract or Concession Agreement and its schedules;
(b) All financing agreements as well as financial models, where applicable;
(c) The names, roles and contact details of key individuals of both parties;
(d) Implementation plan during development, construction, operations and exit phases;
(e) Performance management plan;
(f) Risk management plan;
(g) Financial and contract administration plan;
(h) Relationship management and Contingency plan; and
(i) Contract Termination and Handover plan.
Section 19 • Tamil Nadu Infrastructure Development Board Regulations, 2013
19. Project Management Plan.
tamil-nadu-infrastructure-development-board-regulations-2013-sec-19.json
•
Section 19
{
"act_title": "Tamil Nadu Infrastructure Development Board Regulations, 2013",
"act_slug": "tamil-nadu-infrastructure-development-board-regulations-2013",
"section_label": "Section",
"section": {
"number": "19",
"title": "19. Project Management Plan.",
"chapter": null,
"content": "(a) define the processes that enable all parties to meet their obligations;\n(b) monitor performance by the Parties of their respective obligations under the contract or the Concession Agreement;\n(c) manage differences through proactive relationship management;\n(d) manage unanticipated developments and mitigating risks through efficient risk management; and\n(e) resolve disputes in an expeditious manner, with minimal impact on service delivery.\n(a) The Contract or Concession Agreement and its schedules;\n(b) All financing agreements as well as financial models, where applicable;\n(c) The names, roles and contact details of key individuals of both parties;\n(d) Implementation plan during development, construction, operations and exit phases;\n(e) Performance management plan;\n(f) Risk management plan;\n(g) Financial and contract administration plan;\n(h) Relationship management and Contingency plan; and\n(i) Contract Termination and Handover plan.",
"footnote": "",
"is_definition": false,
"sort_order": 18
},
"prev_section": "18",
"next_section": "20"
}